2015, 03-16 Permit: SW-15000164 Sewer SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW-15000164 Permit Issued Date: 03/16/2015
Expiration Date: 03/16/2016
Project Description: ABANDONMENT OF SEWER CONNECTION
Project Name: CARNAHAN
Primary Contact: HARRY JOHNSON PLUMBING/EXCAVATION INC Applicant: HARRY JOHNSON
PLUMBING/EXCAVATION INC
Phone: 509-520-9308 Address: 605 FOSTER ROAD
WALLA WALLA,WA 99362
Phone: 509-520-9308
Email:
SITE INFORMATION:
Site Address: 4502 E 4TH AVE Owner: STATE OF WASHINGTON-DOT
Parcel Number: 35232.3104 Address: 2714 N MAYFAIR ST
SPOKANE,WA 99207-2090
Phone:
Assessor's Description: CARNHOPE ADD L6B2 Email:
Inspection Area: : (509)-477-3675
Water District: Carnhope Irrigation District Fire District: Spokane Valley Fire
#7
Zoning: Land Area:6750 Square Feet
CONTRACTOR INFORMATION:
HARRYJP935BK, Exp.01/11/2016
HARRY JOHNSON PLUMBING/EXCAVATION INC
605 FOSTER ROAD WALLA WALLA,WA 99362
509-520-9308
DETAILS:
Class Type Quantity Unit Charge Value
SEWER ABANDONMENT 1 $125.00 $125.00
$125.00
FEE DETAIL:
Processing-Utilities $27.12
Utilities Permit $125.00
Total Fee: $152.12
CONDITIONS:
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Possible FEMA Flood Zone
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG--AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR& INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
SEWER PERMITS ARE VALID FOR ONE(1)YEAR FROM THE DATE OF ISSUANCE. FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT(509)477-3604 FROM 8:30-5:00 MONDAY-FRIDAY PRIOR TO COVER.ONE WORKING DAY NOTICE REQUIRED. PERMIT
ALLOWS FOR A 30-MINUTE INSPECTION.ADDITIONAL INSPECTION FEES APPLY AFTER 30 MINUTES.
Date Printed:03/16/2015 08:53:33 Project Coordinator:Kathy Cummings
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW-15000164 Permit Issued Date: 03/16/2015
Expiration Date: 03/16/2016
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED.SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed:03/16/2015 08:53:33 Project Coordinator:Kathy Cummings