2013, 03-06 Permit: SW-13000155 Sewer SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW-13000155 Permit Issued Date: 03/06/2013
Project Description: SEWER CONNECTION
Project Name: SUTTER'S(HERITAGE)
Primary Contact: LARRY MILLER EXCAVATING Applicant: LARRY MILLER EXCAVATING
Phone: 509-218-3335 Address: 7117 E RUTTER AVE
SPOKANE,WA 99212
Phone: 509-218-3335
Email:
SITE INFORMATION:
Site Address: 14021 E 9TH CT Owner: CAMPBELL,SCOTT A
Parcel Number: 45233.3508 Address: 14021 E 9TH CRT
VERADALE,WA 99037-8617
Phone:
Assessor's Description: HERITAGE COURT LT 8 BLK 1 Email:
Inspection Area: : (509)-477-3675
Water District:Vera Irrigation District#15 Fire District:Spokane Valley Fire
Zoning: Land Area: 13827 Square Feet
CONTRACTOR INFORMATION:
LARRYME918DR, Exp.03/19/2013
LARRY MILLER EXCAVATING
7117 E RUTTER AVE
SPOKANE,WA 99212
509-218-3335
DETAILS:
Class Type Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
$125.00
FEE DETAIL:
Processing-Utilities $26.32
Utilities Permit $125.00
Total Fee: $151.32
CONDITIONS:
Inside Public Transit Benefit Area
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
CALL 1-800-424-5555 BEFORE YOU DIG--AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR&INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT(509)477-3604 FROM 8:30-5:00 MONDAY-FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30-MINUTE INSPECTION.ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
Date Printed:03/06/2013 12:24:24 Project Coordinator:Kathy Cummings
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW-13000155 Permit Issued Date: 03/06/2013
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed:03/06/2013 12:24:24 Project Coordinator:Kathy Cummings