2012, 07-18 Permit: SW-12001788 Sewer SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW-12001788 07/18/2012
Expiration Date:
Primary Contact: POUL CONSTRUCTION
Project Name: SUTTERS Applicant: POUL CONSTRUCTION
Permit Type: SEWER Address: 18902 E 2ND AVE
SPOKANE VALLEY,WA 99027
Phone: 509-979-5872
Email:
SITE INFORMATION:
Site Address: 14207 E 8TH AVE Owner: YOCHUM&CUILTY
Parcel Number: 45232.9154 Address: 14207 E 8TH AVE
VERADALE,WA 99037-9659
Subdivision: SP-302-84 Phone:
Assessor's Description: Section 23 Township 25 Range 44,THAT PTN OF Email:
TR'A'AND TR'B'OF SP 84-302 LYG W OF LN
DAF; BEG AT SW COR OF SD TR'B';TH E ALG S
LN OF TR'B', 15 FT TO TRUE POB;TH N
00"02'08"E TO N LN OF TR
Inspection Area:
Water District:Vera Fire District: Spokane Valley Fire
Irrigation District#15
Zoning: Land Area:0.57 Acre(s)
CONTRACTOR INFORMATION:
General Contractor
POULCC*932BQ
POUL CONSTRUCTION
18902 E 2ND AVE
SPOKANE VALLEY,WA 99027
509-979-5872
DETAILS:
Class Type Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
$125.00
FEE DETAIL:
Processing-Utilities $25.94
Utilities Permit $125.00
Total Fee: $150.94
CONDITIONS:
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG--AT LEAST 2 WORKING DAYS IN ADVANCE.SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR&INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
Date Printed:07/18/2012 10:59:57 Printed by:IIS APPPOOLWSP.NET v4.0
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW-12001788 07/18/2012
Expiration Date:
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT(509)477-3604 FROM 8:30-5:00 MONDAY-FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED.PERMIT ALLOWS FOR A 30-MINUTE INSPECTION.ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED.SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME.BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed:07/18/2012 10:59:57 Printed by:IIS APPPOOL\ASP.NET v4.0