2013, 03-05 Permit: SW-13000140 Sewer SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW-13000140 Permit Issued Date: 03/05/2013
Project Description: SEWER CONNECTION
Project Name: S GREENACRES
Primary Contact: KALIN EXCAVATION Applicant: KALIN EXCAVATION
Phone: 509-954-9101 Address: 9229 E WOOLARD RD
COLBERT,WA 99005
Phone: 509-954-9101
Email:
SITE INFORMATION:
Site Address: 18015 E RIVERWAY AVE Owner: PATROUCH,JOHN C&JEAN
Parcel Number: 55071.0120 Address: 18015 E RIVERWAY AVE
GREENACRES,WA 99016-8522
Phone:
Assessor's Description: GRNACRS IRR DIST A PT OF B P BEG AT SWLY Email:
COR B P TH NW LY ALG WLY LN 300FT TH NELY
TO EL 422FT N OF SECOR TH S422FT TO
SECOR TH W TO POB
Inspection Area: : (509)-477-3675
Water District: Consolidated Irrigation Fire District: Spokane Valley Fire
District#19
Zoning: Land Area:2.17 Acre(s)
CONTRACTOR INFORMATION:
KALINE*0431B, Exp.03/31/2013
KALIN EXCAVATION
9229 E WOOLARD RD
COLBERT,WA 99005
509-954-9101
DETAILS:
Class Type Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
$125.00
FEE DETAIL:
Processing-Utilities $26.32
Utilities Permit $125.00
Total Fee: $151.32
CONDITIONS:
Inside Public Transit Benefit Area
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Possible FEMA Flood Zone
Possible Shoreline On Site
Possible Floodplain
Date Printed:03/05/2013 11:17:44 Project Coordinator:Kathy Cummings
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW-13000140 Permit Issued Date: 03/05/2013
CALL 1-800-424-5555 BEFORE YOU DIG—AT LEAST 2 WORKING DAYS IN ADVANCE.SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR& INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT(509)477-3604 FROM 8:30-5:00 MONDAY-FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30-MINUTE INSPECTION.ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED.SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed:03/05/2013 11:17:44 Project Coordinator:Kathy Cummings