2012, 10-25 Permit: SW-12002441 Sewer SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW-12002441 10/25/2012
Expiration Date:
Project Description: SEWER REPAIR Primary Contact: ROTO ROOTER
Project Name: OPPORTUNITY TERRACE Applicant: ROTO ROOTER
Permit Type: SEWER Address: 6214 E ALKI AVE
SPOKANE VALLEY,WA 99212
Phone: 509-484-6937
Email:
SITE INFORMATION:
Site Address: 1212 S WOODLAWN RD Owner: KROLL, RODNEY H
Parcel Number: 45223.2201 Address: 1212 S WOODLAWN RD
SPOKANE,WA 99216-0534
Subdivision: OPPRTUNITY TERRACE Phone:
ESTATES
Assessor's Description: OPPORTUNITY TERRACE ESTATES L1 B5 Email:
Inspection Area:
Water District:Vera Fire District:Spokane Valley Fire
Irrigation District#15
Zoning: Land Area: 12060 Square Feet
CONTRACTOR INFORMATION:
General Contractor
ROTOR**931 BB
ROTO ROOTER
6214 E ALKI AVE
SPOKANE VALLEY,WA 99212
509-484-6937
DETAILS:
Class Type Quantity Unit Charge Value
SEWER SEWER REPAIR 1 $125.00 $125.00
$125.00
FEE DETAIL:
Processing-Utilities $25.94
Utilities Permit $125.00
Total Fee: $150.94
CONDITIONS:
Inside Public Transit Benefit Area
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
CALL 1-800-424-5555 BEFORE YOU DIG--AT LEAST 2 WORKING DAYS IN ADVANCE.SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR&INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
Date Printed:10/25/2012 09:32:30 Printed by:IIS APPPOOLWSP.NET v4.0
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT *
Permit Issued Date:
Application Number: SW-12002441 10/25/2012
Expiration Date:
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT(509)477-3604 FROM 8:30-5:00 MONDAY-FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED.PERMIT ALLOWS FOR A 30-MINUTE INSPECTION.ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED.SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME.BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.