2005, 07-29 Permit: 05005501 SewerSewn CrxNY
SPOKANE COUNTY
DEPARTMENT OF BUILDING & PLANNING
1026 WEST BROADWAY AVENDE • SPOKANE, WA'99260-0050
Site Information
Project Information
Site Address: 6156 E 9TH AVE
Parcel Number: 35243.0109
Subdivision: SYMONS ADD
Block: Lot:
Zoning: UR -3 Urban Residential 3.5
Owner: HARSH, MARTHA
Address: 6156 E 9TH AVE
SPOKANE, WA 99212
Building Inspector: NONE
Water Dist:
Project Number: 05005501 Inv: 1 Issue Date: 7/29/2005
Permit Use: SEWER CONNECTION
Applicant: VISTA CONSTRUCTION & DEV
3420 N TSCHIRLEY RD
SPOKANE, WA 99216 Phone: (509) 926-2243
Contact: VISTA CONSTRUCTION & DEV
3420 N TSCHIRLEY RD
SPOKANE, WA 99216 Phone: (509) 926-2243
Setbacks - Front: Left: Right: Rear:
Group Name:
Project Name:
1 Permits
Sewer Connection Permit
Contractor: VISTA CONSTRUCTION & DEVELOPME License#: VISTACD999DE
SEWER CONNECTION 1 $85.00 PROCESSING FEE
Total Permit Fee:
FOR SEWER INSPECTIONS CALL (509) 477-3604 UTILITIES 8:30-5:00 PM MONDAY THRU FRIDAY
1 $15.00
$100.00
Call for inspection prior to cover. ONE WORKING DAY NOTICE REQUIRED.
Contractor or applicant is to field locate and confirm the elevatidh and position of sewer stub prior to any other excavation.
Sewer stubs are to be checked prior to connection to ensure that they have acceptable grade and are dear and unobstructed to the main
sewer. Sewer lines should be constructed to allow for gravity flow from the lowest level of the structure.
This permit must be presented to the job site inspector for verification.To locate buried cables, gas piping, water lines, eta
CALL BEFORE YOU DIG, (509)456-8000.
STATE LAW RCW 19.122 REQUIRES THAT PRIOR TO ANY EXCAVATION THE "CALL BEFORE YOU DIG" CENTER BE
NOTIFIED. CALL BEFORE YOU DIG AT LEAST 2 WORKING -DAYS IN ADVANCE, (509)456-8000.
Spokane County Code requires the installer comply with all requirements of the Washington State Dept of Labor and Industries,
including those related to trench safety.
-'4P ym1eiSt nni ryh r
Total Fees
$100.00
AmountPaid AmountOwia8
$100.00 $0.00
Tran Date Receipt # Payment Amt
7/29/2005 4428 $100.00
Processed By: Hansen, Tom
Printed By: WENDEL, GLORIA Page 1 of 1
PERMIT
NOTICE
It is the responsibility of the applicant/permittee to see that the use described on the front of this permit complies with applicable codes and requirements and that required
inspections are requested Failure to request inspections as listed below and obtain the necessary approvals before progressing beyond the point where inspections are
required may necessitate removal of certain parts of the construction at the applicant's/permittee's or property owner's expense. At a minimum, the following inspections
ARE REQUIRED by County Code:
I. FOOTING - when forms and reinforcement are n place and prior to placement of concrete—all structures, including manufactured homes.
NOTE: This inspection includes review of the structure's setbacks from property fines. Minimum setbacks are established by County zoning regulations. Typically,
side and rear yard setbacks are measured from property lines, while setbacks for yards abutting streets are measured from the property line or the center Ime of the
roadway right-of-way, whichever provides the greater setback from the center line of the roadway right-of-way. Curb lines and fence Imes are not necessarily indica-
tive of property lines. In some residential areas, the County can own as much as 20 feet of right-of-way between your property and the actual improved streetcurb.
The responsibility to comply with applicable setback provisions lies solely with the permittee—neither Spokane County nor its authorized representatives assume any
responsibility for the verification or location of your property lines. Please verify their location prior to locating your structure. Failure to properly locate the structure
may require its relocation at the owner's/pemuttee's expense.
2. FOUNDATION- when forms and reinforcement are in place and prior to placement of concrete.
3. FRAMING - after all framing, bracing and blocking is in place, and prior to concealing.
4. INSULATION - prior to the installation of drywall.
5. PLUMBING - after rough -in, before covering, and final.
6. MECHANICAL - rough -in of piping, before covering, metal chimneys before concealment, and final.
7. FINAL - when complete and prior to occupancy and/or use. Please provide 24 hours notice. AR permits require final inspection.
NOTE: In addition to inspection of the structure, this inspection includes review of site improvements (typically depicted on the approved site plan) required by
ordinance or as a condition of approval of this permit. Items such as the installation of fire hydrants, fire department access, on-site drainage ("208 swales"), road
improvements, parking, and landscaping are common requirements ofa permit'site plan which must be completed prior to final approval ofa building or issuance
ofa Certificate of Occupancy.
8. MANUFACTURED HOMES - Final inspection required when complete, stairs, handrails, skirling etc. installed, and prim to occupancy; completed inspection record
card must be available on site. Manufactured home installations must comply with the manufactures installation instructions.
9. SEWERS - prior to cover
10. RIGHT-OF-WAY/APPROACH - prior to placement of concrete, or, if gravel approach, after completion.
In addition to the above, any plumbing or mechanical systems or material which would be concealed by framing, drywall, concrete, etc. must be inspected prior to cover.
Check with the department for "special inspections" in conjunction with commercial projects.
FOR INSPECTIONS:
TO INSURE PROMPT SERVICE, PLEASE GIVE ONE WORKING DAY/24 HOUR NOTICE .
PARTS OF YOUR PROJECT MAY REQUIRE PERMITS AND INSPECTIONS
FROM MORE THAN ONE AGENCY.
• Building, plumbing, mechanical and fire inspections, Department • Road cuts for utilities or driveways, Division ofEngineering &
of Building and Code Enforcement Roads - 48-HOUR NOTICE REQUIRED
477-3675 477-3600
or State Department of Transportation
• Construction in a flood plain, Division of Engineering & Roads 456-3000
477-3600
• Electrical wiring, State Department of Labor and Industries
324-2640
On-site waste disposal system, Spokane Regional Health District
324-1560
PERMIT EXPIRATION AND REFUNDS
Unless otherwise noted, this permit will be considered null and void by limitation if the work authorized by the permit is not commenced or is stopped for a period of 180
days, unless a written request for an extension ofthe permit is received and approved by the Building Official prior to expiration. At a minimum an inspection should be
requested at least once every 180 days to assure the validity of the permit. Apermit maybe renewed within one year of the date of expiration for one-half the original fee,
subject to certain limitations—please call us if you have any questions.
Anyrefimd requests must be made in writing by the applicant/permitlee (shown on thereverse) no later than 180 days after the date of fee payment. Refunds of not more
than 80% of the permit fee paid may be authorized when no work has been done under the permit. No refunds may be authorized more than 180 days after fee payment.
MISTAKE?
If you think we've made an error in processing this permit or in conducting inspections pertaining to it, or find erroneous information in the permit, please bring it to our
attention immediately by filing a written request for correction within 10 working days ofdiscovery. All such requests should be directed to the Division of Building and
Code Enforcement at the below address.
• Sewer connection, Division of Utilities
477-3604
or City Public Works Department
625-6300
Spokane County Department of Building and Planning
1026 West Broadway Avenue, Spokane, WA 99260
Phone: (509) 477-3675 Fax: (509) 477-4703 TDD: (509) 477-7133
wwwspokanecountyorg/hp bpr®spokanecountyors