2012, 08-01 Permit: SW-12001873 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW -12001873
08/01/2012
Expiration Date:
Project Description: SEWER CONNECTION
Primary Contact: CROWN CONSTRUCTION LLC
Project Name: TRENTWOOD SEWER
Applicant CROWN CONSTRUCTION LLC
Permit Type: SEWER
Address. 1725 S GRAND
SPOKANE, WA 99203
Phone: 509-216-5995
Email:
SITE INFORMATION:
Site Address: 4126 N WOODLAWN RD
Owner: JACOBS, KEVIN L
Parcel Number: 45032.0112
Address: 4126 N WOODLAWN RD
SPOKANE VALLEY, WA 99216
Subdivision: STEVICKADDITION
Phone:
Assessors Description: STEVICK ADD Lit B1
Email:
Inspection Area:
Water District: Trentwood Fire District: Spokane Valley Fire
Irrigation District #3
Zoning:
Land Area: 10800 Square Feet
CONTRACTOR INFORMATION'
General Contractor
CROWNCL916RS
CROWN CONSTRUCTION LLC
1725 S GRAND
SPOKANE, WA 99203
509-2165995
DETAILS
Class Type
Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
$125.00
FEE DETAIL:
Processing - Utilities $25.94
Utilities Permit $125.00
Total Fee: $150.94
CONDITIONS:
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG—AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS
OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT
ALLOWS FORA 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
Date Printed 08/0112012 08:06:39
Printed by: IIS APPPOOLWSPAET v4.0
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW -12001873 08/01/2012
Expiration Date:
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed 08/0112012 08:06'.39 Printed by: IIS APPPOOLASP.NET Ac