2010, 09-15 Permit App: 10002861 Garage Project Number: 10002861 Inv: 1 Application Date: 9/15/2010 Page 1 of 2
THIS IS NOT A PERMIT
Penalties will be assessed for commencing work without a permit
Proiect Information:
Permit Use: NEW ATTACHED GARAGE-30 X 40 Contact: CARVETH,NORMAN W
Address: 1510 S WILBUR RD
C-S-Z: SPOKANE VALLEY,WA 99206-2710
Setbacks:Front Left: Right: Rear: Phone: (509)995-6143
Group Name:
Project Name:
Site Information:
Plat Key: 002694 Name: TWIN VIEW ADD District: Sout
Parcel Number: 45214.1323 Block: Lot:
SiteAddress: 1510 S WILBUR RD Owner:Name: CARVETH,NORMAN W
Address: 1510 S WILBUR RD
Location::CSV SPOKANE VALLEY,WA 99206-271
Zoning: R-3 SF Res District
Water District: 007 MODEL Hold: ❑
Area: 12,600 Sq Ft Width: 0 Depth: 0 Right Of Way(ft): 0
Nbr of Bldgs: 0 Nbr of Dwellings: 1
Review Information: �x
Review
Building Plan Review , Released By:
Originally Released: 9/15/2010 By: tmelbourn
Landuse/Zoning/HE Conditions Released By:
Originally Released: 9/13/2010 By: tschmidt
Operator: jmm Printed By: JD Print Date: 9/15/2010
Project Number: 10002861 Inv: 1 Application Date: 9/15/2010 Page 2 of 2
THIS IS NOT A PERMIT
Penalties will be assessed for commencing work without a permit
Building Permit
Contractor: OWNER Firm: OWNER
Phone: (000)000-0000
This Application: Total Project:
Description Grp Type Notes Su Ft Valuation Sq Ft Valuation
GAR WOOD U-1 VB PLAN 1,200 $22,800.00 1,200 $22,800.00
REVIEW
FEE
Totals: 1,200 $22,800.00 1,200 $22,800.00
Item Description Units Unit Desc Fee Amount
RESIDENTIAL PERMIT FEE 1 SELECT $363.25
WSBCC SURCHARGE 1 SELECT $4.50
SF PLNS RVW<7999 SQ FT 1 SELECT $145.30
Permit Total Fees: $513.05
Notes:
Payment Summary: �,�
Permit Type Fee Amount Invoice Amount Amount Paid Amount Owing
Building Permit $513.05 $513.05 $145.30 $367.75
$513.05 $513.05 $145.30 $367.75
Disclaimer:
Submittal of this application certifies the owner(or person(s)authorized by the owner)has both examined and finds the information
contained within to be true and correct,and agrees that all provisions of laws and/or regulations governing this type of work will be
complied with. Subsequent issuance of a permit shall not be construed to be a permit for,or an approval of,any violation of any of
the provisions of the code or of any other state or local laws or ordinances.
Signature:
Operator: jmm Printed By: JD Print Date: 9/15/2010
Permit Center PERMIT NUMBER:
SCITY OF 1 1703 E Sprague Ave, Suite B-3
pokane Spokane Valley,WA 99206
(509)688-0036 FAX: (509)688-0037 PERMIT FEE:
; Valley. www.spokanevalley.or7
Community Development t (C
Residential Construction, New Construction Accessory Bldg
Permit Application YC Addition/Remodel Deck
f] Other:
SITE ADDRESS: 1510 _ io I l b u e. PA) .
ASSESSORS PARCEL NO: LEGAL DESCRIPTION:
Building Owner: Contractor:
Name: W OY2 C RV G,Tk Name:
Address: 1510 i lb up__ go ,, Address:
City pQ A E VA OEN/ State:WA Zip:qu, City: State: Zip:
Phone: ..LJ0 cm5 _to 14 3 Fax: Phone: Fax:
..LJ l Contractor Lic No: Exp Date:
Contact Person City Business Lic.No:
Name: S4 ryy E
Phone:
Describe the scope of work in detail: Cost of Project: $ 'i� -4./(�O
PtD �u 6 Au ,E A CHCZ AAQA ILS xzta)
n TO EXIST WE I-100SE_
Proposed Use: i' 2r-►G£ FO2 PE,Q.SONI\\ USE ,
**************The following MUST be complete: (write N/A if not applicable)**********************
HEIGHT T9 PQM AK: DIM :NSIONS #OF STORIES: TOTAL HABITABLE SPACE:
MAIN FLOOR TO SQ. 2"1" FLOOR SQ. FTG: UNFIN BASEMENT SQ. FTG: IMPERVIOUS SURFACE
FTG: 1.� 517.F r, kVA /A AREA: OA
FINISHED BAS MENT GARAGE SQ. FTG: DECK/COV. TIO SQ. FTG: 30% SLOPES ON
SQ. FTG: KJ/A o(4-, laDD 5Q, FT. iJ/A PROPERTY: N
#OF BEDROOMS: CONS RUCTION TYPE: HEAT SOURCE: N �) SEWER OR SEPTIC? I f
O A
The permitee verifies,acknowledges and agrees by their signature that: 1) If this permit is for construction of or on a dwelling,the
dwelling is/will be served by potable water. 2) Ownership of this City of Spokane Valley Permit inure to the property owner. 3) The
signatory is the property owner or has permission to represent the property owner in this transaction. 4) All construction is to be done
in full compliance with the City of Spokane Valley Development Code. Referenced codes are available for review at the City of
Spokane Valley Permit Center. 5) This City of Spokane Valley Permit is not a permit or approval for any violation of federal,state or
local laws, codes or ordinances.6) Plans or additional information may be required to be submitted,and subsequently approved before
this application can be processed.
SIGNATURE: Jry eJJVS4t\ DATE: q. )3. 10
Method of Payment:
D Cash X Check 0 Mastercard 0 VISA
Bankcard#: Expires: VIN#:
Authorized Signature:
REVISED 2/15/07
RESIDENTIAL CHECK LIST DIRECTIONS:
Place a check mark in box next to each document required for complete submittal.
❑ SITE PLAN
O Property lines and dimensions o Setbacks to property lines
o Direction arrow pointing North and orientation to streets o Distance between buildings
o Proposed/existing buildings (footprint and dimensions) o Right of way/easement location &sizes
o Utilities, septic tank/drain field locations and distances o Driveway approach size and location
BUILDING PLANS (3 SETS) (minimum 1/8 inch scale or completely dimensioned)
❑ Elevations (Front/Rear/Sides)with roof peak and wall height including basement:
❑ Foundation Plan (crawlspace, basement or slab on grade):
o Footing sizes and locations o Supporting wood cripple walls or beams
❑ Perimeter concrete foundation wall sizes o Thickened concrete pads supporting
o Crawlspace ventilation beams or girder trusses
❑ Floor Plan of each level (finished or unfinished)with dimensions:
o Floor Joist direction, size and spacing ❑Window and door location and sizes
o Header, beam or concrete lintel sizes o Window well locations if applicable
❑ Brace wall panel locations o Room usage labels
o Water heater and furnace locations o Smoke detector locations
o Exhaust fan locations o Attic and crawl space access locations
o Deck or concrete patio sizes and locations o Fire Wall construction
❑ Roof Plan:
❑ Engineered truss direction and spacing ❑ Ridge, eave and valley lines
❑ Rafter and over frame direction, size and spacing o Beam and girder size and location
❑ Wall Section Detail including:
Roof
o Slope/roofing material/underlayment/ice dam protection o Truss or rafter size, spacing &connection
o Sheathing size and type ❑Attic insulation/air space baffle/ventilation
Ceiling
❑Joist size and spacing ❑ Size of ceiling gypsum wall board
Wall
❑ Height/top plate/stud size and spacing/sole plate o Siding/exterior house wrap/anchor bolts
❑ Exterior sheathing size and type o Insulation, vapor barrier, gypsum wall board
Floor
o Joist size and spacing o Sheathing or concrete floor size/insulation
Foundation Wall
o Concrete or Masonry unit width o Footing bottom to finished ground level depth
o Earth to wood separation distance ❑ Horizontal &vertical reinforcement if any
Footing
❑ Size o Reinforcement if any
Radon
o Passive system with 6mil vapor barrier o Active system with 6 mil vapor barrier
Miscellaneous Construction Details
❑ Deck:
❑ Floor plan/side view/dimensions o Footings/post/and beam size and locations
❑ Floor Joist/decking direction, size and spacing
O Stairway tread rise & run and nosing 0 Handrail/Guard height &spacing
PLANNING DEPT. IPPROVED
x
1
BY: /,,,---i _ -
Vo- di,Vc 1DATE: �i�
T
S
t
<..._ st ..... .
1
Flo'
MEW
j -41sTi TqG T
4 ' �1 Kouse. 9)_
. n4 y
L1
it II \ -0 \
1L
04
If-
i , tib cis
sic..
______.
150 . Wilbur Po.
SIPATIF Apr
For City Use pnly
• / I
PLUS Project Number cr 1
CITY Spokane
Valley° 11703 E Sprague Ave Suite B-3 • Spokane Valley WA 99206
509.688.0036 • Fax: 509.688.0037 • permitcenter@spokanevalley.org
As part of our on-going commitment to customer service during the review process of your project
application, we are providing you with a TARGET DATE for the initial technical application review. If for
any reason we cannot meet this date, we will contact you with a revised target date.
Your application review TARGET DATE is 1 t
The TARGET DATE is the date we estimate your project application will have had its initial technical
review. It is not the date for approval or permit issuance.
Tips for a Smoother Project Application Review
➢ Submit complete, accurate plans and documents.
Extra time may be required for re-submittals as project application reviewers work on multiple applications and it
may be several days before they can look at your new or revised information.
➢ Designate a specific contact person to communicate with the City.
While the person designated as the applicant's contact person with the City can be changed, one individual with the
expertise for dealing with reviewer comments would be the best choice for the entire review process.
➢ Call staff regarding the status of your project only after the target date shown at the top of the page.
Although you should be contacted on or by the target date,please feel free to contact us if you haven't heard from us
by your target date. Staff may contact you before the target date if the initial review is complete. By following this
procedure,you will save time and allow the reviewers to complete the work more expeditiously.
Steps in the Permit Process
1. Counter Complete. Your application has been accepted as counter complete. This means all of the required
documents, as indicated on your Pre-Application Checklist have been submitted or have been approved for deferred
submittal.This does not prevent technical staff from requesting additional information as a result of their technical review.
2. Quality Check. The next step in the process is a quality check to make sure that the application is reviewable and free
from substantive flaws that would prevent technical staff from completing the technical review once it is started. When
this step is complete, your application will be routed to the appropriate staff and remain in their review queue until it
comes up for review.
3. Technical Compliance. Once an application is administratively complete, it is routed to technical staff for compliance
review. Depending on the type of project, technical staff may include multiple reviewers. You should be contacted by
phone,fax, email,or mail by your TARGET DATE once the initial technical compliance review is complete.
4. Permit Issuance. When the technical compliance review of the application is complete, including any subsequent re-
submittals, each reviewer will approve their section of the application and route it to the Permit Center. When all sections
of the application are received, a Permit Specialist will process the application and contact the person specified on your
application for permit pick-up. Information regarding fees and pre-construction meetings (if required)will be provided by
the Permit Specialist at that time.
WHITE-APPLICANT PINK-BUILDING FILE REV 9/07