2010, 09-28 Permit: 10003169 WoodstoveSUTUWI?\
PERMIT CENTER
11703 E. Sprague Avenue, Suite B-3
Spokane Valley, WA 99206
1
Site Information
Project Information
Site Address: 6924 E 9TH AVE
Parcel Number: 35244.0631
Subdivision:
Block: Lot:
Zoning: R-3 SF Res District
Owner: HITE, VALERIE
Address: 6924 E 9TH AVE
SPOKANE VALLEY, WA 99212-0133
Building Inspector: SOUTH
Water Dist: EAST SPOKANE
Project Number: 10003169 Inv: 1 Issue Date: 09/28/2010
Permit Use: 1 WOOD OR PELLET STOVE/INSERT
Applicant: FALCO STOVE SHOP
9310 E SPRAGUE AVE
SPOKANE WA 99206
Contact: FALCO STOVE SHOP
9310 E SPRAGUE AVE
SPOKANE WA 99206
Phone: (509) 926-8911
Phone: (509) 926-8911
Setbacks - Front: Left: Right: Rear:
Group Name:
Project Name:
Permits1
Mechanical Permit Contractor: FALCO STOVE SHOP
License #: FALCOI*953DA
WOOD/PELLET STOVE/INSER
FOR MECHANICAL INSPECTIONS CALL (509) 688-0054.
1 $11.00 PROCESSING FEE
Total Permit Fee:
$37.00
$48.00
Payment Summary
Total Fees AmountPaid AmountOwing
$48.00 $48.00 $0.00
Tran Date Receipt # Payment Amt
09/28/2010 24475 $48.00
Processed By: Main, Jodi L
Printed By: MORRIS, HEATHER Page 1 of 1
PERMIT
NOTICE
The ownership of a Spokane Valley Development Permit will inure to the property owner. The permit applicant, by
definition, is the property owner or an authorized agent of the property owner. It is the responsibility of the
applicant/permittee that the use described on the front of this permit complies with applicable codes and that required
inspections are requested. Failure to request inspections as listed below and obtain the necessary approvals before
progressing beyond the point where inspections are required may necessitate removal of certain parts of the
construction at the applicant's/permittee's or property owner's expense. At a minimum, the following inspections ARE
REQUIRED by City Code:
FOOTING — when fors and reinforcement are In place and prior to placement of concrete -all structures, Including manufactured homes.
NOTE: This inspection includes review of the structure's setback from property lines. Minimum setbacks are established by City of Spokane
Valley Ordinance. Curb lines and fence lines are not necessarily indicative of property lines. The responsibility to comply with applicable
setback provisions lies solely with the perittee-neither the City of Spokane Valley nor its authorized representatives assume any
responsibility for the verification or location of your property lines. Please verify their location prior to locating your structure. Failure to
properly locate the structure may require Its relocation at the owner's/permittee's expense.
FOUNDATION — when fors and reinforcement are in place and prior to placement of concrete.
PLUMBING — after rough -in, before covering, and final.
MECHANICAL— rough -In of piping, before covering, metal chimneys before concealment, and final.
FRAMING — after all framing, bracing and blocking is in place, rough electrical, plumbing and mechanical systems are complete, and prior to
concealing.
FINAL —when complete and prior to occupancy and/or use. All permits require final inspection.
NOTE: In addition to inspection of the structure, this inspection includes review of site Improvements (typically depicted on the approved site
plan) required by ordinance or as a condition of approval of this peril Items such as the installation of fire hydrants, fire department access.
on-site drainage (208' swales), road improvements, parking and landscaping are common requirements of a permit/site plan which must be
completed prior to final approval of a building or issuance of a Certificate of Occupancy,
MANUFACTURED HOMES — Final Inspection required when complete, stairs, handrails, skirting. etc. installed, and prior to occupancy;
completed inspection record card must be available on site.
PLUMBING REVERSALS FOR SEWER CONNECTIONS — prior to cover.
RIGHT-OF-WAY/APPROACH — prior to placement of concrete/asphalt or, if gravel approach, after completion.
In addition to the above, any plumbing or mechanical systems or material which would be concealed by framing, drywall, concrete, etc. must
be inspected prior to cover. Check with the Building department for 'special Inspections- in conjunction with commercial projects.
FOR INSPECTIONS
Please give one working day/24 hour notice. Different parts of your project may require pennits and Inspections from more than one agency.
Building, plumbing (includes interior reversals for sewer) and
mechanical, City of Spokane Valley Building Division 686-0054
Road cuts for utilities or driveways, City of Spokane Valley
Public Woks 688-0195 or State Dept of Transportation
324-6000
Pmrns and inspections for elec1dal ¢.tong. Slate Department M Labor Pemits and Inspections to Sewer Connecbon. Spokane County unritiea Division
And Industries 324-2640 471a504
Permits and inapemau for crone septic enters. Spokane Regional Foe spino and alarm sytents and private access road inspectors. spekane valley
Health DisIna 324.15¢0 Fire Department 092.4122
Slate law RCW 19.122 requires Out prior to any excavation Me 'CALL BEFORE YOU DIG' center mut be no4fiedWI before you dig at least 2 working days In advance. 456-0000.
PERMIT EXPIRATION AND REFUNDS
All permits shall expire by limitation and be declared void if a) work is not started within 180 days of obtaining a permit, or b) work is
abandoned for 180 days or more after beginning work, or c) after two years from the date of permit Issuance, regardless of whether the work R
finished. If a permit Is expired fortime, a new permit may be obtained for half the permit fee based on the value of the remainder of the work to
finish the original permit.
All refund requests must be made in writing by the original permittee to the Building Official no later than 180 days after the date of fee
payment. 100% refunds will be granted for any fee erroneously paid or collected. Refunds of not more than 8O% of a permit fee may be
authorized when no work has been done under the permit issued. Refunds of not more than 80% of a plan review fee paid may be authorized
when an application is withdrawn or cancelled prior to the plan review being completed.
Owner/Agent Date
Staff Approval Date
City of Spokane Valley
Building Dept
Receipt
Receipt Number: 24475 Customer Number
Projects
Project Nbr Inv Nbr' FeeAte Inv Amo Owin
10003169 1Ehoo.J 148.00.1 t $ARJXU $48.00
Total: t g413.0Cla G.".Ve.o'�70 1 s4 on] $48.00
Miscellaneous Items
Tender
Full
PAID Pmt
Total PAID: $48.00
5'vve Check Acct Balance CC Nbr Exv Dale
VISA
Notes:
Tran Date / Time:
By:
Logon User:
Station:
Override By:
1 _,l" 6uuuocxxxxxxx5013 i¢ O6/20141
09/28/2010 4:58:58 PM
HMORRIS
BldgCounter
CX_SV00014A
Printed: 09/28/2010 4:58:58 PM
Total TENDERED:
TENDERED
48.00
Over / (Short)
Change
48.00
$0.00
$0.00