2013, 08-26 Permit: SW-13001492 Sewer SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW-13001492 Permit Issued Date: 08/26/2013
Expiration Date: 08/26/2014
Project Description: SEWER CONNECTION
Project Name: WYNFIELD ADDN/LOT 7 BLOCK 1
Primary Contact: LNL HOMES LLC Applicant: LNL HOMES LLC
Phone: Address: 210 N UNIVERSITY RD#300
SPOKANE VALLEY,WA 99206
Phone:
Email:
SITE INFORMATION:
Site Address: 602 S SELKIRK RD Owner: LNL HOMES LLC
Parcel Number: 55191.0655 Address: 210 N UNIVERSITY RD#300
SPOKANE VALLEY,WA 99206
Phone:
Assessor's Description: CORBIN ADDITION TO GREENACRES LT 10 Email:
BLK 28 EXC W192FT< 11 BLK 28 EXC E192FT
&EXC PTN LT 10 DAF: BEG AT SE COR OF
W192FT LT 10,TH N 5FT TO POB,TH CONT
NOODEG 06MIN 16SDS W 117FT,TH S89DEG 4
Inspection Area: : (509)-477-3675
Water District: Consolidated Irrigation Fire District: Spokane Valley Fire
District#19
Zoning: Land Area: 3.55 Acre(s)
CONTRACTOR INFORMATION:
FOLSOE1994DO, Exp.04/20/2014
FOLSOM EXCAVATING INC
16701 E VALLEYWAY AVE VERADALE,WA 99037
509-891-1232
DETAILS:
Class Type Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
$125.00
FEE DETAIL:
Processing-Utilities $26.32
Utilities Permit $125.00
Total Fee: $151.32
CONDITIONS:
Inside Public Transit Benefit Area
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
CALL 1-800-424-5555 BEFORE YOU DIG—AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR&INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
SEWER PERMITS ARE VALID FOR ONE(1)YEAR FROM THE DATE OF ISSUANCE. FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT(509)477-3604 FROM 8:30-5:00 MONDAY-FRIDAY PRIOR TO COVER.ONE WORKING DAY NOTICE REQUIRED. PERMIT
ALLOWS FOR A 30-MINUTE INSPECTION.ADDITIONAL INSPECTION FEES APPLY AFTER 30 MINUTES.
Date Printed:08/26/2013 12:45:01 Project Coordinator:Julie Shatto
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW-13001492 Permit Issued Date: 08/26/2013
Expiration Date: 08/26/2014
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED.SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE. _
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed:08/26/2013 12:45:01 Project Coordinator:Julie Shatto