16-092.01 Cameron Reilly: Pines & Mirabeau Pkwy Intersection (4, -o'i2O
Spokane
CHANGE ORDER NO: 1
DEPARTMENT OF PUBLIC WORKS CONSTRUCTION CONTRACT NO: 16-092
PROJECT: Pines Road(SR 27)&Mirabeau Parkway Intersection Project CONTRACT DATE: 7/22/2016
PRIME CONTRACTOR: Cameron-Reilly.LLC CIP NO: 238
DESCRIPTION OF CHANGES
This Change Order provides payment for the following two items:
1)Aluminum housing and reflective back plates.
2) Installation of a City furnished Wavetronix Smart Sensor Advance unit and associated equipment.
Item No. Description Unit Quantity Unit Price Total
Force Account Furnish Aluminum Signal Heads and
CO-1.1 Back Plates EST 1 $ 1,436.51 $ 1,436.51
Install Wavetronix Advance 200-V Smartsensor&
CO-1.2 Associated equipment LS 1 840.67 840.67
2,277.18
8.7%Sales Tax $ 198.11
Total Amount of this Change Order(incl.Tax): $ 2,475.29
PHYSICAL COMPLETION
Original Contract Working Days: 15 Revision By This Change Order:
Revisions by Prior Change Orders: 0 Total Revised Contract Working
CONTRACT AMOUNT
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT:
ORIGINAL TOTAL CONTRACT AMOUNT Incl Tax) $ 204,158.17
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT $ 0.00
TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 204,158.17
NET THIS CHANGE ORDER $ 2,475.29
—.—
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 206,633.46
CONTRACTOR ACCEPTANCE: a> DATE: b - 2 'Q"
The contractor hereby accepts this ad) ent under the terms of Section 1-04.4 of the original contract.
RECOMMENDED BY: � 7 DATE: g/0./6,
Project Manager
APPROVED BY: Kt_ ZDATE: e/Z51/C.orks Director
APPROVED BY: /v/ DATE: +I
((( City Manager
ATTACHMENTS:
Distribution: ORIGINAL TO: City of Spokane Valley Clerk's Office
COPIES TO: Contractor,PW Project File,Project Inspector,Finance Department
COSI./Form 9/5'7014
0°/\%1 Public Works Department
Spokane
Capital Improvement Program
alley. 11707 E Sprague Ave Suite 106 ♦ Spokane Valley WA 99206
40,0509.921.1000 ♦ Fax: 509.688-0261 • cityhall®spokanevalley.org
Change Order Memorandum
Date: August 10, 2016
To: Eric Guth Through: Steve Worle ,
From: Craig Aldworth cjA- f
Re: Change Order 1 —Pines Rd (SR 27)& Mirabeau Parkway Intersection Project, CIP 0238
Budget Account No. 311.000.238.595.30.63.00 Cameron-Reilly Contract 16-092 •O
This Change Order provides payment to the Contractor for the following two items:
A)The project is installing a signal on a State Highway, and WSDOT prefers aluminum vehicle signal
head housings with aluminum reflective back plates. The project was bid with polycarbonate vehicle
signal head housings and reflective back plates. The additional cost estimate for changing to the
aluminum housing and back plates including tax is $1,561.49.
B)When the existing northbound vehicle detection loops, installed in 1999,were tested this spring by
WSDOT,they were electrically viable,these loops were included in the project design. They were
retested after the project started and found to be defective. The northbound curbside lane vehicle
detection loop(and the other loop lead)is under a concrete pavement slab that was installed to protect
an AT&T Fiber Optic line that may lie directly under the defective loops. Removing the concrete
pavement panel to replace the loops would impact the travelling public, increase project cost and risk
damaging the fiber optic line. Therefore, a Wavetronix Smart Sensor Advance unit will be purchased
by the City and installed by the Contractor. The advance detection unit installation cost is $913.81.
The total Change order cost is $2,475.29.
The cost for the City to purchase the Wavetronix Smart Sensor Advance unit and associated equipment is
$8,096.52. The total increase in project cost(including the change order cost and the cost of the City
purchased Wavetronix equipment)is$10,571.82. This project is 80%funded by Transportation
Improvement Board with a 20%match is funded by Spokane Valley Street Preservation Fund 303. There
are sufficient funds in the project budget to cover these costs.
Original Contract amount= $ 204,158.17
Previous Change Order Cost= $ 0.00
Change Order#1 Cost= $ 2,475.29
Project Cost including Change Order#1 = $ 206,633.46
15% of Original Contract amount= $30,623.73
Max Public Works Director Contract authority= $30,623.73
Change Order Cost to date = $2,475.29
Remaining P.W. Director Contract Authority after CO#1 $28,148.44
Cc: Finance Department, Clerk's Office
Scrn Public Works Department
eCapital Improvement Program
.0,0VaIle y
y 11707 E Sprague Ave Suite 106 ♦ Spokane Valley WA 99206
509.921.1000 ♦ Fax: 509.921.1008 ♦ cityhall@spokanevalley.org
Change Order Memo
Date: August 10,2016
By: Craig Aldworth
Re: Change Order 1
Pines Rd (SR27)& Mirabeau Parkway Project, CIP 0238
1. Describe the Change This Change Order pays for A) aluminum vehicle signal head
housings and back plates; and B) installation of Wavetronix Smart Sensor Advance unit.
2. Evolution of the Change
A) Since the project is installing a signal on a State Highway, and the City will contract
with the WSDOT Eastern Region Signal Shop to maintain the signal, the system
components have been selected to match WSDOT Eastern Region preferences.
WSDOT prefers aluminum vehicle signal head housings with aluminum reflective
back plates. The project was bid with polycarbonate vehicle signal head housings
and reflective back plates.
B) When the existing northbound vehicle detection loops, installed in 1999, were tested
this spring by WSDOT, they were electrically viable, so they were included in the
project design. They were retested after the project started and found to be
defective. The northbound curbside lane vehicle detection loop (and the other loop
lead) is under a concrete pavement panel that was installed to protect an AT&T Fiber
Optic line that may lie directly under the defective loops. Removing the PCC panel
to replace the loops would impact the travelling public, increase project cost and risk
damaging the fiber optic line. Staff prefers to purchase a Wavetronix Smart Sensor
Advance unit to be installed by the Contractor.
3. Payment
A) The estimate of$1,561.49 increase in cost for aluminum over the bid polycarbonate
components is an estimate. Actual payment will be based on the invoice difference
between polycarbonate components and aluminum obtained from the Contractor's
supplier.
B) The attached spreadsheet estimates a $913.81 cost for installing the Wavetronix Smart
Sensor Advance unit. The Change Order Cost is $2,475.29, and the cost of the City
purchased Wavetronix Smart Sensor Advance unit including tax is $8,096.52. The total
cost of the additional work to the project is $10,571.82.
4. Time An additional 0.25 day of time was granted.
5. Prior Approval
The Change Order was verbally approved by the acting Public Works Director 8/9/2016.
6. Attachments
CO 1.1 Western Systems polycarbonate quote and Colvico Email
CO 1.2 Force Account Estimate of Wavetronix Smart Sensor Advance installation cost
P:\Public Works\Capital Projects\Street Projects\0238-Pines Road(SR-27)Mirabeau Pkwy Intersection\Construction Admin\Change Orders\CO Cost Estimate Spreadsheet.xls
•
Spol�an�""` C.Aldworth
Valliey 8/4/2016
Pines Rd (SR27) & Mirabeau Parkway Intersection Project
CIP 0238
CO 1 Cost Estimate
Item Description Quantity Unit Unit Cost(Incl Tax) Total
CO 1.1 Additional cost for Aluminum Vehicle Signal Head and
Reflective Backplates 1 LS $ 1,561.49 $1,561.49
CO-1.2 Force Acount cost to Install Advance Detector 1 ES l $ 913.81 $ 913.81
CO 1 Total $2,475.30
P:\Public Works\Capital Projects\Street Projects\0238-Pines Road(SR-27)Mirabeau Pkwy Intersection\Construction Admin\Change Orders\CO Cost Estimate Spreadsheet.xls
��1fpp C.Aldworth
it Tovak ss��aii�. 8/4/2016
y
Pines Rd (SR27) & Mirabeau Parkway Intersection Project
CIP 0238
CO 1.1 Spreadsheet For Furnishing Aluminum Signal Head Housing and Aluminum Reflector Back Plates
COLVICO SUB CONTRACTOR LABOR
Rate incl. FA Labor Total Labor
Trade Name No.of Hours fringe FICA/FUTA/SUTP L&I' Rate 29%P&O Rate Total Labor Cost
Total Sub Labor Cost 0.00
COLVICO SUB CONTRACTOR EQUIPMENT
Equipment Item No.Units Unit Qty Unit Type Unit Cost 21%P&O Total Total Equipment
Sub Eq Total Cost 0.00
Total Equipment
Equipment Item No.Units Unit Qty Unit Type Unit Cost 21%P&O Cost
Additional Cost for Aluminum Vehicle Signal Head Housing 1 LS 1060 222.60 1282.60
and Aluminum Reflective Back Plates
Sub Material Total 1,282.60
SubContractor Total 1,282.60
12%Prime Markup 153.91
Total Cost 1,436.51
8.7%Tax 124.98
Total 1,561.49
P:\Public Works\Capital Projects\Street Projects\0238-Pines Road(SR-27)Mirabeau Pkwy Intersection\Construction Admin\Change Orders\CO Cost Estimate Spreadsheet.xls
•
C.Aldworth
cilinikb m � 8/4/2016
.Valley. Pines Rd (SR27) & Mirabeau Parkway Intersection Project
CIP 0238
CO 1.2 Force Account Estimate Spreadsheet For Installing Wavetronics Advance Detector
COLVICO SUB CONTRACTOR LABOR
Rate incl. FA Labor Total Labor
Trade Name No.of Hours fringe FICA/FUTA/SUTP L&1' Rate 29%P&O Rate Total Labor Cost
Colvico Travis Ludlam,Electrician 3 52.60 5.09 2.18 59.87 17.36 77.23 231.70
Colvico Laborer 3 40.00 4.64 2.18 46.82 13.58 60.40 181.19
Total Sub Labor Cost 412.89
COLVICO SUB CONTRACTOR EQUIPMENT
Equipment Item No.Units Unit Qty Unit Type Unit Cost 21%P&O Total Total Equipment
Ford F-250 PU 3 Hr 29.70 89.1 18.71 107.81 107.81
Line Truck 3 Hr 30.00 90 18.90 108.90 108.90
Sub Eq Total Cost 216.71
COLVICO SUB CONTRACTOR MATERIAL
Total Candle Total Equipment
Equipment Item No.Units Unit Qty Unit Type Unit Cost 21%P&O Cost Cost
Misc Mounting Hardware 1 LS 100 21.00 121.00 121.00
Sub Material Total 121.00
SubContractor Total 750.60
12%Prime Markup 90.07
Total Force Account Cost 840.67
8.7%Tax 73.14
Total 913.81
0238-Pines RD Mirabeau Parkway Intersection
All Activity as of Aug 24 2016
Project Prior Life
Original Adjusted Years 2015 2016 To Date Available
REVENUES Budget Budget Actual Actual Actual Actual Encumbered Funds
TIB 357,069.00 357,069.00 0.00 0.00 24,578.30 24,578.30 0.00 332,490.70
302 89,269.00 89,269.00 0.00 0.00 6,768.40 6,768.40 0.00 82,500.60
Total Revenue 446,338.00 446,338.00 0.00 0.00 31,346.70 31,346.70 0.00 414,991.30
Original Adjusted Prior 2015 2016 Life Available
EXPENDITURES Budget Budget Years Actual Actual To Date Encumbered Funds
Preliminary Engineering
Salaries&Wages 5,000.00 5,000.00 0.00 0.00 10,534.63 10,534.63 0.00 -5,534.63
Overtime 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Employee Benefits 1,750.00 1,750.00 0.00 0.00 3,850.96 3,850.96 0.00 -2,100.96
Employee Benefits 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Engineering&Architectural 35,337.00 35,337.00 0.00 0.00 35,883.98 35,883.98 673.02 -1,220.00
Prof.Svcs-Survey 0.00 0.00 0.00 0.00 4,298.75 4,298.75 7,801.25 -12,100.00
Prof.Svcs.-Geotech 0.00 0.00 0.00 0.00 2,512.72 2,512.72 487.28 -3,000.00
Advertising 1,000.00 1,000.00 0.00 0.00 822.64 822.64 0.00 177.36
Printing&Binding 500.00 500.00 0.00 0.00 0.00 0.00 0.00 500.00
Miscellaneous Services 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PE Contingency 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Prelim.Engineering 43,587.00 43,587.00 0.00 0.00 57,903.68 57,903.68 8,961.55 -23,278.23
Right of Way
ROW Acquisition 0.00 0.00 0.00 594.00 594.00 0.00 -594.00
Total Right of Way 0.00 0.00 0.00 0.00 594.00 594.00 0.00 -594.00
Construction
Salaries&Wages 3,000.00 3,000.00 0.00 0.00 5,454.59 5,454.59 0.00 -2,454.59
Overtime 0.00 0.00 0.00 0.00 744.15 744.15 0.00 -744.15
Employee Benefits 1,050.00 1,050.00 0.00 0.00 1,998.97 1,998.97 0.00 -948.97
Employee Benefits 0.00 0.00 0.00 0.00 27.07 27.07 0.00 -27.07
Prof.Svcs.Mat.Testing 2,000.00 2,000.00 0.00 0.00 0.00 0.00 0.00 2,000.00
Prof.Svcs.-Consulting 37,537.00 37,537.00 0.00 0.00 0.00 0.00 0.00 37,537.00
Advertising 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Printing&Binding 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Construction 359,164.00 359,164.00 0.00 0.00 6,271.99 6,271.99 29,867.50 323,024.51
Traffic Control Devices 0.00 0.00 0.00 1,461.80 1,461.80 0.00 -1,461.80
Contingency 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Construction 402,751.00 402,751.00 0.00 0.00 15,958.57 15,958.57 29,867.50 356,924.93
Total Expenditures 446,338.00 446,338.00 0.00 0.00 74,456.25 74,456.25 38,829.05 333,052.70
�[fIk 14���
Pines RD Mirabeau Parkway Intersection - #0238
.000 Val leyAug 24 2016
Expenditure Accounts I Budget
PE Description Current I Change New
303.000.238.595.10.10.00 Salaries &Wages 5,000 5,535 10,535
303.000.238.595.10.10.99 Overtime - -
303.000.238.595.10.20.00 Employee Benefits 1,750 2,101 3,851
303.000.238.595.10.20.99 Employee Benefits - -
303.000.238.595.10.41.02 Engineering &Architectural 35,337 35,337
303.000.238.595.10.41.06 Prof. Svcs -Survey - 6,000 6,000
303.000.238.595.10.41.07 Prof. Svcs. -Geotech - 3,000 3,000
303.000.238.595.10.41.17 Advertising 1,000 (177) 823
303.000.238.595.10.49.03 Printing & Binding 500 (500) -
303.000.238.595.10.49.06 Miscellaneous Services - -
303.000.238.595.10.99.99 PE Contingency - - 1
I Sub Total: 43,587 15,959 59,546
RW Description Current Change New
303.000.238.595.20.61.01 ROW Acquisition - 2,500 2,500
I Sub Total: - 2,500 2,500
CN Description Current I Change New
303.000.238.595.64.10.00 Salaries &Wages 3,000 3,500 6,500
303.000.238.595.64.10.99 Overtime - 1,500 1,500
303.000.238.595.64.20.00 Employee Benefits 1,050 1,000 2,050
303.000.238.595.64.20.99 Employee Benefits - -
303.000.238.595.64.41.08 Prof. Svcs. Mat. Testing 2,000 1,105 3,105
303.000.238.595.64.41.10 Prof. Svcs. -Consulting 37,537 (32,537) 5,000
303.000.238.595.64.41.17 Advertising - -
303.000.238.595.64.49.03 Printing & Binding - -
303.000.238.595.64.63.00 Construction 359,164 (152,531) 206,633
303.000.238.595.64.63.03 Traffic Control Devices - 103,185 103,185
303.000.238.595.64.99.99 Contingency - 335 335
3...................
Sub Total: 402,751 (7, . , ) 328,308
Project Total: I 446,338 , 55,984) 390,354
s12'°'$-4E: r..,T Comet /06
1 i - U O f3c1 0667r
Funding Accounts Budget
PE Description Current I Change New
0334.0380 TIB 357,069 (55,984) 301,085
0397.3020 302 89,269 89,269
3
I Project Total: 446,338 (55,984) 390,354
APPROVALS
Project Manager Date Sr Capital Proj Eng Date
9
Public Works Director Date Finance Director Date
3 Accounting will look up BARS code according to Description
Notes
8/24/2016 Budget Adjustment including Change Order 1