1991, 05-24 Addendum No 1: Remodeling & Addition • 110 110 ~ i REMODELING AND ADDITION, 1991 ADDENDUM NO. 1 VALLEY HOSPITAL & MEDICAL CENTER May 24 , 1991 Northwest Architectural Company, P.S. , 90057 Page 1 This Addendum is hereby made a part of the Contract Documents to the same extent as though it were originally included therein. ARCHITECTURAL/STRUCTURAL SPECIFICATIONS : SUPPLEMENTARY INSTRUCTIONS TO BIDDERS, Page 1 , Line 21 : ADD: "Robert B. Goebel , General Contracting, Inc. " SECTION 01010, SUMMARY OF WORK, Page 1 , Line 28 : ADD: "The Medical Records Department addition must ' be complete, with the Owner able to occupy the space, before work on the Outpatient and SAC Department can begin. " SECTION 02831 , CHAIN LINK FENCES AND GATES: ADD: Entire section as attached. SECTION 06100, .ROUGH CARPENTRY, Page 1 , Line 49 : CHANGE: "Where wood is required to have fire-retardant treatment . . . " TO "All wood is required to have fire- retardant treatment . . . " SECTION 07250, SPRAYED-ON FIREPROOFING, Line 7 : ADD: "Repair or replace fireproofing in Radiology suite where new structural framing disturbs fireproofing around existing structural members . " SECTION 10010, MISCELLANEOUS SPECIALTIES, Page 2 , Line 37 : • ADD: "Revolving Darkroom Door: Shall be Speedmatic by ESECO, Model 2W28 , Cat . No. 9010, color as selected. " SECTION 13091 , X-RAY PROTECTION, Page 1 , Line 37-40 : DELETE: Reference to "single source responsibility" . DRAWINGS: SHEET A2 . 2 : • REMOVE: Notation "limits of contract to extend 8 ' -0" beyond • the foundation of the new addition. " REMOVE: Portion of existing curb as shown on attached Drawing CA-3 . • SHEET A2 . 3 : - MOVE Door 119 to east wall of .Room 119 and provide 18" clear on strike side of door. • • 411 - i REMODELING AND ADDITION, 1991 ADDENDUM NO. 1 VALLEY HOSPITAL & MEDICAL CENTER May 24, 1991 Northwest Architectural Company, P. S . , 90057 Page 2 • In Room 121 , MOVE floor sink 3 ' -0" to the east to provide clearance by strike side of Door 121 . Under wall types, Types 11 and 12 , MOVE "vapor barrier" to follow "R-19 batt insul . " Under wall types, Type 11 , CHANGE 6" metal studs to 8" metal studs: SHEET A2 .4 : Under wall types, Types 11 and 12 , MOVE "vapor barrier" to • follow "R-19 matt insul . " At Door 172 , PROVIDE a landing 44" in length and from north wall of Room 172 to strike side of door in width. Provide a 3 '-0" long ramp down for 2-1/2" drop on the west and south side of landing. See attached Drawing CA-3 . In Room 172 , VERIFY mobile file track dimensions with mobile file supplier. LOCATE wall between Rooms 152 and 153 , 13 ' -0" from face of finish of south wall of Room 152 to face of finish of new • wall . PROVIDE revised casework, floor finishes and door location for Office 154 as shown on attached drawings CA-1 and CA-2 . In Room 156 and 163 , at existing walls with electrical outlets and other .penetrations that will receive new lead- lined gypsum board over existing wall finish, BREAK away enough of existing wall around penetration to glue lead liner behind object in wall . PROVIDE 6 ' -0" chain link fence and gate at new fuel tanks as shown on attached Drawing CA-3 . Under wall types; Type 11 , CHANGE 6" metal studs to 8" metal studs. SHEET A2 . 5 : PROVIDE horizontal blinds on exterior windows in Rooms 170 and 171 . SHEET A3 . 1 : Under Door & Relite Schedule, at Door 151 , CHANGE door type to Type "B" . Under Room Finish Schedule, at Room 154 , CHANGE flooring finish to "VCT" . CHANGE flooring color to "V5" . CHANGE base color to R2" . ADD to remarks column "Partial VCT floor to match existing" . 411 411 9 ► REMODELING AND ADDITION, 1991 ADDENDUM NO . 1 VALLEY HOSPITAL & MEDICAL CENTER May 24 , 1991 Northwest Architectural Company, P. S . , 90057 Page 3 Under Color & Finish Notes, under vinyl composition tile, ADD "V5 - match existing" . Under Color & Finish Notes, under rubber base, ADD "R2 - match existing" . Under Color & Finish Notes, under wallcovering border/W4 , RELOCATE "rigid vinyl wallcovering" to the left to form separate heading. Under frame types, at Type "D" , CHANGE height to 3 ' -4-" and width to 5 ' -0" . Under "Abbreviations" at "ATGB" , CHANGE to read "ATGB acoustical tile on ( 1 ) layer 5/8" Type X Gyp. Bd. ( 12" x 12" w/vinyl - plastic finish) . " SHEET 4 . 1 : At Details 1/A4 . 1 through 4/A4 . 1 , CHANGE 6" stl . studs to 8" stl. studs. At Detail 1/A4 . 1 , ADD note "sprayed-on fireproofing" indication to underside of metal deck and face of structural framing. At south and west elevations, ADD "Paint in color to be selected" to note "Align 4" channel screed with existing, typ. " - SHEET A6 . 1 : At Elevation 19 , CHANGE 2 ' -0" dimension to 5 ' -0" . At Elevation 31 , RAISE top of P-lam counter to 3_' -4" . SHEET A6 . 2 : Under washroom fixture schedule, CHANGE item "Toilet paper dispenser" to be "OFOI" . Item "CT room services" to be • "OFCI" . SHEET A6. 3 : At Details 8/A6 .3 and 9/A6. 3 , REVISE as shown on attached Drawing CA-4 . SHEET A7. 2 : REVISE sprinkler head locations in Rooms 156, 157 , 158 , 159 , 160, 163 , and 166 as shown on attached Drawing CA-5 . PROVIDE suspended ceiling brace wires as shown on attached Drawing CA-6. SHEET S2 . 2 : ADD: Entire sheet as attached. 4111 • REMODELING AND ADDITION, 1991 ADDENDUM NO. 1 VALLEY HOSPITAL & MEDICAL CENTER May 24 , 1991 Northwest Architectural Company_, P. S. , 90057 G.E. Medical Systems drawings for Cath Lab, Cover Sheet, A. 1 , S. 1 , E. 1 , E. 2 and D. 1 are attached. Meeting minutes from Pre-Bid Conference are attached. END OF ADDENDUM N3 N C . is , , ® -.J -_=-1 IL \ RECEPT. & TELEPHONE OUTLET BELOW COUNTER TOP. PROVIDE GROMMETED HOLES FOR POWER • AND TELEPHONE CORDS. k t i t ,....,_ . . _ EXISTING -r E' ►. T., ; ....• 1.: . CLOCK RELOCATED i i E i 1 '1 E A ' Ler 4 I Q • €... .; i ei-�'� T i i- I TO 2(1 P20A) EXISTING SPARE BKRS PNL 'IN4' • • n ; � a . I • . Arm". 411110iM ® ,_ — co 1 r=" li i . ,I , ROOM 154 - RADIOLOGY RECEPTION SCALE: 1/g = 1'-0r ADDENDUM #1 May 24, 1991 VALLEY HOSPITAL & MEDICAL CENTER REMODELING & ADDITIONS, 1991 VALLEY HOSPITAL & MEDICAL CENTER,90057 ADDENDUM #1 Northwest Architectural Company. P.S. Page 1 SPECIFICATIONS • Section 16760 - Nurse Call System System is Executone System and no substitutions will be allowed. Section 16761 - Intercom System Delete entire section and replace with Section 16761 - Overhead Paging/Music System. • PANEL SCHEDULES Delete panels CRX, BN3 and BN4 and replace with new panel schedules. Insert new panel schedule A3. DRAWINGS Drawing E1.1 System note 4 - Delete paragraph for device boxes and replace with: • "electrical contractor shall verify all nurse call box sizes with equipment supplier". Drawing E2.1 Room 111 - Add two Type 15 fixtures with a 600W dimmer mounted next to door. Circuit to lighting circuit serving this room. Drawing E2.2 Room 117 - Provide 120 volt AC door closure relay from receptacle circuit B-26. Drawing E3.1 • Rooms 158 and 157 - J-boxes shown without call outs are for lighting interconnection for foot switch control from X-ray table. Coordinate exact requirements with GEMS and hospital personnel. S S REMODELING & ADDITIONS, 1991 VALLEY HOSPITAL & MEDICAL CENTER,90057 ADDENDUM #1 Northwest Architectural Company. P.S. Page 2 • Drawing E3.2 Room 159 - Delete magnetic door holder. Replaced with a door closure provided by others. Electrical contractor shall provide relay, 120 volt AL from receptacle circuit BN4-9 and interlock to fire alarm system. • Room 152 - Provide 120 volt AC to door closure relay from receptacle circuit BN-24. Room 156 - Provide telephone/computer outlet above counter on north wall. See architectural elevations for location. • - Room 154 - See attached drawing showing electrical revisions. Add duct smoke detectors and shut down relays to AC-1 and AC-2. Interconnect to fire alarm system as required by Simplex Fire Alarm Company. Drawing E4.1 C.T. Lab Power Plan Change note 12 wall duct from 3"x14" to 3"x12". Add the paragraph to note 17: "120 volt AC 2#12, 1#12G, 3/4"C from panel CRX circuit CRX-12". Drawing E4.2 New drawing dated 5/24/91. • • Drawing E5.1 Remove existing drawing dated 4/26/91 and replace with new drawing dated 5/24/91. • REMODELING & ADDITIONS, 1991 16761 VALLEY HOSPITAL & MEDICAL CENTER,90057 PAGING/MUSIC SYS. Northwest Architectural Company.. P.S. Page 1 PART ONE - GENERAL RELATED DOCUMENTS Drawings and General provisions of contract, including general and supplementary conditions and Division-1 specifications sections apply to work of this section. • REQUIREMENTS The contractor shall furnish and install all equipment, accessories, and materials necessary for the extension of the existing intercom system in accordance with this specification and applicable drawings. • The equipment furnished under this specification shall be the standard product manufactured to match the existing system equipment manufacturer. All components and the system as a whole shall meet or exceed the minimum standards issued by the EIA. All work in conjunction with this installation shall meet the provisions of the National Electrical Code. Each major component shall bear the manufacturer's name, catalog number and UL label. SYSTEM DESCRIPTION Overhead Paging/Music system is existing. Electrical contractor shall provide and install the following items: Ceiling speaker to match existing - • Volume control wall mount to match existing Signal/Intercom cable to match existing PART THREE - EXECUTION INSTALLATION The contractor shall install the overhead paging/music system in conduit to all locations shown and as required by the equipment manufacturer. Provide all backboxes,junction boxes, faceplates, etc., as necessary for a complete installation. END OF SECTION 16761 it . 0 • . . . • . . . . O . pN c�pp Cp NNa��{ t�pp s z N"fiDaDON< tCaDNNXRV, 8 ` X8 • . 2 w Z E 0 co d I CC -J 0 W U CO J Z -, W w w a Z3 a•gq25 5T v- U UW U>- Z W W W W W W W W W W W W El it 6 61_aaaaaana.a1aaaa co fix= 2Uop0)CO000OV) NtnfnCOV) u) - a. . opp CCpCpppOp CpCp i/ N M U O O W §O O EN N 0 8 8 8 o 8 f 0 0 ' g } Z Q v.v D Y o 0 0 0 0 0 o c p d o 0 Q J r Z N z O 1- y1- m FIRS RRRRRRRRRRRRRR Z J < et U III 11111111111111 E o xO. N aa.a N a a a aO. a a a a a a a a a a @ I Z • ¢g 0 eie S w a 0 m C9 00 = m RRRRR RRRRRRRRRRRR �a8 $ E81. -J 0 W 0 11111 I I I i l l l l l i t l xRCxxrx i �. < J 00 M LL ^-.-a N a a a a a a a a a a a a ' o 5 88c O O 00 a ( ? a �� � � ,-cCicCiNN Qa' 000000 10 0 (IL., (7 = > o 2 • 0O 0W • J[c2IY Z II 11 II U II U U U II o < 3-o 2 "59 w o � 0 c 2 o U • -'01A o m., W 131- $v Z z = 80x2 . z O a1 38 L x c J E be < V N O cow F. <0 0 W LC , 0 - LUa E w w O o t� U 0 • • WtnW �Er c0ZZZZIli LIJ C) CD CD 0 WWWWWwW J x CSC3h D>-J - - >• 0 I J10_S m2SSimcococ)u)coco • Z .-0) 1.0PO) �t71fJP0) NNNNMCO 1.0 -, W @ Z ` O Z 0 CC < 0 G. J A _ .( 0 • I m a ' () N N'V (I) • z O • (r Ir 0 O w ad 0 w 0 • 2 2 N 3¢v gam¢ . 0w a 0 0 0 w m il 0 '' 888 088888"388 m r) (V w -N r 0 a> 0 0 0 0 0 N O O N N 2, O 11 0 r 6 2,Z N Z 0 y W .. O < z � acr � RER 2 >• n=. CO aaa e 0 w I a O Z = m Nop pQ0NQC J w U � ° o O n a.aai XXXX 2 I- O w Q = J r r r O I H J O en Z O Z 888 888888 8 S. C a Q Z ¢ N r N 0 a C G C O O N I O cj 220 > o? • UO 0w Q JCC2IX z NONNIUUNK t m 90 9 si .mC ` mV tiQQ coaLo $o Z 0 �OJc Z &1 O L XCC N al I- N 0 J Ir w < I-' 0 CO LLI W CO W U `5 = 0 m a a 2 iO_ M www fi 0 mC�m > a cg 1_I . Z —loan O w iz:< : Z OZ U Cr < O a d J - • ill . . 0 . . • • O Z 01 • N1ra3C° ONNNAMgi ppNN pp8oo sr• . • 1 ' Z 0L_ t co cc Ili w 0 a O • • NN0NNN0ANC) • g C)C)() C)C.) C) U C) C.) 4a4a4aa6a • �b.�b.b.b.b.�biLWWWWWWwwWwww WWWwwwwww¢¢ ¢¢¢¢¢¢ ¢¢ C.)C.) UC)C) C) c�C)C) QacEaaaaaa4Ea4 www www wWan.a.CLdaaaaC/) ) a 00 0W e¢ta¢fp¢¢¢CCCCCC8 roc cccncc CV CO CDCDg �0i � CD CD CDtAN 0 (88i8882i_ 88 A 1N7 w 0 0 0 0 0 0 df • >- Z > O N to ZN Z 0 g a z JQI- m RRRRRRRRRRRRRRRRRRRRR i wE >= 2 a a a a a a CL a CL a a a a a a as a n.a.CL LI Z g 0 '5 UJ n. 15 UJ 2 z oS m RRRRRRRRRRRSRR 8 04< gg $ ` < ac w Cn o iiiIiiiiiiiiii I xRxx .sx 2 0 `O CD I � aaaaaaaaaaaaaa n O 0) ZZ §ERP- § § § RE § mE §?^ Qa Eri 8882 , Eto Q O J. 00 0 W ¢¢¢¢¢ ¢¢¢CL¢¢ Z J¢ JCL2 =Y Z • HUHUNDUHU o a . ...3 . �� c „'2 C 0 ... CB CV eicoW 1:1 rL a Z• _ J �� 5Z0 $ o O • I - x c J W ae z W H N- O LIJZCC5 , SS¢ a. cncoco cncncococncncncnQ4S ~ • 0 220 �, CO UUUUUUUUUUUZZ6 z o as a a 4'a a4 a as >' ¢ riLLLLLLtt�tFF►= m J O WWWWWWWWWWW�a„<� . w _ __ J c•) U C)C) C)C)U C) U U C) C.)C) Z W W W W W W W W W W W V U U ,• . a , Z W ¢¢¢¢¢¢¢¢¢¢¢D 25 C a - > m ct t� pf t� t[� _ Z .-c7N t. Of .- 1747 n CA N N N N N M c7 c7 Mc 07 Q O -I W < Z • O Z U ¢ < 0 an. J • III, tik . • • • • O • Z - • • N� co0OpSiNtNSp Sy e8Sp p? • • z 0 idwSJ E a O <UU ¢ W 5 �QQw8 U)coco co coco0co • 222uU 2i Ow0 <aaoaSi«a • aa tttht ttititiwwwwww . Y Y Y W w W W W W W W W¢¢¢¢¢¢ • CC ' www'"Lu uiwaaaaaaa N D O O U)u. ¢¢¢Z¢Q¢cL¢co co co co co co a. 0o ow 2 cG¢¢¢¢¢ ¢¢ >-(S o Z > W O 0 Z N Z CO � Nx m RRRRB RRRRRRRRRRRRRRR i2 Z J < _ �j 1 1 1 1 1 111111111111111 W0 1 2 a a a a.a. a a a a a a a.n.a a.a a a a a 1 Z Z_ I.o G c7 `3 + 88 a8 J z = m RRRRRRRRRRRRRRRRRRRRR < W a I I I 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 X Y X X X O O W o J aaaaaaaaaaaaaaaaaaaaa c II- 852c,25� 8 $ 88 8 G d Z P— = a N RNin88 Qa .- 4000mlO 0 •> O- 2 0 O co W J J¢ ¢ ¢ ¢ J¢ 2 X Y Z . uonHUUHR u v < co s`9w 0 a -. c .. mU z c¢ O $ S1 $c z O O a & 38 8 _L 0co X c ¢ J - btZ < 2 0 U N U ¢ < f- ¢ COLU 2 w = O O al U CL M - are0M) Qm ¢m O O • • LU�ti - Ja.w00;:0 . S 0 >XVUVX►_-< iI<X >- >- viviw}-iwmZL5�aWWWWWWWWWW Lu Q �1I--¢w¢ OwOw ¢¢¢¢¢¢¢¢¢¢ J 22 U w�0 0 <<« ««« 00I-:LU1 _ W w_aaaaaaaaaa > 03 > ��0 0>F-¢a¢>co0)cn0)0)0) cococo • Z .••x co 01.-O> r co 0P co N N8 N N M s3 8 N M •t - - •'-- - --_ . O O t- W < z O Z cc < 0 CL n. J • REMODELING AND ADDITION, 1991 02831 VALLEY HOSPITAL & MEDICAL CENTER CHAIN LINK FENCES AND GATES Northwest Architectural Company, P.S . , 90057 • Page 1 1 2 3 SECTION 02831 - CHAIN LINK FENCES AND GATES 4 PART 1 - GENERAL 5 RELATED DOCUMENTS : 6 Drawings and general provisions of Contract, including General 7 and Supplementary Conditions and Division 1 Specification 8 Sections, apply to this Section. 9 SUMMARY: 10 This Section includes the following: 11 Galvanized steel chain link fence and gates. 12 SUBMITTALS : 13 General : Submit the following in accordance with Conditions of 14 Contract and Division 1 Specification Sections. 15 Product data in the form of manufacturer ' s technical data, 16 specifications, and installation instructions for fence and gate 17 posts, fabric, gates, and accessories. 18 Shop drawings showing location of fence, gates, each post,. and 19 details of post installation, extension arms, gate swing, 20 hardware, and accessories . • 21 QUALITY ASSURANCE: , 22 Single-Source Responsibility: Obtain chain link fences and gates 23 as complete units, including necessary erection accessories, 24 fittings, and fastenings from a single source or manufacturer. 25 PART 2 - PRODUCT 26 MANUFACTURERS : 27 Manufacturers: Subject to compliance with requirements , provide 28 products by one of the following: • • REMODELING AND ADDITION, 1991 02831 VALLEY HOSPITAL & MEDICAL CENTER CHAIN LINK FENCES AND GATES . Northwest Architectural Company, P. S . ; 90057 Page 2 1 Galvanized Steel Fencing and Fabric: 2 Allied Tube and Conduit Corp. • • 3 American Chain Link Fence Company 4 American Tube Company 5 Anchor Fence, Inc. - 6 Capitol Wire and Fence Co. , Inc. 7 Century Tube Corp. 8 . Cyclone Fence Div. /USX Corp. • 9 FABRIC: - 10 Selvage: Fabric 72 inches high and over shall be knuckled at one 11 selvage and twisted at the other . , 12 Steel Fabric : Comply with Chain Link Fence Manufacturers 13 Institute (CLFMI) Product Manual . Wire size includes zinc 14 coating. 15 Size: 2-inch mesh, 11-gage (0. 120-inch diameter) wire. 16 Galvanized Steel Finish: ASTM A 392 , Class 1 , with not less 17 than 1 . 2 oz. zinc per sq. ft . of uncoated wire surface. • 18 FRAMING: • 19 Strength requirements for posts and rails conforming to ASTM F 20 669 . 21 Pipe shall be straight , true to section, material , and sizes 22 specified, and shall conform to the following weights per foot : • 23 NPS in Outside Diameter Type I Type II '-- - 24 inches (OD) in inches Steel Steel Aluminum 25 1 1 . 315 1 . 68 - 1 . 35 - 0 .435 26 1-1/4 1 . 660 2 . 27 1 . 84 0. 786 • 27 1-1/2 ' 1 . 900 2 . 72 - 2 . 28 28 2 2 . 375 3 . 65 3 . 12 1 . 260 29 2-1/2 2 . 875 - 5 . 79 - 4 . 64 2 . 004 30 3 3 . 500 7. 58 5 .71 31 3-1/2 4 .000 9 . 11 6. 56 3 . 151 32 4 4 . 500 10 . 79 ---- 33 6 6. 625 18 . 97 ---- 6 . 564 34 8 8 . 625 28 . 55 ---- 9.878 35 _ Steel Framework, General : Posts, rails, braces, and gate frames. 36 Type I Pipe: Hot-dipped galvanized steel pipe conforming to 37 ASTM F 1083 , plain ends, standard weight (schedule 40) with 411 S • . REMODELING AND ADDITION, 1991 02831 VALLEY HOSPITAL & MEDICAL CENTER CHAIN LINK FENCES AND GATES Northwest Architectural Company, P.S . , 90057 Page 3 • 1 - not less than 1 .8 oz . zinc per sq. ft . of surface - area 2 coated. • 3 Type II Pipe: Manufactured from steel conforming to ASTM A 4 569 or A 446 , grade D, cold formed, electric welded with 5 minimum yield strength of 50,000 psi and triple coated with 6 minimum 0.9 oz. zinc per sq. ft. after welding, a chromate 7 conversion coating and a clear polymer overcoat. Corrosion 8 protection on inside surfaces shall protect the metal from • 9 • corrosion when subjected to the salt spray test of ASTM B 10 117 for 300 hours with the end point of 5 percent Red Rust. 11 C Section: Rolled form steel shapes conforming to ASTM F • 12 669 , group II produced from steel conforming to A 446, grade 13 D, or ASTM A 570, grade 45, cold formed, hot-dip galvanized 14 with minimum 2 .0 oz. zinc per sq. ft . of surface area 15 conforming to ASTM A 123 or ASTM A 525; or 5 percent 1-6 aluminum-mischmetal coated with minimum 1 .0 oz. coating per 17 sq. ft . of surface area each side conforming to ASTM A 875 . 18 H Section: Hot-rolled steel H shape with minimum yield 19 strength of 45,000 psi conforming to ASTM F 669 , group III 20 and hot-dip galvanized with minimum 2 .0 oz. zinc per sq. ft . 21 of surface area conforming to ASTM A 123 . 22 Square Tubing: Fabricated from steel -conforming to ASTM A 23 500, grade B and hot-dip galvanized with - minimum 2 .0 oz . 24 zinc per sq. ft . of surface area conforming to ASTM A 123 . -- 25 End, corner, and pull posts for following fabric heights : - • 26 Up to 6 feet : 2 .375-inch OD Type I or II steel pipe, 2-inch 27 square galvanized steel tubing weighing 2.. 60 lb. per lin. 28 ft. , or 3 . 5-inch by 3 .5-inch roll-formed sections weighing 29 4 . 85 lb. per lin. ft . 30 Line or intermediate posts for following fabric heights: 31 Up to 6 feet : 1 . 90-inch OD Type I or II• steel pipe, ' 1 . 875- 32 inch by 1 . 625-inch C section weighing 2 . 28 lb. per lin: ft . , 33 or 2 . 25-inch x 1 .70-inch galvanized steel H section weighing 34 3 . 26 lb. per lin. ft. 35 Gate Posts: Furnish posts for supporting single gate leaf, or 36 one leaf. of a double. gate installation, tor nominal gate.-widths 37 as follows: • - c> 38 Up to 6 feet : 2 . 875-inch OD Type I or II steel pipe, 2 . 50- 39 inch square galvanized steel tubing weighing 5. 10 lbs. per 40 lin. ft . , or 3 . 5-inch x 3 . 5-inch roll-formed' sections 41 weighing 4 . 85 lbs. per lin. ft . REMODELING AND ADDITION, 1991 02831 VALLEY HOSPITAL & MEDICAL CENTER CHAIN LINK FENCES AND GATES Northwest Architectural Company, P. S. , 90057 Page 4 1 Top Rail : Manufacturer ' s longest lengths, with expansion-type 2 couplings, approximately 6 inches long) for each joint . Provide, 3 means for attaching top rail securely to each gate corner, pull , 4 and end post . 5 FITTINGS AND ACCESSORIES: 6 Material : Comply with ASTM F 626. 'Mill-finished aluminum or 7 galvanized iron or steel, to suit manufacturer' s standards . . • 8 Zinc Coating: Unless specified otherwise, galvanize steel ' 9 _ - - fence. fittings and accessories in accordance with ASTM A 10 153, with zinc weights per Table I . 11 Tie Wires: 12-gage (0. 106-inch diameter) galvanized steel with a 12 minimum of 0. 80 oz. per sq. ft . of zinc coating of surface area 13 in accordance with ASTM A 641 , Class 3 or 9-gage (0 . 106-inch- 14 diameter) aluminum wire alloy 1100-H14 or equal , to match fabric 15 core material . 16 Post Brace Assembly: Manufacturer ' s standard adjustable brace at 17 end and gate posts and at both sides of corner and pull posts, . 18 with horizontal brace located at midheight of fabric. Use same 19 material as top rail for brace, and truss to line posts with 3/8- 20 inch-diameter -rod and adjustable tightener. Provide manufacturers 21_ standard galvanized steel or cast iron or cast aluminum cap for 22 each end. . 23 Bottom and Center Rail : Same material as top rail . Provide 24 manufacturer's standard galvanized steel or cast iron or cast 25 aluminum cap for each end. 26 Post and Line Caps: Provide weathertight closure cap for each 27 post . Provide line post caps with loop to receive tension wire or 28 - top rail . 29 Tension or Stretcher Bars: Hot-dip galvanized steel with minimum 30 length 2 inches less than full height of fabric, minimum cross- 31 section.. of 3/16 inch by 3/4 inch and minimum' 1 . 2 oz. zinc coating * 32 . per sq. ft. of surface area. Provide one bar for each gate and 33 end post , and two for -each corner and pull post, except where 34 fabric is integrally woven into post.• 35 Tension and Brace • Bands: Minimum 3/4-inch-wide hot-dip 36 galvanized steel with minimum 1 . 2 oz. zinc coating per sq. ft. of 37 surface area. 38 Tension Bands : Minimum 14 gage (0 .074 inch) thick. 39 . Tension and Brace Bands: Minimum 12 gage (0 . 105 inch) 40 thick. 411! 410 REMODELING AND ADDITION, 1991 02831 VALLEY HOSPITAL & MEDICAL CENTER CHAIN LINK FENCES AND GATES Northwest Architectural Company, P. S. , 90057 Page 5 1 Concrete: Provide concrete consisting of Portland cement, ASTM C 2 150, aggregates ASTM C 33, and clean water. Mix materials to 3 • obtain concrete with a minimum 28-day compressive strength of 4 2500 psi . Use at least 4 sacks of cement per cu. yd. , 1-inch 5 maximum size aggregate, maximum 3-inch slump, and 2 to 4 percent 6 entrained air. . 7 GATES : . 8 Fabrication: Fabricate perimeter frames of gates from metal and 9 finish to match fence framework. Assemble gate frames by 10 welding. Provide horizontal and vertical . members to ensure 11 proper gate operation and attachment of fabric, hardware, and 12 accessories. Space frame members maximum of 8 feet apart unless 13 otherwise indicated. 14 Provide same fabric as for fence unless otherwise indicated. 15 Install fabric with tension bars and bands at vertical edges 16 - and at top and bottom edges. 17 o Install diagonal cross-bracing consisting + f o 3/8-inch- 18 diameter adjustable-length trussrods on gates to ensure 19 frame rigidity without sag or twist . . 20 Swing Gates: Comply with ASTM F 900. 21 Steel : 22 . Up to 6 feet High and 3 feet -Wide: Fabricate perimeter 23 frames of minimum 1 . 660-inch OD Type I or II steel pipe 24 or 1 . 50-inch square galvanized steel tubing weighing 25 1 : 90 lb per sq ft . 26 Gate Hardware: Provide hardware and accessories for 27 each gate, galvanized per ASTM A 153 , and in accordance 28 with the following: 29 Hinges: Size and material to suit gate size, non- 30 lift-off type, offset to permit 180-deg, gate . 31 opening. 32Latch: Forked type or plunger-bar type to permit 33 ' operation from either side of gate, with padlock 34 - eye as integral part of latch. -~. - ---- 411- 410 REMODELING AND ADDITION, . 1991 02831 VALLEY HOSPITAL & MEDICAL CENTER CHAIN LINK FENCES AND GATES • Northwest Architectural Company, P.S . , 90057 Page 6 1 PART 3 - EXECUTION 2 INSTALLATION: 3 General : Install fence in compliance with ASTM F 567 . Do not 4 begin installation and erection before final grading is 5 completed, unless otherwise permitted. 6 Apply fabric to outside of framework. . 7 Excavation: Drill or hand-excavate (using . post-hole digger) . 8 holes for posts to diameters and spacings indicated, in firm, 9 undisturbed or compacted soil . 10 If not indicated on drawings, excavate holes for each post 11 to minimum diameter recommended by fence manufacturer, but 12 not less than 4 times largest cross-section of post . 13 Unless otherwise indicated, excavate hole depths 14 approximately 3 inches lower than post bottom, with bottom 15 - of posts set not less than 36 inches below finish grade 16 surface. 17 Setting Posts: Center and align posts in holes 3 inches above 18 bottom of excavation. Space maximum 10 feet o . c. , unless 19 otherwise indicated. 20 Protect portion of 'posts above ground from concrete 21 splatter . Place concrete around posts and vibrate or tamp 22 for consolidation. Check each post for vertical and top 23 alignment, and hold in position during placement • and 24 finishing operations. 25 Hold concrete footing below grade as .required to 26 accommodate the concrete mowing strip specified in 27 Section 02520 Concrete Curbs and Walls. 28 Top Rails: Run rail continuously through line post caps, bending 29 to radius for curved runs and at other posts terminating into 30 rail end attached to posts or post caps fabricated to receive 31 rail . Provide expansion couplings as recommended by fencing 32 manufacturer. 33 Bottom and Center Rails: Provide bottom rails for all fencing 34 and center rails where indicated. Install in one piece between 35 posts and flush with post on fabric side, using rail ends and 36 special offset fittings where necessary. 37 Brace Assemblies : Install braces so posts are plumb when 38 diagonal rod is under proper tension. All 411 REMODELING AND ADDITION, 1991 02831 VALLEY HOSPITAL & MEDICAL CENTER CHAIN LINK FENCES AND GATES Northwest Architectural Company, P. S . , 90057 Page 7 1 Fabric: Leave approximately 2 inches between finish grade and 2 bottom selvage unless otherwise indicated. Pull fabric taut and 3 tie to posts, rails, and tension wires. Install fabric on 4 security side of fence, and anchor to framework so that fabric 5 remains in tension after pulling force is released. 6 Tension or Stretcher Bars: Thread through or• clamp to fabric 4 7 inches o. c . , and secure to end, corner, pull, and gate posts with 8 tension bands spaced not over 15 inches o. c. 9 Tie Wires: Use U-shaped wire of proper length to secure fabric 10 firmly to posts and rails with ends twisted at least 2 full 11 turns. Bend ends of wire to minimize hazard to persons or 12 clothing. 13 Maximum Spacing: Tie fabric to line posts 12 inches o. c . 14 and to rails and braces 24 inches o.c. • 15 Fasteners : Install nuts for tension bands and hardware bolts on 16 side of fence opposite fabric side. Peen ends of bolts or score 17 threads to prevent removal of nuts . 18 Gates: Install gates plumb, level, and secure for full opening 19 without interference . Install ground-set items in concrete for 20 anchorage. Adjust hardware for smooth operation and lubricate 21 where necessary. 22 END OF SECTION 02831 I 0 N i - • FILES (ISo) E-LJS' EXIG"t• p..eLOGA12 1700R• PROVIDE New FRAME q RAD1OLOS`( eL C1 RoN,G OL-OSS REEF-T-ION __ 'p � Nf' 54) 2'_6,1i • _ ,1,c, New WALs _o T YP PF2.IN1 i �_� cA61 Nom_ L -J 1 - - PLA51-IG LAM. - I _ 21-o" -5HELVINS ON - HEAVY DU-The N ': - WALL STAND. cXIST1 ON -DeSi�- t 4, n!i P�F2AGKE iS Ra.GE, T GouNTE� � +� . 4-� _ / UI ir.W_ • iti I 4ii N ; EXIT /Ii�u I : v�-r . 1 I -NPI NS CED 0 1 < •� I / S.-1-LJ FZN .....1 , IiEw vert -� - __.... • ==�+ ,r, DESK CI N - FLOOF PLAN • -.„ • V,4.11 = 1'_0" • ADDt✓NDUM NO, ! &if A V,4 L L EY I fOS P I-1 AL s M E IGAL G c.V R .ioe N0.01005-7 4F ; / SPOKANE, WA, DRAWN SP•�I GA- I / 0, fZeV1910N� To F. -74E7101K�= b P'TN DATE 5•2 • 0 . • -Go0RDINAT5 SLAT IN Sloe op GA5IN1=7 RcMoVAI oP PAPEt2 -TRAY w/ cxie-i Pp.IN r 1D L-J �1I IIIFirP,DJ. SHI�LVIN6 4 WALL EfZAGKETB EXIST • r . 1 1 ___J,_ cA61NET- ,L g ' - I - , . ml k9I SPAGE -NI-N, . ir f 0 154 EAST . RSL oc•A-r—C I 0 G LOGS PfzINTERs- or gfPecL - P-ig("' -- N,I,c, _ �__ 1 1 1 , ?` — ADS .V i Ne d oPeN ) r.w-- J 1 J mai._L._ S-,c;4ET oII , - - - I -4 __- -- k— _ ._-< VN5a. SPACE• I. _ �f.---.. -- -I t-a DRAWER Ea. LIQ-3 , E-r�.1, • • 0 1E4 sou-n-4 . . 1,4.11 =__ 11_011 APDcNDUM NO- I I, w _(ALLaY NOSPITAL4 MED(CAL.GENTE2.,o6No.°ICt7 ',ri : F .-SPO AAN E, WA . DRAWN SrGf�.-2 G►�yt��ag -RVIeIO J To RADIOLOGY REC'cPTio`J DATE 5.24. I S • faoI!-al goDH . _ _ _ _.. ____ _ NEW FUEL-TANK .-- 4 PAD ` _ 1NKF� E1 G� �IN � INFPA"t . *-PIOVIDE PAIN MEOIG"L. —a _./ FL AMMA13'J / WoRDINS EI - �GO12,175 .. �— — — — -ADD ITION I x NO SMO -INS I L - - - - - - aL. -- ��_ Ncw cuRC3 7 _�-- L - PZEMOVE PoRT1ON OF jr, EXIST. Gu(Z.g 0 GONG. . 9'fEoc ."____1,. ..NEW LANDING w/ / PAMP .VOWN r/ r • 1-1 FUEL.-TAN PLAN - WE ,� • 1/S I1 = II-01! .4.-::-..,A; &1-c r, CHAIN !_N14 • T FEN�C &ATE . pPo\JIJE FAIN T�J -METAL_ -51CN v// W04D I NG N . - 11 PI-AM Mp.SLE No SMoi1-I No 11 . ... [ii ni [—I 2I • NEW rUi:L: TAN!�- PAP _ . , a _ . , .. . .N ex 16-1", EN GINE _ GENCRA,TofzB!...!IL.Dlto . 0 FUSL -TANK PL.A!NI -- c-,AT • .. -__ N I/III = 11,011 - _ --. _ _- ~----- . _ Arp.;OE---•-NrJLM No, i ,_ i,' w VA L.-L.-�Y {4O5 P IITA1_4 M rte!GOAL GE�e No. alooS7 ioq to ; / 5 POIAAN c, WA, DRAWN GP GA- J' _ / I1 F-e k1 iNe Fort FUSL_ -r-,Ari'4-5 DATE S'24.91 Ili Z� ERSL/¢"�YPE'' M . .• . ' • . , • . . • . . • G`( . 62, TET, WALL ONLY .. P A X • • --_-:.72-...L:It-E- -. • • . • -.moi .r1- — - LAERS 5/S i' YP ''x'' c� ',--.1....1 ::::i.::,--7,-----');- ,L. il AR uN� SE L j Ij cOLUMN - STA& cR' :� ,i I1 JOINT , TYP, , .4;' - 5"Tl✓EL i. i..,_. . •-T-.j•_•1•!�• -&L' t rn . STUDS@ Ia11o.G, ii . - _ = _ ^ L INTE.. IO, ��AL F!NISI• -- 1RE PRoTE-GTION EXT. WAL. L- ///1/ i////1/.////,.////./1. — extol-, WALL_ OR GO'.�L�MN _. 4 A �RS 5/8L' -rYPE "x"?• 89, A,i�:. r.:v mica-=- . 79 ! . ----- -- . ; JOINSr "7-(P,"7-(P,- STESL•GOLJMtN- 9se 5`rgUo, if r .j ,0 a i K-r�rO— \ AL L FIN15i . • i i ! , , „-/. ,i - 7 • r • • ---, • i .I t - 3 • s ----. ! ; , Ell I • • • ___________ _ . • : -7--- ---7._::::•Ii.' :11.7.1t4::.1 Li • vIA-1 .FIO E TIONG� 11.1 ,. _. ` ai•i o ,.WALL- oP COL.UMN -••, I ir • 311 _ I i-cm ___ 1 ••rr d , .i'1.-I. isI ty 1.,1. .!. •S/3'i TYP, i'? YP F,d, E?,. 5i - ° . ,I __.1 4 M-Ti.... .:I • PST 51 pcs op STEcL C L-uMN • °- --- -• •- 7 4 L.AYERs o/8!L T`A'PE i5cu •. .02 -1 -1 A'r et--1 .o= STccL_ co_u M i . • :I . • FF1PE P J-TCCTION 6 -1 NT WAIL . 9A 3 n= Li_au ApoeN9uNi No, I /f' A VALLE'1 HOSPITAL 4 MEDIG,AL c . ca.r 2 Joe i+a cio06-i 'pir : . SPoKAN , WA, DRAWN sP GA- 4 °Vag GATE 5'Z4'.91 - FIRE PRoT1=�TIof~ of C.01-.1-!H NS • I • Fab) . 1 11 1 0 ( 16 4 ) ii 0 %I: 15 4 0 OM AD CI H ffi( 156 )® O Ig 111111M2Mall1111111111111111 ■■■■r . ME I■ ' 11 ® 10'116i‘IIEE.1_ d r ■■� H.. �p.m ■■ .� o I.�1.�0 EIN11611gib. ..�l1■■1 U ■ .1.11111A4 _ WM MB IN cwsk le FIN 0 0 ...■■ .r.. 1.immargiso �� _�� a - InI6iLiIhi pa ■ ■■o�..:�■—.., ►_ ■ rasiciliorrris■■■ T�� _■ 161 ) 111815"11 ■ 1101016MIMSH FAIIMM II r • ti ` 4..-4 • 0 111 I . vagicar IL IRiQUIdR • 165 , ' & _ I Q. 6 1 1 :. 1 o 1 ® 'O1 ■ ■ • •.6.2 In 1 1163 • --- 1 ° am ��r.�4,01 ■ _ ■�kkJ- ■ ill ;--; . ■ Qi •_,_ o If 2J : . ■ Q I like ';■ ' - . DeLETe ccDED No-re *a ii i 0� 0_ Oma•E_I)N PAR"T'IA R IO�.oG'I' R�FrECT 7 ;LSI ?':...AN V511 =11_011 ADP57UH No, I r A vi4Lt...eY Ho$p,/IITAL 4 Mev1 +L G.=N-i cg. JQ Na.g003"1 /- A �.�� + j / SPOK•AN e, YVA. DRAWN S(� V/'1� I I/ SPRINKLc? i-; .AD -V161U' L6 ::: 5,2�r.c11 1- • • 12 GA. HANGER WIRE - • _ • NOTE: • • THIS DESIGN IS MINIMUM 3 TURNS BASED ON UBC • • • STANDARDS TO FACIUTATE INSTALLATION ON . 47-18 8" MAX 2 ADJACENT WALLS: • WALL CONNECTION TO STUD, CMU, OR CONCRETE • POP RIVET PERIMETER SECTION • WALL ANGLE WALL UNE /i. /Iris/i ' 4 ACOUSTICAL PANEL MAIN RUNNER OR CROSS TEE STRUCTURE ABOVE _ MECHANICAL FASTENER COMPRESSION POST 1. 1111. � 4 12 GA. SPLAY BRACE WIRES 90' FROM EACH OTHER • - - 45' FROM MAIN k CROSS TEES MAIN RUNNER LATERAL DESIGN CROSS TEE SUSPENDED CLG. DETAIL NOT TO SCALE • ADD� Di 4•4 ;moo. I ip' w VALLEY (400?ITAL 4 MCOICAL. GCN =2 Jos NO.(10°57 `,1 i i GPOKAN^ , WA. n DRAWN 5P GA-G P/ G�(LI NC SP-,AGE vGTj�(�. DATE 5.24-.91 S • MECHANICAL ADDENDUM VALLEY HOSPITAL MAY 22. 1991 PAGE 1 • The additions, omissions, clarifications, and corrections contained herein shall be made to Drawings and Specifications for the Project, and shall be included in scope of work and proposals to be submitted. References made below to Specifications and Drawings shall be used as a general guide only. Bidder shall determine the work affected by Addendum items. • MECHANICAL SPECIFICATIONS • • ' 15 010 1.01 A. 1. Change "Field verify tank size (approximately 750 gallons)" to "Tank size is • 2,000 gallons". 1.03 A. 1. Add "Or give verbal (telephone) notification to local Washington State Department of Ecology office within 5 working days of beginning tank • closure process". - 1.04 A. Add "If excavation zone assessment results in additional excavation being • required then the additional work shall be done under separate contract". B. Contractor shall contract Staley Oil Company (922-2700) to remove oil from existing underground tanks and store oil off site until new tanks have been installed and passed final inspection. The oil then shall be filled into the new tanks. If all existing oil cannot be placed in new tanks, the Owner shall pay the oil company directly for continuing storage cost on the remainder of the oil. C. The Owner shall provide oil and day tanks for oil during construction. 15021 • 1.02 A. 2. Approved Balancing Agency: Add "e. Maiani Construction Services". 15 090 3.01 Add "F. Any structural steel work shall be done -by an approved fabricator or special inspections are required under UBC Section 304 14(G). 15 176.r 1.01 A. "' Add "2. Obtain County permit for tank installations". -'_. 3.01 Add "C. Provide security and signage around tank installations during construction". . . • . 15 520 0 _ -. r 2.01 C. Add "6. All new fire sprinkler heads shall be fast response type". 15 575 DELETE. • • • MECHANICAL ADDENDUM • VALLEY HOSPITAL MAY 22. 1991 PAGE 2 DRAWINGS • Sheet M1.1 Plumbing Fixture Schedule: • 1. P.1 & P.2 - Faucet info should be "Sloan". 2. P.6-First P.6 in schedule should read P.3. Sink manufacturer should read "Elkay". 3. P.4 - Model number should read BCRR-15. Manufacturer should be "Elkay". 4. Add P.10 - Medical Prep. Sink, existing relocated, coordinate rough-in. 5. Add P.11 - Nourishment Station, existing relocated, coordinate rough-in. Sheet M3.1 1. Existing sprinkler heads shown as beginning relocated on architectural reflected ceiling plan shall be replaced with new fire sprinkler heads. (All new sprinkler heads shall be fast response type.) . Sheet M3.3 1. Provide fuel oil vent from new 300 gallon tank into boiler room and up through roof. Terminate vent 18" above roof. 2. Provide fuel oil vent for new 300 gallon tank at engine generator building. Run vent up side of main building and terminate 12" above roof parapet. 3. Delete all Halon fire protection systems in room 156, 157, 158, 159, 163 and 167. 4. Remove existing wet fire sprinkler heads and install new sprinkler heads where shown on architectural reflected ceiling plan, rooms 156, 1,57, 158, 159, 160, 163 . and 171. (All new sprinkler heads shall be fast response type.) • Sheet M4.1 • 1. Provide type 2 fire dampers in all new ceiling air outlets in rooms 100 to 119. -Sheet M5.1 1. Delete treated 4 x 4's for mounting of condensing units CU1 & 2. Mount and bolt condensing units on 18" high continuous steel curbs. Remove roof insulation at base of curb and bolt curb directly to roof decking. provide flashing around curbs and install roofing membrane to match existing on all curb surfaces for complete roof seal. • S • 411 MECHANICAL ADDENDUM VALLEY HOSPITAL MAY 22. 1991 PAGE 3 Sheet M7.1 1. Delete "Halon Fire Protection System interlocks with Air Systems". 2. AC-1 and AC-2 shall have automatic shut-down in case of fire under Division 16. . ACCEPTANCE OF SUBSTITUTIONS Add the following to accepted list of manufacturers at this time. This is an acceptance of quality only. No attempt has been made to check each item as to special features, capacities or physical dimensions especially required by this project. It shall be the responsibility of supplier, manufacturer and Contractor to check all requirements before submitting for final approval. Final approval of exact features, sizes, capacities, etc., all of which must match equipment and materials indicated/specified, will be determined when submitting shop drawings for approval during construction period. Section Item Manufacturer 15 050; 2.01 Pipe Hangers PHD Manufacturing, Inc. 15 730; 2.01 Constant Volume Terminal Units Tuttle & Bailey 15 800; 2.02 Medium Velocity Duct &.Fittings Metco, Inc. 15 811; 2.01 Fire Dampers Ruskin 15 840; 2.02 Grilles, Registers & Diffusers Tuttle & Bailey - 2.04 • 40 S 1rthwest / V dun West 1203 Riverside.Spokane, Washington 99201 509-838-8240 FAX 509-838-8261 ,U `�� f.a'4 y 1'.S. OfJkra in Spokane and Seattle PRE-BID CONFERENCE • • PROJECT: Valley Hospital and Medical Center PROJECT NO.: 90057-1Ba DATE: May 21, 1991 • IN ATTENDANCE: Kurt Nierenberg, Pro Heating&Air Conditioning James B. Picken, Riley Engineering Todd Harnetiaux, Lydig Construction, Inc. • Robert Askins, Shea Construction, Inc. Don Davey, Arc Electric Bert Pickel, Spokane Concrete Cutting Al Eberhardt, Grinnell Fire Protection Greg Ripley, Ripley's Plumbing, Inc. . Dan Rude, C &R Plumbing Glen Pollock, McClintock&Turk Don McIntosh, SMK Mechanical • Terry Goebel, R.B. Goebel, General Contracting Inc. Tony Bishop, Bouten Construction McIntosh Waffle Libby, Rainbow Electric -- Peter Smith, Associated Construction, Inc. Tom Fox, Valley Hospital and Medical Center Don Evans, Doyle Engineering Steve Piscitello, Northwest Architectural Company • The following is a summary of the major items that were discussed during the conference meeting: 1. Steve Piscitello gave a brief overview of the scope of the project along.with the identification of the areas that are to receive first priority in the construction schedule. 2. Addendum No. 1 will be issued on Friday, May 24, and should be received by all planholders by early next week. 3. Jim Picken, the mechanical engineer for Riley Engineering, reviewed certain mechanical items that will be incorporated into the Addendum: •'*' a. The halon fire protection system will be deleted and replaced with a wet sprinkler system with quick response sprinkler heads. . b. The two fuel tanks being removed will have the fuel oil drained, stored off site and refilled by Staley Oil (922-2700) for a fee. The owner will pay for this service. • llrnreE. Blarknrrr.A/�l Dale S. Brookir..41.4 Richard E. Cook.PE Robert J. Gros.,nan.A/A .i.Frrd'hingr..A/A StrrrnJ. .41.4 B.wwa A..\'i.•hrn.A/A B. .41.1 Gregory/. Stark Senior.4 soon t, : Cohn R.Jo,us. CS!. William.41.Podohnrk.A1A i Pre-Bid Conference Valley Hospital and Medical Center, 90057 - lAb May 21, 1991 Page 2 • c. Tom Fox asked about a credit for the fuel oil not refilled in the new tanks, as the new tanks are smaller than the existing ones. Picken will contact Staley Oil. • d. Picken indicated the Specifications address what is to be done if the soil surrounding the fuel tanks is contaminated. The question was asked regarding liability if the fuel oil company spills oil while draining the tank. This should be the responsibility of the fuel oil company. • • e. Fox indicated the hospital will provide the temporary fuel to operate the emergency generators • during the transition period. f. Fox also dictated that a "paper trail" should follow the removal and disposal of the fuel tanks for ��.-- liability reasons. The fuel tanks should be destroyed and not resold. 4. Piscitello asked Fox about any requirements for the removal of asbestos. Fox indicated that all asbestos has been removed under prior contracts. 5. The owner has paid a plan review fee of $1,924.33 to the County. The contractor must reimburse this amount to the owner, as called for in the Specifications. 6. Fox will identify an area on the hospital site that can be used as a staging area by the contractor. In addition, a small amount of parking spaces will be provided. 7. A question was asked about the complexity of installation of the equipment that has been identified as "Owner Furnished - Contractor Installed". Fox will identify any equipment that is unusual or out of the ordinary. 8. Under Specification Section 13091, X-Ray Protection, the paragraph on "Single Source Responsibility" was questioned. The consensus was that this requirement will be more costly to the owner. This will be addressed in the Addendum. • 9. A second site visit for interested parties will occur on Friday, May 31, at 10:00 a:m. Meet in the main lobby. • 10. .Fox indicated he will provide a location within the hospital for the storage of items to be salvaged for the owner. 11.,; There;was a lengthy discussion on the interruption of existing HVAC, medical gases, power, sprinkler lines, and other services during the tie-in of the new work. T Fox confirmed what is already called for in the Specifications with regards to coordinating shut-down of services with his department. Fox stressed that any shut-down of services for an extended period of time could not be tolerated. - 12. Fox indicated that an air balancing of the entire hospital will occur after this project is complete but that each remodeled area should be balanced now under this contract. ; , . I i Pre-Bid Conference Valley Hospital and Medical Center, 90057 - lAb May 21, 1991 . Page 3 13. A question was asked about the calendar days for completion of work on the proposal form and about liquidated damages. There are no liquidated damages and the contractor needs to fill in the blank number of days to complete the project. While the owner is anxious to have the project completed as quickly as possible, no completion date has been established. . This concluded the Pre-Bid Conference meeting. Upon adjournment, the attendees toured the facility to view the areas being affected by the remodel. • Submitted by Steven Piscitello, AIA8p . cc: Planholders • Ben Nielsen, Northwest Architectural Company • kp/PBC52191