2014, 08-19 Permit: SW-14001214 Sewer SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW-14001214 Permit Issued Date: 08/19/2014
Expiration Date: 08/19/2015
Project Description: SEWER CONNECTION
Project Name: SUTTERS PH 1
Primary Contact: STOLZ INCORPORATED Applicant: STOLZ INCORPORATED
Phone: (509)928-8621 Address: 3808 S CHAPMAN RD
GREENACRES,WA 99016
Phone: (509)928-8621
Email:
SITE INFORMATION:
Site Address: 14007 E 8TH AVE Owner: SPOKANE SUPERIOR SOLUTIONS LLC
Parcel Number: 45232.9156 Address: 3933 LAKE WASHINGTON BLVD NE#
100
KIRKLAND,WA 98033
Phone:
Assessor's Description: 23-25-44 TR"A"OF S.P.00-1250 AUDITOR'S Email:
FILE#4729796 BK 18 PG 17 BEING A PTN OF
NW1/4(DEFERRED TAXES DUE TO THE STATE
OF WASHINGTON)
Inspection Area: : (509)-477-3675
Water District:Vera Irrigation District#15 Fire District:Spokane Valley Fire
Zoning: Land Area:21662 Square Feet
CONTRACTOR INFORMATION:
STOLZI*053N8, Exp. 11/01/2015
STOLZ INCORPORATED
3808 S CHAPMAN RD GREENACRES,WA 99016
(509)928-8621
DETAILS:
Class Type Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
$125.00
FEE DETAIL:
Processing-Utilities $26.64
Utilities Permit $125.00
Total Fee: $151.64
CONDITIONS:
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG--AT LEAST 2 WORKING DAYS IN ADVANCE.SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR&INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
SEWER PERMITS ARE VALID FOR ONE(1)YEAR FROM THE DATE OF ISSUANCE. FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT(509)477-3604 FROM 8:30-5:00 MONDAY-FRIDAY PRIOR TO COVER.ONE WORKING DAY NOTICE REQUIRED. PERMIT
ALLOWS FOR A 30-MINUTE INSPECTION.ADDITIONAL INSPECTION FEES APPLY AFTER 30 MINUTES.
Date Printed:08/19/2014 07:37:43 Project Coordinator:Vickie Merriott
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW-14001214 Permit Issued Date: 08/19/2014
Expiration Date: 08/19/2015
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED.SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME.BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed:08/19/2014 07:37:43 Project Coordinator:Vickie Merriott