16-077.01 Inland Asphalt: Broadway Street Preservation . • r Spo°F]�ane I�`alley CHANGE ORDER NO: 1 DEPARTMENT OF PUBLIC WORKS CONSTRUCTION CONTRACT NO: 16-077.Q PROJECT: Broadway Street Preservation Project CONTRACT DATE: 6/23/2016 PRIME CONTRACTOR: Inland Asphalt Company CIP NO: 233 DESCRIPTION OF CHANGES This Change Order pertains to Bid Schedule: A, Bid Items 116 and 117 The attached General Special Provision 5-04.3(7)A allows the Contractor to submit a Job Mix formula for Hot Mix Paving directly to the Engineer for approval. This change results in a reduction to the Contract amount as noted herein. Item No. Description Unit Quantity Unit Price Total CO 1 Adoption of GSP 5-04.3(7)A LS 1 $ 0.00 $ 0.00 Total Amount of this Change Order(incl.Tax): $ 0.00 PHYSICAL COMPLETION Original Contract Working Days: 15 Revision By This Change Order: 0 Revisions by Prior Change Orders: 0 Total Revised Contract Working Days: 15 CONTRACT AMOUNT THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT: ORIGINAL TOTAL CONTRACT AMOUNT $ 424,424.24 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT(through CO#, $ 0.00 TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 424,424.24 NET THIS CHANGE ORDERf 0.00 TOTAL CONTRACT AMOUNT INCLUDING Ti# ( C� • ,j ri : I � $ 424,424.24 CONTRACTOR ACCEPTANCE: •1 /ti DATE: -7/i/C,, G, I `' r The contractor hereby accepts this adjustment under t terms if Section 1-04.4 of the original contract. RECOMMENDED BY: � DATE: 6 .,j) •/(p P Mana r APPROVED BY: DATE: 7/ /f Public Works Director APPROVED BY: 4,4 DATE: City Manager ATTACHMENTS: Distribution: ORIGINAL TO: City of Spokane Valley Clerk's Office COPIES TO: Contractor,PW Project File,Project Inspector,Finance Department COSV Form yf5/2014 Scn'Y of Public Works Department pokane Capital Improvement Program .0,0Valley 11707 E Sprague Ave Suite 106 ♦ Spokane Valley WA 99206 509.921.1000 ♦ Fax: 509.688-0261 • cityhall®spokanevalley.org Change Order 1 Memorandum Date: July 5, 2016 To: Eric Guth, Public Works Director From: Craig Aldworth, Pr. Engr. c./4- h ugh: Steve M.Worley, CIP Manager Re: Change Order#1 for Broadway Street Pr ervation Project, CIP#0233 Budget Account No.: 311.000.233.595.30.63.00 Inland Asphalt Co. Contract No. 16-077.01 This change order adopts the attached General Special Provision 5-04.3(7)A. This GSP allows the Contractor to submit an HMA Job Mix Formula directly to the Engineer for approval. The total estimated cost (including sales tax) for this Change Order work is $0.00 , paid for by Fund 311. There are sufficient funds in the project budget to cover these costs. Original Contract Amount: $424,424.24 Previous Change Order Cost: $0.00 Change Order#1 Cost: $0.00 Project Cost including Change Order#1: $424,424.24 15% of Original Contract amount: $63,663.64 Max Public Works Director Contract authority: $63,663.64 ($75,000 or 15% of original contract amount, whichever is less) Change Order Cost to date: $0.00 Remaining P.W. Director Contract Authority after CO#1: $63,663.64 cc: Finance Department Clerk's office SCOP 5-04.3 Construction Requirements 5-04.3(7) Preparation of Aggregates 5-04.3(7)A Mix Design 5-04.3(7)A1 General (***** ) The first two paragraphs of Section 5-04.3(7)A1 are deleted and replaced with the following: An approved mix design is required for all HMA paving. An approved mix design, must be either 1) listed on the Qualified Products List(QPL); or 2) submitted with a Mix Design Verification report prepared by an Independent Laboratory satisfying WSDOT accreditation standards. The Contractor shall develop a mix design prior to the initial production of HMA and no more than 3 months prior to submitting for QPL evaluation. The mix design shall be developed in accordance with WSDOT Standard Operating Procedure 732 and meet the requirements of Sections 9-03.8(2) and 9-03.8(6). To add a mix design to the QPL, it shall be submitted by the Contractor to the WSDOT State Materials Laboratory on WSDOT Form 350-042EF. If the mix design is approved it will be listed on the QPL for up to 24 consecutive months. After a mix design has been on the QPL for 12 months the listing will be extended provided the Contractor submits a certification letter to the Qualified Products Engineer verifying that the aggregate and asphalt binder have not changed. The Contractor may submit the certification one month prior to expiration of the mix design approval. Within 7 calendar days of receipt of the Contractor's certification the QPL will be updated. The maximum duration for approval of a mix design and listing on the QPL will be 24 months from the date of initial approval or as approved by the Engineer. If the Contractor requests approval by submitting his Mix Design to the Engineer, the Mix Design Verification report shall directly reference the Mix Number being submitted. The Contractor shall submit Mix Design with 20 percent RAP or less by total weight of HMA. . y Spoisne CITY OF Public Works Department Capital Improvement Program Valley 11707 E Sprague Ave Suite 106 ♦ Spokane Valley WA 99206 509.921.1000 ♦ Fax: 509.921.1008 ♦ cityhall@spokanevalley.org Change Order Memo Date: June 30, 2016 By: Craig Aldworth Re: Change Order 1 Broadway Street Preservation Project, CIP 0233 1. Describe the Change This change order adopts the attached General Special Provision 5-04.3(7)A. This GSP allows the Contractor to submit an HMA Job Mix Formula directly to the Engineer for approval. 2. Evolution of the Change The 2016 WSDOT Standard Specifications revised the HMA Section concerning submittals of Job Mix Formulas. Under the new procedure only those Job Mix Formulas that had been verified by the State Laboratory and placed on the Qualified Products List (QPL) could be approved by the Local Agency. The City of Spokane and Spokane both waived this new requirement to allow local Contractors and independent testing laboratories time to adjust to the new requirement. The Change will allow a local independent testing lab to provide a job mix formula for the submitted Job Mix formula. 3. Payment This is a no cost change order. 4. Time No additional time was granted or taken away. 5. Prior Approval The Change Order was approved by the acting Public Works Director on 6. Attachments General Special Provision 5-04.3(7)A.