Architecture • LanescspeArchfecture CHANGE ORDER-003
Issue Date: 11/11/2016
_ .j [
PROJECT OWNER CONTRACTOR DISTRIBUTION X
Spokane Valley City Hall City of Spokane Valley Meridian Construction Steve Worley X
10210 E.Sprague 11707 E.Sprague Ave. 12310 E Mirabeau Parkway Mark D'Agostino X
Spokane Valley,WA 99206 Suite 106 Suite 100 Steve Roth X
Spokane Valley,WA 99206 Spokane Valley,WA 99216 Jim Paras X
CONTRACT FOR: GENERAL CONSTRUCTION
CONTRACT DATE: 5-20-2016 r
You are hereby directed to make the following changes in the contract:
REFERENCE DESCRIPTION AMOUNT
COP-002R3 Delete Under-slab Plumbing and Thin slab in south wing ($8,498.62)
CCD-002
COP-004R3 Under-slab Plumbing in North Wing $13,093.21
ASI-002
CCD-003
COP-012 Structural Connections and Elevations $1,714.00
RFI-004
COP-018 Additional Steel from Submittal Review $1,340.00
Submittal 0046
COP-025 Elevator Head Height adjustment $3,149.61
ASI_012
COP-028 Waste Piping Not Shown $715.39
RFI-060
COP-030.2 Native Cornerstone $1,878.36
PR-004
TOTAL $13,391.95
The Original Contract Sum was: $9,742,700.00
Net Change by Previously authorized Change Orders: $15,487.00
The Contract Sum prior to this Change Order was: $9,758,187.00
The Contract Sum will be increased by this Change Order in the amount of: $13,391.95
The new Contract Sum including this Change Order will be: $9,771,578.95
The Contract time will be unchanged/Changed by: 0 days
The Date of Substantial Completion as of the date of this Change Order therefore is: 7/25/2017
ARCHITECT CONTRACTOR OWNER REPRESENTATIVE
Architects West,Inc. Meridian Construction City of Spokane Valley
210 E.Lakeside Ave. 12310 E.Mirabeau Parkway,Ste 100 11707 E.Sprague Ave.,Suite
Coeur d'Alene,ID 83814 Spokane Valley,WA 99216 106
Spokane Valley,WA 99206
SIGNATURE: SIGNATURE: SIGNATURE:
.1111
DATE: 10/31/2016 DATE: i (/ 9/I t.l' DATE: // /21
1509—SPOKANE VALLEY CITY HALL CHANGE ORDER-003 —11/11/2016
Page 1 of 1
210 East Lakeside Avenue 1 Coeur d'Alene,Idaho 83814 1 ph 208-667-9402 1 fx 208-667-6103 I www.architectswest.corn
l\111111106,
CITY OF
P blic Works Department
u p
�� Capital Improvement Program
.00ValleY
11707 E Sprague Ave Suite 106 ♦ Spokane Valley WA 99206
509.921.1000 ♦ Fax: 509.688-0261 • cityhall®spokanevalley.org
Change Order Memorandum
Date: November 29, 2016
l`
To: Eric Guth-Public Works Director
From: Steve M.Worley-Capital Improvement Program Manager ,� /
Re: New City Hall Project#0215-Change Order#3 /V
Budget Account No. 313.000.215.594.18.62.00 Meridian Construction Contract#16-091.03
The purpose of this memorandum is to request Public Works Director approval of Change Order
#3. This change order provides for five items as described below:
1. Delete Under-slab Plumbing and Thin Slab in South Wing ($8,498.62)
2. Under-slab Plumbing in North Wing $13,093.21
3. Structural Connections and Elevations $1,714.00
4. Additional Steel from Submittal Review $1,340.00
5. Elevator Head Height Adjustment $3,149.61
6. Waste Piping Not Shown $715.39
7. Native Cornerstone $1,878.36
Total $13,391.95
The Contract Time is not changed by this change order. The Substantial Completion Date remains
at 7/25/2017. Following is a summary of the Contract amount:
Original Contract amount(without 8.7% sales tax) $9,742,700.00
Previous Change Orders $15,487.00
Change Order#3 $13,391.95
Revised Contract Amount including Change Order#1 $9,771,578.95
Note: The required 8.7% sales tax will be added to the total Contract Amount as payments are
made.
Maximum Public Works Director Contract Authority $75,000.00
Change Order Cost to date= $28,878.95
Remaining P.W. Director Change Order Authority $46,121.05
Cc: Finance Department, Clerk's Office