16-066.01 Inland Asphalt: McDonald Road Diet e '
Spode
.000Valley
CHANGE ORDER NO: 1
DEPARTMENT OF PUBLIC WORKS CONSTRUCTION CONTRACT NO: 16-066 t 01
PROJECT: McDonald Road Diet-CIP#221 CONTRACT DATE: 7/19/2016
PRIME CONTRACTOR: Inland Asphalt CIP NO: 221
DESCRIPTION OF CHANGES
This change order revises the lump sum bid item TRAFFIC SIGNAL SYSTEM MODIFICATIONS because the City is now
furnishing the Opticom multimode phase selector and detectors.
Item No. Description Unit Quantity Unit Price Total
327 TRAFFIC SIGNAL SYSTEM MODIFICATIONS L.S. 1 $ (63,000.00) $ (63,000.00)
338 TRAFFIC SIGNAL SYSTEM MODIFICATIONS-REV L.S. 1 $ 58,876.00 $ 58,876.00
Total Amount of this Change Order(incl.Tax): $ (4,124.00)
PHYSICAL COMPLETION
Original Contract Working Days: 60 Revision By This Change Order: 0
Revisions by Prior Change Orders: 0 Total Revised Contract Working Days: 60
CONTRACT AMOUNT
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT:
ORIGINAL TOTAL CONTRACT AMOUNT $ 1,728,000.00
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT $ 0.00
TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 1,728,000.00
NET THIS CHANGE ORDER $ (4,124.00)
TOTAL CONTRACT AMOUNT INCLUD G T t$C � jt„S:R $ 1,723,876.00
CONTRACTOR ACCEPTANCE: /4Y, DATE:
The contractor hereby accepts this adjustment and-f t:terms of Section 1-04.4 of the original contract.
RECOMMENDED BY: ffjk(,(,4 DATE: 1( (.,
Project Manager I It
APPROVED BY: � �� !G�1 DATE: M 7 //
t3ublic Works Director
Y
APPROVED BY: /t/ .,L( DATE:
City Manager
ATTACHMENTS: N/A
Distribution: ORIGINAL TO: City of Spokane Valley Clerk's Office
COPIES TO: Contractor,PW Project File,Project Inspector,Finance Department
COSV Form 9/5/2014
L -
SC °F Public Works Department
poiianeCapital Improvement Program
4 so IS*Valley 11707 E Sprague Ave Suite 106 ♦ Spokane Valley WA 99206
509.921.1000 ♦ Fax: 509.688-0261 • cityhall@spokanevalley.org
Change Order Memorandum
Date: 8/9/16
To: Eric Guth, Public Works Director
From: Erica K. Amsden E Through: Steve M.Worley, CIP Mana
Re: Change Order#1 for McDonald Road Diet, CIP#0221
Budget Account No.303.000.221.595.30.63.00
•So .
Inland Asphalt Company Contract No. 16-066.01
The City of Spokane Valley is furnishing several proprietary items for the Traffic Signal System
Modifications bid item. Our traffic department mistakenly ordered additional equipment that was
intended to be furnished by the contractor. We have an approved Public Interest Finding that
allows the City to furnish these items. This change order reduces the Traffic Signal System
Modifications lump sum bid item by the invoiced amount that was paid for the additional
equipment.
The total estimated cost (including sales tax) for this Change Order work is -$4,124.00. There
are no increases to the construction cost for this item.
Original Contract Amount: $1,728,000
Previous Change Order Cost: $0
Change Order#1 Cost: -$4,124
Project Cost including Change Order#1: $1,723,876.00
15% of Original Contract amount: $259,200 •
Max Public Works Director Contract authority: $75,000
Change Order Cost to date: -$4,124
Remaining P.W. Director Contract Authority after CO#1:
75000
cc: Finance Department
Clerk's office
ECOP
•
Hughbanks, Al (Inland Asphalt)
From: Erica Amsden [eamsden@spokanevalley.org]
Sent: Wednesday, July 20,2016 10:28 AM
To: Benson, Dan(Inland Asphalt)
Cc: Hughbanks, Al (Inland Asphalt);Tibbits,Jamie(Inland Asphalt); 'Tom Baldwin'
Subject: McDonald Road Diet Change Order 1
Attachments: Opticon Invoice.pdf
Good Morning Dan,
The Traffic Signal System Modification bid item included furnishing and installation of a multimode phase selector and
detectors. The City of Spokane Valley has mistakenly ordered these items with the other equipment we are furnishing. The City
proposes reducing the Traffic Signal System Modifications lump sum total cost by the cost of these materials and furnishing the
items to Colvico. This change would reduce the traffic signal modification bid item by $4,124,the amount of the attached
invoice. The new lump sum Traffic Signal System Modifications item would then be$58,876.
Please let me know if you agree with this proposed change.
Thanks,
Erica K. Amsden, P.E.
City of Spokane Valley
509-720-5012
eamsden@ spokanevallev.oro
1
P
Advanced STT r
F :
r. Traffic f o� c 'r
.s?_i-)ai Traffic iC:
Products
Opticom Preemption System - '' It's About Time
Agency City of Spokane Valley Date 6/21/2016 1
Contact Ryan Kipp Phone No. _
Address Fax No.
City State _f Zip Code
Project McDonald Rd Opticom Quote County
ATP Sales Rep,Mike Singson
.r..
it 'o•e 10. 'escr . on 1 nr -rice • ce
1 764 Opticom 764,4 Channel MultiMode Phase Selector . $2,751.00 $2,751.00.
4 711 Opticom 711 One Channel,One Dir.Detector $425.60 $1,702.40
I TRADE IN Any Phase Selector-Vintage,Manufacturer,Out-of-warrany 25% 468735
SUBTOTAL $3,766.65
Sales Tax 8.70% 330.04
WSDOE Fee _ 0.74% $2$
TOTAL $4;4 :134
This quote will he honored for 90 days. 54123.56
Advanced Traffic Products does not provide installation service.
For Installation costs you will need to contact a contractor or government agency for a quote
This price does not include taxes.