2014, 09-05 Permit: SW-14001313 SewerSPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -14001313
Permit Issued Date: 09/05/2014
Expiration Date: 09/05/2015
Project Description:
Project Name:
Primary Contact:
Phone:
SEWER CONNECTION
GREEN HAVEN PH 3
BOSAK, ANDREW/LEHMAN, SUSAN
509-924-4210
Applicant: BOSAK, ANDREW/LEHMAN, SUSAN
Address:
Phone:
Email:
18123 E SPRINGFIELD
GREENACRES, WA 99016
509-924-4210
SITE INFORMATION:
Site Address:
Parcel Number:
18123 E SPRINGFIELD CT
55184.3804
Assessor's Description: CANAL 1ST ADDITION LT 4 BLK 1
Inspection Area: : (509)-477-3675
Zoning:
Owner:
Address:
Phone:
Email:
Water District: Consolidated Irrigation
District #19
BOSAK, ANDREW/LEHMAN, SUSAN
18123 E SPRINGFIELD
GREENACRES, WA 99016
509-924-4210
Fire District: Spokane Valley Fire
Land Area: 12734 Square Feet
DETAILS:
Class Type
Quantity Unit Charge Value
SEWER SEWER CONNECTION
FEE DETAIL:
Processing - Utilities
Utilities Permit
Total Fee:
$26.64
$125.00
$151.64
1 $125.00 $125.00
$125.00
CONDITIONS:
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
SEWER PERMITS ARE VALID FOR ONE (1) YEAR FROM THE DATE OF ISSUANCE. FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER. ONE WORKING DAY NOTICE REQUIRED. PERMIT
ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 09/05/2014 09:27:14 Project Coordinator: Kathy Cummings