2013, 04-04 Permit: SW-13000374 Sewer SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW-13000374 Permit Issued Date: 04/04/2013
Expiration Date: 04/04/2014
Project Description: SEWER CONNECTION
Project Name: WOODLAWN/BEVERLY HILLS
Primary Contact: MADSON, ROBERT Applicant: MADSON, ROBERT
Phone: Address: 6309 E 8TH AVE
SPOKANE,WA 99212-0526
Phone:
Email:
SITE INFORMATION:
Site Address: 6309 E 8TH AVE Owner: MADSON, ROBERT
Parcel Number: 35242.2645 Address: 6309 E 8TH AVE
SPOKANE,WA 99212-0526
Phone:
Assessor's Description: APPLEWAY HEIGHTS S 80FT LT 14&SW1/4 LT Email:
13 BLK 2
Inspection Area: : (509)-477-3675
Water District: East Spokane Water District Fire District: Spokane Valley Fire
#1
Zoning: Land Area: 14334 Square Feet
CONTRACTOR INFORMATION:
OWNER, Exp. 12/31/2015
OWNER
NOT KNOWN AT TIME OF ENTRY
UNKNOWN, UK 00000
DETAILS:
Class Type Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
$125.00
FEE DETAIL:
Processing-Utilities $26.32
Utilities Permit $125.00
Total Fee: $151.32
CONDITIONS:
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Inside Public Transit Benefit Area
Parcel within 100 feet of pipeline(s)owned by the following: (Yellowstone)
CALL 1-800-424-5555 BEFORE YOU DIG--AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR&INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
SEWER PERMITS ARE VALID FOR ONE (1)YEAR FROM THE DATE OF ISSUANCE. FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT(509)477-3604 FROM 8:30-5:00 MONDAY-FRIDAY PRIOR TO COVER. ONE WORKING DAY NOTICE REQUIRED. PERMIT
ALLOWS FOR A 30-MINUTE INSPECTION.ADDITIONAL INSPECTION FEES APPLY AFTER 30 MINUTES.
Date Printed:04/04/2013 09:09:15 Project Coordinator:Dawn Dompier
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW-13000374 Permit Issued Date: 04/04/2013
Expiration Date: 04/04/2014
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed:04/04/2013 09:09:15 Project Coordinator:Dawn Dompier