2012, 08-10 Permit: SW-12001949 Sewer SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW-12001949 08/09/2012
Expiration Date: 08/10/2012
Project Description: SEWER CONNECTION Primary Contact: COURCHAINE CONSTRUCTION
Project Name: SUTTERS Applicant: COURCHAINE CONSTRUCTION
Permit Type: SEWER Address: 19818 E SPRAGUE
GREENACRES,WA 99216
Phone: 509-924-5485
Email:
SITE INFORMATION:
Site Address: 14509 E 10TH AVE Owner: REED, PAMELA A
Parcel Number: 45233.1303 Address: 14509 E 10TH AVE
VERADALE,WA 99037-9605
Subdivision: HELSTROM'S Phone:
SUBDIVISION NO.3
Assessors Description: VERA HELSTROM SUB3 L3B1 Email:
Inspection Area:
Water District:Vera Fire District:Spokane Valley Fire
Irrigation District#15
Zoning: Land Area: 10452 Square Feet
CONTRACTOR INFORMATION:
General Contractor
COURCC*181R7
COURCHAINE EXCAVATION
19818 E SPRAGUE
GREENACRES,WA 99016
509-928-0846
DETAILS:
Class Type Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
$125.00
FEE DETAIL:
Processing-Utilities $25.94
Utilities Permit $125.00
Total Fee: $150.94
CONDITIONS:
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG--AT LEAST 2 WORKING DAYS IN ADVANCE.SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR&INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
Date Printed:08/09/2012 15:28:07 Printed by:IIS APPPOOLWSP.NET v4.0
SPOKANE COUNTY WADING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW-12001949 08/09/2012
Expiration Date: 08/10/2012
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT(509)477-3604 FROM 8:30-5:00 MONDAY-FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED.PERMIT ALLOWS FOR A 30-MINUTE INSPECTION.ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION. _
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED.SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE. _
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME.BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed:08/09/2012 15:28:07 Printed by:IIS APPPOOLWSP.NET v4.0