2014, 05-29 Permit: SW-14000740 Sewer SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW-14000740 Permit Issued Date: 05/29/2014
Expiration Date: 05/29/2015
Project Description: SEWER CONNECTION
Project Name: VACANT PROPERTY
Primary Contact: TUPIKOV, SVETLANA Applicant: TUPIKOV,SVETLANA
Phone: 509-280-0944 Address: 2219 E MARSHALL AVE
SPOKANE,WA 99207
Phone: 509-280-0944
Email:
SITE INFORMATION: U✓j„ 3 04 -du
Site Address: /pYOWN� Owner: TUPIKOV, SVETLANA
Parcel Number: 35243.0828 Address: 2219 E MARSHALL AVE
SPOKANE,WA 99207
Phone: 509-280-0944
Assessor's Description: BETTMANS ADD L23-24B4 Email:
Inspection Area: : (509)-477-3675
Water District:Spokane County Water Fire District:Spokane Valley Fire
District#3
Zoning: Land Area: 13500 Square Feet
CONTRACTOR INFORMATION:
OWNER, Exp. 12/31/2015
OWNER PERFORMING THE WORK
SAME AS SITE ADDRESS SAME,WA 00000
509-218-7562
dale@dalethomasplumbing.com
DETAILS:
Class Type Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
$125.00
FEE DETAIL:
Processing-Utilities $26.64
Utilities Permit $125.00
Total Fee: $151.64
CONDITIONS:
Possible FEMA Flood Zone
Possible Stream On Site
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Parcel within 100 feet of pipeline(s)owned by the following: (Yellowstone)
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG--AT LEAST 2 WORKING DAYS IN ADVANCE.SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR&INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
SEWER PERMITS ARE VALID FOR ONE(1)YEAR FROM THE DATE OF ISSUANCE. FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT(509)477-3604 FROM 8:30-5:00 MONDAY-FRIDAY PRIOR TO COVER. ONE WORKING DAY NOTICE REQUIRED.PERMIT
ALLOWS FOR A 30-MINUTE INSPECTION.ADDITIONAL INSPECTION FEES APPLY AFTER 30 MINUTES.
Date Printed:05/29/2014 10:56:25 Project Coordinator:Kathy Cummings
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW-14000740 Permit Issued Date: 05/29/2014
Expiration Date: 05/29/2015
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed:05/29/2014 10:56:25 Project Coordinator:Kathy Cummings