2012, 10-31 Permit: SW-12002468 Sewer SPOKANE COUNTY!,3UILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW-12002468 10/31/2012
Expiration Date:
Project Description: SEWER CONNECTION Primary Contact: VIETZKE EXCAVATING CO
Project Name: SUTTERS PH 3 Applicant: VIETZKE EXCAVATING CO
Permit Type: SEWER Address: 2011 S CRAIG RD
AIRWAY HEIGHTS,WA 99001
Phone: 509-244-9607
Email:
SITE INFORMATION:
Site Address: 807 S WARREN RD Owner: FORSTER,ANDREA L
Parcel Number: 45233.0105 Address: 1310 LAKEWOOD LN
BELLINGHAM,WA 98229
Subdivision: KRALIK SUBDIVISION Phone:
Assessor's Description: VERA KRALIK B146 L5 B1 Email:
Inspection Area:
Water District:Vera Fire District:Spokane Valley Fire
Irrigation District#15
Zoning: Land Area: 13680 Square Feet
CONTRACTOR INFORMATION:
General Contractor
VIETZEC121MA
VIETZKE EXCAVATING CO
2011 S CRAIG RD
AIRWAY HEIGHTS,WA 99001
509-244-9607
DETAILS:
Class Type Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
$125.00
FEE DETAIL:
Processing-Utilities $25.94
Utilities Permit $125.00
Total Fee: $150.94
CONDITIONS:
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG--AT LEAST 2 WORKING DAYS IN ADVANCE.SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR&INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
Date Printed: 10/31/2012 12:53:50 Printed by:115 APPPOOLWSP.NET v4.0
SPOKANE COL.NTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW-12002468 10/31/2012
Expiration Date:
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT(509)477-3604 FROM 8:30-5:00 MONDAY-FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30-MINUTE INSPECTION.ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION. _
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME.BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed:10/31/2012 12:53:50 Printed by:IIS APPPOOL\ASP.NET v4.0