2012, 09-26 Permit: APR-2012-0063 Approach Permit Center
SCITYok
pane
Valley®
11703 E Sprague Ave Suite B3 Spokane Valley WA 99206
509.720-5240♦ Fax: 509.688.0037♦email: permitcenter@spokanevalley.org
APR-2012-0063 DE-APPROACH
PROJECT NAME: ISSUED: 09/26/2012
SITE ADDRESS: 505 N VERCLER RD SPOKANE VALLEY EXPIRES: 01/01/0001
PARCEL: 45153.2908
APPLICANT: ADAIR HOMES INC OWNER: RAU CONSTRUCTION, INC
1101 SE TECH CENTER DR STE 160 34 W 34TH AVE
VANCOUVER,WA 98683 SPOKANE,WA 99203
509-443-3444
GENERAL CONTRACTOR: ADAIR HOMES INC License: ADAIRH*262RZ
1101 SE TECH CENTER DR STE 160 Expires: 01/09/2013
VANCOUVER,WA 98683
509-443-3444
GENERAL CONTRACTOR: MUELLER JACKHAMMER INC. License: MUELLJ1060N6
3628 E 32ND AVE Expires: 08/22/2013
SPOKANE,WA 99223
509-534-7143
VALUATIONS: FEES: Paid Due
Approach $52.00 $0.00
Total: Total Due: $0.00
FIXTURES
Qtv Mechanical Fixtures Qty Plumbing Fixtures
Qty Electrical Fixtures
REQUIRED INSPECTIONS
Eng site visit/progress inspection Final Acceptance
CONDITIONS
* Saw cutting of existing curb to create an approach is not allowed within the
City's jurisdiction. Approach is to be inspected by the City's ROW Inspector prior to concrete placement. Approach to be
constructed per City Standard Plan R-111.
* The existing approach on Vercler is to be removed and replaced with curb/gutter, swale.
Printed:09-26-2012 10:49:36
Page 1 of 2
NOTICE
The ownership of a Spokane Valley Development Permit will inure to the property owner. The permit applicant, by definition, is the
property owner or an authorized agent of the property owner. It is the responsibility of the applicant/permitee that the use described on
the front of this permit complies with applicable codes and that required inspections are requested. Failure to request inspections as
listed below and obtain the necessary approvals before progressing beyond the point where inspections are required and may
necessitate removal of certain parts of the construction are at the applicant's/permittee's or property owner's expense.
At a minimum,the following inspections ARE REQUIRED by the Spokane Valley Municipal Code(SVMC):
FOOTING - when forms and reinforcements are in place and prior to placement of concrete-all structures, including manufactured
homes.
NOTE: This inspection includes review of the structures setback from property lines. Minimum setbacks are established by SVMC.
Curb lines and fence lines are not necessarily indicative of property lines. The responsibility to comply with applicable setback
provisions lies solely with the permitee-neither the City of Spokane Valley nor its authorized representatives assume any
responsibility for the verification or location of your property lines. Please verify their location prior to locating your structure.
Failure to properly locate the structure may require its relocation at the owner's/permittee's expense.
FOUNDATION-when forms and reinforcement are in place and prior to placement of concrete.
PLUMBING-after rough-in, before covering and final.
MECHANICAL-rough-in of piping, before covering, metal chimneys before concealment and final.
FRAMING -after all framing, bracing and blocking is in place, rough electrical, plumbing and mechanical systems are complete, and
prior to concealing.
FINAL-when complete and prior to occupancy and/or use; all permits require final inspection.
NOTE: In addition to inspection of the structure, this inspection includes review of site improvements (typically depicted on the
approved site plan) required by ordinance or as a condition of approval of this permit. Items such as installation of fire hydrants,
fire department access, on-site drainage (208'swales), road improvements,parking and landscaping are common requirements of
a permit/site plan which must be completed prior to final approval of a building or issuance of a Certificate of Occupancy.
MANUFACTURED HOMES-final inspection required when complete, stairs, handrails, skirting, etc. installed and prior to occupancy;
completed inspection record card must be available on site.
PLUMBING REVERSALS FOR SEWER CONNECTIONS-prior to cover
RIGHT-OF-WAY/APPROACH -prior to placement of concrete/asphalt or, if gravel approach, after completion.
In addition to the above, any plumbing or mechanical systems or material which would be concealed by framing, drywall, concrete, etc.,
must be inspected prior to cover. Check with the Building department for special inspections in conjunction with commercial projects.
State law RCW 19.122 requires that prior to any excavation the 'CALL BEFORE YOU DIG' center must be notified. Call 411 at least 3
working days in advance.
PERMIT EXPIRATION AND REFUNDS
Expirations:
Building or other permits (regulated under SVMC Chapter 24) shall expire by limitation and be declared void if a) work is not started
within 180 days of obtaining a permit, or b)work is abandoned for 180 days or more after beginning work, or c)after two years from the
date of permit issuance, regardless of whether the work is finished. If a permit is expired for time, a new permit may be obtained for
half the permit fee based on the value of the remainder of the work required to finish the original permit.
Right-of-way permits (regulated under SVMC Chapter 22) issued between April 1, and September 30, are valid for 30 days after the
date of issuance, with a one-time 30-day extension available. Right-of-way permits issued between October 1,and March 31, shall be
valid until the following April 30.
Refunds:
All refund requests must be made in writing by the original permitee to the Building Official no later than 180 days after the date of fee
payment. Full refunds will be granted for any permit issued in error. Rate of refund shall be as set forth in the City of Spokane Valley
Master Fee Schedule in effect at the time of permit application. A copy of this schedule is available at Permit Center and also available
for reference on the city website at: http://www.spokanevalley.org and search for"fees"
Owner/Agent � , _, Date: 5 - 2 /2_
Staff Approval Date:
soara`reit
Valle® 11703 E Sprague Ave Suite B-3 • Spokane Valley WA 99206
♦509.720.5240 ♦ Fax: 509.688.0037 •
Memorandum
Date: 9/27/2012
To: FINANCE DEPARTMENT
From: JENNA DAVIS
CC: DOUG POWELL
Re: REFUND-505 N VERCLER RD-APPROACH PERMIT
PROJECT NUMBER: APR-2012-0063
PROJECT ADDRESS: 505 N VERCLER RD
PROJECT TYPE: APPROACH PERMIT
REASON: Refunding permit fee amount of$52 as the permit was issued
in error.
REFUND TYPE: Per the currently adopted fee schedule,please refund the
applicant in the amount of$52. 2
GL ACCOUNT :
AUTHORIZED BY:
DATE: - - Z-E
ORIGINAL TO FINANCE AND COPY TO FILE WITH PAPERWORK
11707 E. Sprague
r QTkOF ,Spokane Valley WA 99206 Receipt Number: 201202377
P
S okan'e��
jValley® (509)921-1000
cityhall@spokanevalley.org
'' ( "1/4- 4.411(/'
Date: 10/08/2012 Cashier: MTurbak Payer/Payee ADAIR HOMES INC
Name: 1101 SE TECH CENTER DR STE
160
VANCOUVER WA 98683
Original Fee Amount Fee
Permit Number Parcel Fee Description p Amount Paid Balance
APR-2012-0063 45153.2908 Approach ($52.00) ($52.00) $0.00
505 N VERCLER RD 001 032000/3224000
SPOKANE VALLEY
RES APPROACH
Total: ($52.00) $0.00
Receipt# Receipt Previous Payment History Amount Permit# Parcel
Date Fee Description Paid
201202236 09/26/2012 Approach $52.00 APR-2012-0063 45153.2908
Total: $52.00