2012, 09-06 Permit: SW-12002136 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW -12002136
Permit Issued Date:
09/06/2012
Expiration Date:
Project Description: SEWER CONNECTION
Project Name: CLEMENT
Permit Type: SEWER
Primary Contact: LARRY MILLER EXCAVATING
Applicant: LARRY MILLER EXCAVATING
Address: 7117 E RUTTER AVE
SPOKANE, WA 99212
Phone: 509-218-3335
Email:
SITE INFORMATION:
Site Address:
Parcel Number:
Subdivision:
Assessor's Description:
Inspection Area:
17916 E SPRAGUE AVE
55191.2102
CORBIN ADDITION
TR B SP90-647 AUD #9106130300 BEING A PTN
OF LT 4, BLK 26 CORBIN AND GREENACRES
Water District:
Consolidated Irrigation
District #19
Zoning: Land Area: 15600 Square Feet
Owner:
Address:
Phone:
Email:
JOHNSON, MORRIS F
17916 E SPRAGUE AVE
SPOKANE, WA 99216
509-499-6651
Fire District: Spokane Valley Fire
CONTRACTOR INFORMATION:
General Contractor
LARRYME918DR
LARRY MILLER EXCAVATING
7117 E RUTTER AVE
SPOKANE, WA 99212
509-218-3335
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
FEE DETAIL:
Processing - Utilities
Utilities Permit
Total Fee:
$125.00
$25.94
$125.00
$150.94
CONDITIONS:
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
Date Printed: 09/06/2012 09:55:45
Printed by: IIS APPPOOL\ASP.NET v4.0
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW -12002136 09/06/2012
Expiration Date:
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 09/06/2012 09:55:45
Printed by: IIS APPPOOL\ASP.NET v4.0