REMODELING AND ADDITION, 1991 ADDENDUM NO. 1
VALLEY HOSPITAL & MEDICAL CENTER May 24 , 1991
Northwest Architectural Company, P.S. , 90057 Page 1
This Addendum is hereby made a part of the Contract Documents to
the same extent as though it were originally included therein.
ARCHITECTURAL/STRUCTURAL
SPECIFICATIONS :
SUPPLEMENTARY INSTRUCTIONS TO BIDDERS, Page 1 , Line 21 :
ADD: "Robert B. Goebel , General Contracting, Inc. "
SECTION 01010, SUMMARY OF WORK, Page 1 , Line 28 :
ADD: "The Medical Records Department addition must ' be
complete, with the Owner able to occupy the space, before
work on the Outpatient and SAC Department can begin. "
SECTION 02831 , CHAIN LINK FENCES AND GATES:
ADD: Entire section as attached.
SECTION 06100, .ROUGH CARPENTRY, Page 1 , Line 49 :
CHANGE: "Where wood is required to have fire-retardant
treatment . . . " TO "All wood is required to have fire-
retardant treatment . . . "
SECTION 07250, SPRAYED-ON FIREPROOFING, Line 7 :
ADD: "Repair or replace fireproofing in Radiology suite
where new structural framing disturbs fireproofing around
existing structural members . "
SECTION 10010, MISCELLANEOUS SPECIALTIES, Page 2 , Line 37 : •
ADD: "Revolving Darkroom Door: Shall be Speedmatic by
ESECO, Model 2W28 , Cat . No. 9010, color as selected. "
SECTION 13091 , X-RAY PROTECTION, Page 1 , Line 37-40 :
DELETE: Reference to "single source responsibility" .
DRAWINGS:
SHEET A2 . 2 :
• REMOVE: Notation "limits of contract to extend 8 ' -0" beyond •
the foundation of the new addition. "
REMOVE: Portion of existing curb as shown on attached
Drawing CA-3 .
•
SHEET A2 . 3 : -
MOVE Door 119 to east wall of .Room 119 and provide 18" clear
on strike side of door.
•
• 411 - i
REMODELING AND ADDITION, 1991 ADDENDUM NO. 1
VALLEY HOSPITAL & MEDICAL CENTER May 24, 1991
Northwest Architectural Company, P. S . , 90057 Page 2
•
In Room 121 , MOVE floor sink 3 ' -0" to the east to provide
clearance by strike side of Door 121 .
Under wall types, Types 11 and 12 , MOVE "vapor barrier" to
follow "R-19 batt insul . "
Under wall types, Type 11 , CHANGE 6" metal studs to 8" metal
studs:
SHEET A2 .4 :
Under wall types, Types 11 and 12 , MOVE "vapor barrier" to
•
follow "R-19 matt insul . "
At Door 172 , PROVIDE a landing 44" in length and from north
wall of Room 172 to strike side of door in width. Provide a
3 '-0" long ramp down for 2-1/2" drop on the west and south
side of landing. See attached Drawing CA-3 .
In Room 172 , VERIFY mobile file track dimensions with mobile
file supplier.
LOCATE wall between Rooms 152 and 153 , 13 ' -0" from face of
finish of south wall of Room 152 to face of finish of new
•
wall .
PROVIDE revised casework, floor finishes and door location
for Office 154 as shown on attached drawings CA-1 and CA-2 .
In Room 156 and 163 , at existing walls with electrical
outlets and other .penetrations that will receive new lead-
lined gypsum board over existing wall finish, BREAK away
enough of existing wall around penetration to glue lead
liner behind object in wall .
PROVIDE 6 ' -0" chain link fence and gate at new fuel tanks as
shown on attached Drawing CA-3 .
Under wall types; Type 11 , CHANGE 6" metal studs to 8" metal
studs.
SHEET A2 . 5 :
PROVIDE horizontal blinds on exterior windows in Rooms 170
and 171 .
SHEET A3 . 1 :
Under Door & Relite Schedule, at Door 151 , CHANGE door type
to Type "B" .
Under Room Finish Schedule, at Room 154 , CHANGE flooring
finish to "VCT" . CHANGE flooring color to "V5" . CHANGE
base color to R2" . ADD to remarks column "Partial VCT floor
to match existing" .
411 411
9 ►
REMODELING AND ADDITION, 1991 ADDENDUM NO . 1
VALLEY HOSPITAL & MEDICAL CENTER May 24 , 1991
Northwest Architectural Company, P. S . , 90057 Page 3
Under Color & Finish Notes, under vinyl composition tile,
ADD "V5 - match existing" .
Under Color & Finish Notes, under rubber base, ADD "R2 -
match existing" .
Under Color & Finish Notes, under wallcovering border/W4 ,
RELOCATE "rigid vinyl wallcovering" to the left to form
separate heading.
Under frame types, at Type "D" , CHANGE height to 3 ' -4-" and
width to 5 ' -0" .
Under "Abbreviations" at "ATGB" , CHANGE to read "ATGB
acoustical tile on ( 1 ) layer 5/8" Type X Gyp. Bd. ( 12" x 12"
w/vinyl - plastic finish) . "
SHEET 4 . 1 :
At Details 1/A4 . 1 through 4/A4 . 1 , CHANGE 6" stl . studs to 8"
stl. studs.
At Detail 1/A4 . 1 , ADD note "sprayed-on fireproofing"
indication to underside of metal deck and face of structural
framing.
At south and west elevations, ADD
"Paint in color to be selected" to note
"Align 4" channel screed with existing, typ. " -
SHEET A6 . 1 :
At Elevation 19 , CHANGE 2 ' -0" dimension to 5 ' -0" .
At Elevation 31 , RAISE top of P-lam counter to 3_' -4" .
SHEET A6 . 2 :
Under washroom fixture schedule, CHANGE item "Toilet paper
dispenser" to be "OFOI" . Item "CT room services" to be
•
"OFCI" .
SHEET A6. 3 :
At Details 8/A6 .3 and 9/A6. 3 , REVISE as shown on attached
Drawing CA-4 .
SHEET A7. 2 :
REVISE sprinkler head locations in Rooms 156, 157 , 158 , 159 ,
160, 163 , and 166 as shown on attached Drawing CA-5 .
PROVIDE suspended ceiling brace wires as shown on attached
Drawing CA-6.
SHEET S2 . 2 :
ADD: Entire sheet as attached.
4111
•
REMODELING AND ADDITION, 1991 ADDENDUM NO. 1
VALLEY HOSPITAL & MEDICAL CENTER May 24 , 1991
Northwest Architectural Company_, P. S. , 90057
G.E. Medical Systems drawings for Cath Lab, Cover Sheet, A. 1 ,
S. 1 , E. 1 , E. 2 and D. 1 are attached.
Meeting minutes from Pre-Bid Conference are attached.
END OF ADDENDUM
N3
N C
. is , ,
® -.J -_=-1 IL \
RECEPT. & TELEPHONE OUTLET
BELOW COUNTER TOP. PROVIDE
GROMMETED HOLES FOR POWER •
AND TELEPHONE CORDS.
k
t i t
,....,_ . .
_ EXISTING -r
E' ►. T., ; ....• 1.: . CLOCK
RELOCATED
i i
E i 1
'1
E A ' Ler 4 I
Q • €... .; i ei-�'� T i i- I
TO 2(1 P20A)
EXISTING SPARE
BKRS PNL 'IN4'
•
• n ; � a . I •
. Arm".
411110iM
® ,_ —
co 1
r=" li i
. ,I ,
ROOM 154 - RADIOLOGY RECEPTION
SCALE: 1/g = 1'-0r ADDENDUM #1 May 24, 1991
VALLEY HOSPITAL & MEDICAL CENTER
REMODELING & ADDITIONS, 1991
VALLEY HOSPITAL & MEDICAL CENTER,90057 ADDENDUM #1
Northwest Architectural Company. P.S. Page 1
SPECIFICATIONS
•
Section 16760 - Nurse Call System
System is Executone System and no substitutions will be allowed.
Section 16761 - Intercom System
Delete entire section and replace with Section 16761 - Overhead Paging/Music System.
•
PANEL SCHEDULES
Delete panels CRX, BN3 and BN4 and replace with new panel schedules.
Insert new panel schedule A3.
DRAWINGS
Drawing E1.1
System note 4 - Delete paragraph for device boxes and replace with:
•
"electrical contractor shall verify all nurse call box sizes with equipment
supplier".
Drawing E2.1
Room 111 - Add two Type 15 fixtures with a 600W dimmer mounted next to door.
Circuit to lighting circuit serving this room.
Drawing E2.2
Room 117 - Provide 120 volt AC door closure relay from receptacle circuit B-26.
Drawing E3.1 •
Rooms 158 and 157 - J-boxes shown without call outs are for lighting interconnection
for foot switch control from X-ray table. Coordinate exact requirements with GEMS and
hospital personnel.
S S
REMODELING & ADDITIONS, 1991
VALLEY HOSPITAL & MEDICAL CENTER,90057 ADDENDUM #1
Northwest Architectural Company. P.S. Page 2
• Drawing E3.2
Room 159 - Delete magnetic door holder. Replaced with a door closure provided by
others. Electrical contractor shall provide relay, 120 volt AL from receptacle circuit
BN4-9 and interlock to fire alarm system.
•
Room 152 - Provide 120 volt AC to door closure relay from receptacle circuit BN-24.
Room 156 - Provide telephone/computer outlet above counter on north wall. See
architectural elevations for location. •
-
Room 154 - See attached drawing showing electrical revisions.
Add duct smoke detectors and shut down relays to AC-1 and AC-2. Interconnect to fire
alarm system as required by Simplex Fire Alarm Company.
Drawing E4.1 C.T. Lab Power Plan
Change note 12 wall duct from 3"x14" to 3"x12".
Add the paragraph to note 17:
"120 volt AC 2#12, 1#12G, 3/4"C from panel CRX circuit CRX-12".
Drawing E4.2
New drawing dated 5/24/91. •
• Drawing E5.1
Remove existing drawing dated 4/26/91 and replace with new drawing dated 5/24/91.
•
REMODELING & ADDITIONS, 1991 16761
VALLEY HOSPITAL & MEDICAL CENTER,90057 PAGING/MUSIC SYS.
Northwest Architectural Company.. P.S. Page 1
PART ONE - GENERAL
RELATED DOCUMENTS
Drawings and General provisions of contract, including general and supplementary conditions
and Division-1 specifications sections apply to work of this section.
•
REQUIREMENTS
The contractor shall furnish and install all equipment, accessories, and materials necessary for
the extension of the existing intercom system in accordance with this specification and applicable
drawings. •
The equipment furnished under this specification shall be the standard product manufactured to
match the existing system equipment manufacturer.
All components and the system as a whole shall meet or exceed the minimum standards issued
by the EIA. All work in conjunction with this installation shall meet the provisions of the
National Electrical Code.
Each major component shall bear the manufacturer's name, catalog number and UL label.
SYSTEM DESCRIPTION
Overhead Paging/Music system is existing. Electrical contractor shall provide and install the
following items:
Ceiling speaker to match existing - •
Volume control wall mount to match existing
Signal/Intercom cable to match existing
PART THREE - EXECUTION
INSTALLATION
The contractor shall install the overhead paging/music system in conduit to all locations shown
and as required by the equipment manufacturer.
Provide all backboxes,junction boxes, faceplates, etc., as necessary for a complete installation.
END OF SECTION 16761
it .
0
•
. . .
•
.
.
.
. O
. pN c�pp Cp NNa��{ t�pp
s z N"fiDaDON< tCaDNNXRV, 8 ` X8
• .
2
w
Z E
0 co d
I CC
-J 0
W U
CO J Z -, W
w w a Z3
a•gq25 5T
v- U UW
U>- Z W W W W W W W W W W W W
El it 6 61_aaaaaana.a1aaaa co
fix= 2Uop0)CO000OV) NtnfnCOV) u) - a. .
opp CCpCpppOp CpCp i/
N M U O O W §O O EN N 0 8 8 8 o 8 f 0 0 ' g
} Z Q v.v D Y o 0 0 0 0 0 o c p
d o 0 Q J r
Z N z
O 1- y1- m FIRS RRRRRRRRRRRRRR
Z J < et U III 11111111111111
E o xO. N aa.a N a a a aO. a a a a a a a a a a @ I
Z • ¢g 0 eie
S w a
0 m
C9 00 = m
RRRRR RRRRRRRRRRRR �a8 $ E81. -J 0
W 0 11111 I I I i l l l l l i t l xRCxxrx i �. <
J 00 M LL ^-.-a N a a a a a a a a a a a a '
o 5 88c O O
00 a ( ? a �� � � ,-cCicCiNN Qa' 000000 10 0
(IL., (7 =
> o
2
• 0O 0W • J[c2IY Z
II 11 II U II U U U II
o <
3-o 2
"59 w
o � 0 c 2 o U
• -'01A o m., W
131- $v Z
z = 80x2 . z
O a1 38
L x c J
E be <
V N O
cow F.
<0 0 W LC ,
0 - LUa E w w
O o t� U 0 • •
WtnW �Er c0ZZZZIli LIJ C) CD CD 0 WWWWWwW
J x CSC3h D>-J - -
>• 0 I J10_S m2SSimcococ)u)coco •
Z .-0) 1.0PO) �t71fJP0) NNNNMCO 1.0
-, W @ Z `
O Z 0
CC < 0
G. J
A
_ .( 0
• I
m
a
'
()
N N'V (I)
• z
O
• (r Ir
0 O
w ad
0 w
0 •
2 2 N
3¢v
gam¢ .
0w
a
0 0 0 w m il
0 '' 888 088888"388 m r)
(V w -N r 0 a> 0 0 0 0 0 N O O N N
2, O 11 0 r
6 2,Z N Z 0
y W .. O <
z � acr � RER
2 >• n=. CO aaa e 0
w I a
O
Z = m Nop pQ0NQC J
w U � °
o O n a.aai XXXX
2 I- O
w Q = J r r r O I
H J
O en Z
O Z 888 888888 8 S.
C a Q Z ¢ N r N 0 a C G C O O N I O cj
220 > o?
•
UO 0w Q JCC2IX z
NONNIUUNK
t
m
90
9
si
.mC ` mV
tiQQ coaLo $o
Z
0 �OJc Z
&1
O
L XCC
N
al I-
N 0
J Ir w
< I-' 0
CO LLI W CO W
U `5
= 0 m a a 2
iO_ M www
fi 0 mC�m
> a cg 1_I .
Z —loan
O
w iz:< : Z
OZ U
Cr < O
a d J -
• ill . .
0
.
.
•
• O
Z
01
• N1ra3C° ONNNAMgi ppNN pp8oo
sr•
.
•
1 '
Z
0L_
t
co cc
Ili
w
0 a
O •
• NN0NNN0ANC) •
g
C)C)() C)C.) C) U C) C.)
4a4a4aa6a •
�b.�b.b.b.b.�biLWWWWWWwwWwww
WWWwwwwww¢¢ ¢¢¢¢¢¢ ¢¢
C.)C.) UC)C) C) c�C)C) QacEaaaaaa4Ea4
www www wWan.a.CLdaaaaC/) ) a
00 0W e¢ta¢fp¢¢¢CCCCCC8 roc cccncc
CV CO CDCDg �0i � CD CD CDtAN 0 (88i8882i_ 88 A 1N7
w 0 0 0 0 0 0 df
• >- Z > O N to
ZN Z 0
g a
z JQI- m RRRRRRRRRRRRRRRRRRRRR i
wE >= 2 a a a a a a CL a CL a a a a a a as a n.a.CL
LI Z g 0 '5 UJ n.
15 UJ 2
z oS m RRRRRRRRRRRSRR 8 04< gg $ ` < ac
w Cn o iiiIiiiiiiiiii I xRxx .sx 2 0 `O
CD I � aaaaaaaaaaaaaa n
O 0) ZZ §ERP- § § § RE § mE §?^ Qa Eri 8882 , Eto
Q O J.
00 0 W ¢¢¢¢¢ ¢¢¢CL¢¢ Z J¢ JCL2 =Y Z •
HUHUNDUHU
o a
. ...3
. �� c „'2 C 0
... CB CV eicoW
1:1 rL a
Z• _ J �� 5Z0 $ o O
• I
- x c J
W ae z
W H
N- O LIJZCC5 ,
SS¢
a. cncoco cncncococncncncnQ4S ~
• 0 220 �,
CO UUUUUUUUUUUZZ6 z
o as a a 4'a a4 a as
>' ¢ riLLLLLLtt�tFF►= m
J O WWWWWWWWWWW�a„<� . w _ __
J c•) U C)C) C)C)U C) U U C) C.)C) Z
W W W W W W W W W W W V U U ,• . a ,
Z W ¢¢¢¢¢¢¢¢¢¢¢D 25 C a -
> m ct t� pf t� t[� _
Z .-c7N t. Of .- 1747 n CA N N N N N M c7 c7 Mc 07 Q
O
-I W < Z •
O Z U
¢ < 0
an. J
•
III, tik .
•
•
•
• O
• Z -
•
•
N� co0OpSiNtNSp Sy e8Sp p?
•
•
z
0
idwSJ
E a
O <UU ¢ W 5
�QQw8 U)coco co coco0co
• 222uU 2i
Ow0 <aaoaSi«a
• aa tttht ttititiwwwwww .
Y Y Y W w W W W W W W W¢¢¢¢¢¢ •
CC ' www'"Lu uiwaaaaaaa N
D O O U)u. ¢¢¢Z¢Q¢cL¢co co co co co co a.
0o ow 2 cG¢¢¢¢¢ ¢¢
>-(S o Z > W O
0
Z N Z
CO � Nx m RRRRB RRRRRRRRRRRRRRR i2
Z J < _ �j 1 1 1 1 1 111111111111111
W0 1 2 a a a a.a. a a a a a a a.n.a a.a a a a a 1 Z
Z_ I.o G
c7 `3 + 88 a8 J
z = m RRRRRRRRRRRRRRRRRRRRR <
W a I I I 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 X Y X X X O O
W o J aaaaaaaaaaaaaaaaaaaaa c II-
852c,25� 8 $ 88 8
G d Z P—
= a N RNin88 Qa .- 4000mlO
0 •> O-
2
0 O co W J J¢ ¢ ¢ ¢ J¢ 2 X Y Z
. uonHUUHR u
v <
co
s`9w
0
a -. c .. mU
z c¢ O $ S1 $c z
O O a & 38 8
_L 0co
X c
¢ J - btZ <
2 0 U N
U ¢ < f-
¢ COLU 2 w
= O O al
U
CL M - are0M) Qm ¢m
O O • • LU�ti -
Ja.w00;:0 .
S 0 >XVUVX►_-< iI<X
>- >- viviw}-iwmZL5�aWWWWWWWWWW
Lu Q �1I--¢w¢ OwOw ¢¢¢¢¢¢¢¢¢¢
J 22 U w�0 0 <<« «««
00I-:LU1 _ W w_aaaaaaaaaa
> 03 > ��0 0>F-¢a¢>co0)cn0)0)0) cococo
• Z .••x co 01.-O> r co 0P co N N8 N N M s3 8 N M •t - - •'-- - --_ .
O
O
t- W < z
O Z
cc < 0
CL n. J
•
REMODELING AND ADDITION, 1991 02831
VALLEY HOSPITAL & MEDICAL CENTER CHAIN LINK FENCES AND GATES
Northwest Architectural Company, P.S . , 90057 • Page 1
1
2
3 SECTION 02831 - CHAIN LINK FENCES AND GATES
4 PART 1 - GENERAL
5 RELATED DOCUMENTS :
6 Drawings and general provisions of Contract, including General
7 and Supplementary Conditions and Division 1 Specification
8 Sections, apply to this Section.
9 SUMMARY:
10 This Section includes the following:
11 Galvanized steel chain link fence and gates.
12 SUBMITTALS :
13 General : Submit the following in accordance with Conditions of
14 Contract and Division 1 Specification Sections.
15 Product data in the form of manufacturer ' s technical data,
16 specifications, and installation instructions for fence and gate
17 posts, fabric, gates, and accessories.
18 Shop drawings showing location of fence, gates, each post,. and
19 details of post installation, extension arms, gate swing,
20 hardware, and accessories .
•
21 QUALITY ASSURANCE: ,
22 Single-Source Responsibility: Obtain chain link fences and gates
23 as complete units, including necessary erection accessories,
24 fittings, and fastenings from a single source or manufacturer.
25 PART 2 - PRODUCT
26 MANUFACTURERS :
27 Manufacturers: Subject to compliance with requirements , provide
28 products by one of the following:
•
•
REMODELING AND ADDITION, 1991 02831
VALLEY HOSPITAL & MEDICAL CENTER CHAIN LINK FENCES AND GATES .
Northwest Architectural Company, P. S . ; 90057 Page 2
1 Galvanized Steel Fencing and Fabric:
2 Allied Tube and Conduit Corp. •
•
3 American Chain Link Fence Company
4 American Tube Company
5 Anchor Fence, Inc. -
6 Capitol Wire and Fence Co. , Inc.
7 Century Tube Corp.
8 . Cyclone Fence Div. /USX Corp.
• 9 FABRIC: -
10 Selvage: Fabric 72 inches high and over shall be knuckled at one
11 selvage and twisted at the other . ,
12 Steel Fabric : Comply with Chain Link Fence Manufacturers
13 Institute (CLFMI) Product Manual . Wire size includes zinc
14 coating.
15 Size: 2-inch mesh, 11-gage (0. 120-inch diameter) wire.
16 Galvanized Steel Finish: ASTM A 392 , Class 1 , with not less
17 than 1 . 2 oz. zinc per sq. ft . of uncoated wire surface.
•
18 FRAMING: •
19 Strength requirements for posts and rails conforming to ASTM F
20 669 .
21 Pipe shall be straight , true to section, material , and sizes
22 specified, and shall conform to the following weights per foot :
•
23 NPS in Outside Diameter Type I Type II '-- -
24 inches (OD) in inches Steel Steel Aluminum
25 1 1 . 315 1 . 68 - 1 . 35 - 0 .435
26 1-1/4 1 . 660 2 . 27 1 . 84 0. 786
•
27 1-1/2 ' 1 . 900 2 . 72 - 2 . 28
28 2 2 . 375 3 . 65 3 . 12 1 . 260
29 2-1/2 2 . 875 - 5 . 79 - 4 . 64 2 . 004
30 3 3 . 500 7. 58 5 .71
31 3-1/2 4 .000 9 . 11 6. 56 3 . 151
32 4 4 . 500 10 . 79 ----
33 6 6. 625 18 . 97 ---- 6 . 564
34 8 8 . 625 28 . 55 ---- 9.878
35 _ Steel Framework, General : Posts, rails, braces, and gate frames.
36 Type I Pipe: Hot-dipped galvanized steel pipe conforming to
37 ASTM F 1083 , plain ends, standard weight (schedule 40) with
411 S
•
. REMODELING AND ADDITION, 1991 02831
VALLEY HOSPITAL & MEDICAL CENTER CHAIN LINK FENCES AND GATES
Northwest Architectural Company, P.S . , 90057 Page 3
• 1 - not less than 1 .8 oz . zinc per sq. ft . of surface - area
2 coated.
• 3 Type II Pipe: Manufactured from steel conforming to ASTM A
4 569 or A 446 , grade D, cold formed, electric welded with
5 minimum yield strength of 50,000 psi and triple coated with
6 minimum 0.9 oz. zinc per sq. ft. after welding, a chromate
7 conversion coating and a clear polymer overcoat. Corrosion
8 protection on inside surfaces shall protect the metal from
• 9 • corrosion when subjected to the salt spray test of ASTM B
10 117 for 300 hours with the end point of 5 percent Red Rust.
11 C Section: Rolled form steel shapes conforming to ASTM F
•
12 669 , group II produced from steel conforming to A 446, grade
13 D, or ASTM A 570, grade 45, cold formed, hot-dip galvanized
14 with minimum 2 .0 oz. zinc per sq. ft . of surface area
15 conforming to ASTM A 123 or ASTM A 525; or 5 percent
1-6 aluminum-mischmetal coated with minimum 1 .0 oz. coating per
17 sq. ft . of surface area each side conforming to ASTM A 875 .
18 H Section: Hot-rolled steel H shape with minimum yield
19 strength of 45,000 psi conforming to ASTM F 669 , group III
20 and hot-dip galvanized with minimum 2 .0 oz. zinc per sq. ft .
21 of surface area conforming to ASTM A 123 .
22 Square Tubing: Fabricated from steel -conforming to ASTM A
23 500, grade B and hot-dip galvanized with - minimum 2 .0 oz .
24 zinc per sq. ft . of surface area conforming to ASTM A 123 . --
25 End, corner, and pull posts for following fabric heights : - •
26 Up to 6 feet : 2 .375-inch OD Type I or II steel pipe, 2-inch
27 square galvanized steel tubing weighing 2.. 60 lb. per lin.
28 ft. , or 3 . 5-inch by 3 .5-inch roll-formed sections weighing
29 4 . 85 lb. per lin. ft .
30 Line or intermediate posts for following fabric heights:
31 Up to 6 feet : 1 . 90-inch OD Type I or II• steel pipe, ' 1 . 875-
32 inch by 1 . 625-inch C section weighing 2 . 28 lb. per lin: ft . ,
33 or 2 . 25-inch x 1 .70-inch galvanized steel H section weighing
34 3 . 26 lb. per lin. ft.
35 Gate Posts: Furnish posts for supporting single gate leaf, or
36 one leaf. of a double. gate installation, tor nominal gate.-widths
37 as follows: •
-
c>
38 Up to 6 feet : 2 . 875-inch OD Type I or II steel pipe, 2 . 50-
39 inch square galvanized steel tubing weighing 5. 10 lbs. per
40 lin. ft . , or 3 . 5-inch x 3 . 5-inch roll-formed' sections
41 weighing 4 . 85 lbs. per lin. ft .
REMODELING AND ADDITION, 1991 02831
VALLEY HOSPITAL & MEDICAL CENTER CHAIN LINK FENCES AND GATES
Northwest Architectural Company, P. S. , 90057 Page 4
1 Top Rail : Manufacturer ' s longest lengths, with expansion-type
2 couplings, approximately 6 inches long) for each joint . Provide,
3 means for attaching top rail securely to each gate corner, pull ,
4 and end post .
5 FITTINGS AND ACCESSORIES:
6 Material : Comply with ASTM F 626. 'Mill-finished aluminum or
7 galvanized iron or steel, to suit manufacturer' s standards . .
•
8 Zinc Coating: Unless specified otherwise, galvanize steel
' 9 _ - - fence. fittings and accessories in accordance with ASTM A
10 153, with zinc weights per Table I .
11 Tie Wires: 12-gage (0. 106-inch diameter) galvanized steel with a
12 minimum of 0. 80 oz. per sq. ft . of zinc coating of surface area
13 in accordance with ASTM A 641 , Class 3 or 9-gage (0 . 106-inch-
14 diameter) aluminum wire alloy 1100-H14 or equal , to match fabric
15 core material .
16 Post Brace Assembly: Manufacturer ' s standard adjustable brace at
17 end and gate posts and at both sides of corner and pull posts, .
18 with horizontal brace located at midheight of fabric. Use same
19 material as top rail for brace, and truss to line posts with 3/8-
20 inch-diameter -rod and adjustable tightener. Provide manufacturers
21_ standard galvanized steel or cast iron or cast aluminum cap for
22 each end. .
23 Bottom and Center Rail : Same material as top rail . Provide
24 manufacturer's standard galvanized steel or cast iron or cast
25 aluminum cap for each end.
26 Post and Line Caps: Provide weathertight closure cap for each
27 post . Provide line post caps with loop to receive tension wire or
28 - top rail .
29 Tension or Stretcher Bars: Hot-dip galvanized steel with minimum
30 length 2 inches less than full height of fabric, minimum cross-
31 section.. of 3/16 inch by 3/4 inch and minimum' 1 . 2 oz. zinc coating
* 32 . per sq. ft. of surface area. Provide one bar for each gate and
33 end post , and two for -each corner and pull post, except where
34 fabric is integrally woven into post.•
35 Tension and Brace • Bands: Minimum 3/4-inch-wide hot-dip
36 galvanized steel with minimum 1 . 2 oz. zinc coating per sq. ft. of
37 surface area.
38 Tension Bands : Minimum 14 gage (0 .074 inch) thick.
39 . Tension and Brace Bands: Minimum 12 gage (0 . 105 inch)
40 thick.
411! 410
REMODELING AND ADDITION, 1991 02831
VALLEY HOSPITAL & MEDICAL CENTER CHAIN LINK FENCES AND GATES
Northwest Architectural Company, P. S. , 90057 Page 5
1 Concrete: Provide concrete consisting of Portland cement, ASTM C
2 150, aggregates ASTM C 33, and clean water. Mix materials to
3 • obtain concrete with a minimum 28-day compressive strength of
4 2500 psi . Use at least 4 sacks of cement per cu. yd. , 1-inch
5 maximum size aggregate, maximum 3-inch slump, and 2 to 4 percent
6 entrained air. .
7 GATES : .
8 Fabrication: Fabricate perimeter frames of gates from metal and
9 finish to match fence framework. Assemble gate frames by
10 welding. Provide horizontal and vertical . members to ensure
11 proper gate operation and attachment of fabric, hardware, and
12 accessories. Space frame members maximum of 8 feet apart unless
13 otherwise indicated.
14 Provide same fabric as for fence unless otherwise indicated.
15 Install fabric with tension bars and bands at vertical edges
16 - and at top and bottom edges.
17 o Install diagonal cross-bracing consisting + f
o 3/8-inch-
18 diameter adjustable-length trussrods on gates to ensure
19 frame rigidity without sag or twist . .
20 Swing Gates: Comply with ASTM F 900.
21 Steel :
22 . Up to 6 feet High and 3 feet -Wide: Fabricate perimeter
23 frames of minimum 1 . 660-inch OD Type I or II steel pipe
24 or 1 . 50-inch square galvanized steel tubing weighing
25 1 : 90 lb per sq ft .
26 Gate Hardware: Provide hardware and accessories for
27 each gate, galvanized per ASTM A 153 , and in accordance
28 with the following:
29 Hinges: Size and material to suit gate size, non-
30 lift-off type, offset to permit 180-deg, gate .
31 opening.
32Latch: Forked type or plunger-bar type to permit
33 ' operation from either side of gate, with padlock
34 - eye as integral part of latch. -~. - ----
411- 410
REMODELING AND ADDITION, . 1991 02831
VALLEY HOSPITAL & MEDICAL CENTER CHAIN LINK FENCES AND GATES •
Northwest Architectural Company, P.S . , 90057 Page 6
1 PART 3 - EXECUTION
2 INSTALLATION:
3 General : Install fence in compliance with ASTM F 567 . Do not
4 begin installation and erection before final grading is
5 completed, unless otherwise permitted.
6 Apply fabric to outside of framework. .
7 Excavation: Drill or hand-excavate (using . post-hole digger)
. 8 holes for posts to diameters and spacings indicated, in firm,
9 undisturbed or compacted soil .
10 If not indicated on drawings, excavate holes for each post
11 to minimum diameter recommended by fence manufacturer, but
12 not less than 4 times largest cross-section of post .
13 Unless otherwise indicated, excavate hole depths
14 approximately 3 inches lower than post bottom, with bottom
15 - of posts set not less than 36 inches below finish grade
16 surface.
17 Setting Posts: Center and align posts in holes 3 inches above
18 bottom of excavation. Space maximum 10 feet o . c. , unless
19 otherwise indicated.
20 Protect portion of 'posts above ground from concrete
21 splatter . Place concrete around posts and vibrate or tamp
22 for consolidation. Check each post for vertical and top
23 alignment, and hold in position during placement • and
24 finishing operations.
25 Hold concrete footing below grade as .required to
26 accommodate the concrete mowing strip specified in
27 Section 02520 Concrete Curbs and Walls.
28 Top Rails: Run rail continuously through line post caps, bending
29 to radius for curved runs and at other posts terminating into
30 rail end attached to posts or post caps fabricated to receive
31 rail . Provide expansion couplings as recommended by fencing
32 manufacturer.
33 Bottom and Center Rails: Provide bottom rails for all fencing
34 and center rails where indicated. Install in one piece between
35 posts and flush with post on fabric side, using rail ends and
36 special offset fittings where necessary.
37 Brace Assemblies : Install braces so posts are plumb when
38 diagonal rod is under proper tension.
All 411
REMODELING AND ADDITION, 1991 02831
VALLEY HOSPITAL & MEDICAL CENTER CHAIN LINK FENCES AND GATES
Northwest Architectural Company, P. S . , 90057 Page 7
1 Fabric: Leave approximately 2 inches between finish grade and
2 bottom selvage unless otherwise indicated. Pull fabric taut and
3 tie to posts, rails, and tension wires. Install fabric on
4 security side of fence, and anchor to framework so that fabric
5 remains in tension after pulling force is released.
6 Tension or Stretcher Bars: Thread through or• clamp to fabric 4
7 inches o. c . , and secure to end, corner, pull, and gate posts with
8 tension bands spaced not over 15 inches o. c.
9 Tie Wires: Use U-shaped wire of proper length to secure fabric
10 firmly to posts and rails with ends twisted at least 2 full
11 turns. Bend ends of wire to minimize hazard to persons or
12 clothing.
13 Maximum Spacing: Tie fabric to line posts 12 inches o. c .
14 and to rails and braces 24 inches o.c.
•
15 Fasteners : Install nuts for tension bands and hardware bolts on
16 side of fence opposite fabric side. Peen ends of bolts or score
17 threads to prevent removal of nuts .
18 Gates: Install gates plumb, level, and secure for full opening
19 without interference . Install ground-set items in concrete for
20 anchorage. Adjust hardware for smooth operation and lubricate
21 where necessary.
22 END OF SECTION 02831
I 0
N i -
•
FILES
(ISo)
E-LJS' EXIG"t•
p..eLOGA12 1700R•
PROVIDE New FRAME q
RAD1OLOS`( eL C1 RoN,G OL-OSS
REEF-T-ION __
'p � Nf' 54) 2'_6,1i • _ ,1,c, New WALs
_o
T YP
PF2.IN1 i �_�
cA61 Nom_ L -J 1 - - PLA51-IG LAM.
- I _ 21-o" -5HELVINS ON
- HEAVY DU-The
N ': - WALL STAND.
cXIST1 ON -DeSi�- t 4, n!i P�F2AGKE iS
Ra.GE, T
GouNTE� � +� . 4-� _ / UI ir.W_
• iti I 4ii
N ; EXIT /Ii�u I :
v�-r . 1 I -NPI NS
CED
0 1 < •� I / S.-1-LJ FZN
.....1
, IiEw vert
-� - __.... • ==�+ ,r, DESK
CI
N - FLOOF PLAN • -.„ •
V,4.11 = 1'_0"
• ADDt✓NDUM NO, !
&if A V,4 L L EY I fOS P I-1 AL s M E IGAL G c.V R .ioe N0.01005-7
4F ; / SPOKANE, WA, DRAWN SP•�I GA- I
/ 0, fZeV1910N� To F. -74E7101K�= b
P'TN DATE 5•2
• 0 .
•
-Go0RDINAT5 SLAT IN
Sloe op GA5IN1=7
RcMoVAI oP PAPEt2
-TRAY w/ cxie-i Pp.IN r
1D
L-J �1I IIIFirP,DJ. SHI�LVIN6 4
WALL EfZAGKETB
EXIST • r .
1
1 ___J,_
cA61NET- ,L g ' - I - , .
ml k9I
SPAGE -NI-N, .
ir f
0 154 EAST .
RSL oc•A-r—C
I 0 G LOGS
PfzINTERs- or gfPecL - P-ig("'
--
N,I,c, _ �__ 1 1 1 ,
?` — ADS .V i Ne d
oPeN ) r.w-- J 1 J mai._L._ S-,c;4ET
oII , - - - I
-4 __- -- k— _ ._-< VN5a. SPACE•
I. _ �f.---.. -- -I t-a DRAWER
Ea. LIQ-3 , E-r�.1,
•
•
0 1E4 sou-n-4 .
. 1,4.11 =__ 11_011
APDcNDUM NO- I
I, w _(ALLaY NOSPITAL4 MED(CAL.GENTE2.,o6No.°ICt7
',ri : F .-SPO AAN E, WA . DRAWN SrGf�.-2
G►�yt��ag -RVIeIO J To RADIOLOGY REC'cPTio`J DATE 5.24. I
S •
faoI!-al goDH . _ _ _ _.. ____ _
NEW FUEL-TANK .--
4 PAD
` _ 1NKF� E1
G� �IN
� INFPA"t .
*-PIOVIDE PAIN
MEOIG"L. —a _./ FL AMMA13'J / WoRDINS
EI
- �GO12,175 .. �— — — —
-ADD ITION I x NO SMO -INS I
L - - - - - - aL. -- ��_ Ncw cuRC3
7 _�-- L - PZEMOVE PoRT1ON OF
jr,
EXIST. Gu(Z.g 0 GONG.
. 9'fEoc
."____1,. ..NEW LANDING w/
/ PAMP .VOWN
r/
r
•
1-1 FUEL.-TAN PLAN - WE ,�
• 1/S I1 = II-01!
.4.-::-..,A; &1-c r, CHAIN !_N14
• T FEN�C &ATE . pPo\JIJE
FAIN T�J -METAL_ -51CN
v// W04D I NG
N . - 11 PI-AM Mp.SLE
No SMoi1-I No 11 .
... [ii ni [—I 2I • NEW rUi:L: TAN!�-
PAP _
. , a _ . , .. . .N
ex 16-1", EN GINE
_ GENCRA,TofzB!...!IL.Dlto
. 0 FUSL -TANK PL.A!NI -- c-,AT • .. -__
N I/III = 11,011 - _ --. _ _- ~----- .
_ Arp.;OE---•-NrJLM No, i
,_ i,' w VA L.-L.-�Y {4O5 P IITA1_4 M rte!GOAL GE�e No. alooS7
ioq
to ; / 5 POIAAN c, WA, DRAWN GP GA- J' _
/ I1 F-e k1 iNe Fort FUSL_ -r-,Ari'4-5 DATE S'24.91
Ili Z� ERSL/¢"�YPE'' M
. .• . ' • . , • . . • . . • G`( . 62, TET, WALL ONLY
.. P A X
•
•
--_-:.72-...L:It-E- -. • • . • -.moi .r1- — - LAERS 5/S i' YP ''x''
c� ',--.1....1 ::::i.::,--7,-----');- ,L. il AR uN� SE L
j Ij cOLUMN - STA& cR'
:� ,i I1 JOINT , TYP,
, .4;' -
5"Tl✓EL
i. i..,_. . •-T-.j•_•1•!�• -&L' t rn . STUDS@ Ia11o.G,
ii
. - _ = _ ^ L
INTE.. IO, ��AL F!NISI•
-- 1RE PRoTE-GTION EXT. WAL. L-
///1/ i////1/.////,.////./1. — extol-, WALL_ OR GO'.�L�MN
_. 4 A �RS 5/8L' -rYPE "x"?• 89, A,i�:. r.:v mica-=- .
79
! . ----- -- . ; JOINSr "7-(P,"7-(P,-
STESL•GOLJMtN- 9se 5`rgUo,
if r .j ,0 a i K-r�rO— \ AL L FIN15i
. • i i ! , , „-/. ,i - 7 • r •
•
---, • i .I t - 3
• s ----. ! ; , Ell
I
• • • ___________ _ . • : -7--- ---7._::::•Ii.' :11.7.1t4::.1 Li • vIA-1
.FIO E TIONG� 11.1
,. _. ` ai•i o
,.WALL- oP COL.UMN -••, I
ir
• 311 _ I i-cm ___ 1 ••rr d , .i'1.-I.
isI ty 1.,1. .!.
•S/3'i TYP, i'? YP F,d, E?,. 5i - ° . ,I __.1 4
M-Ti.... .:I
• PST 51 pcs op STEcL C L-uMN • °- --- -• •- 7
4 L.AYERs o/8!L T`A'PE i5cu •. .02 -1 -1
A'r et--1 .o= STccL_ co_u M i . • :I .
• FF1PE P J-TCCTION 6 -1 NT WAIL .
9A 3 n= Li_au ApoeN9uNi No, I
/f' A VALLE'1 HOSPITAL 4 MEDIG,AL c
. ca.r 2 Joe i+a cio06-i
'pir : . SPoKAN , WA, DRAWN sP GA- 4
°Vag GATE 5'Z4'.91 -
FIRE PRoT1=�TIof~ of C.01-.1-!H NS
•
I
• Fab)
. 1 11
1 0 ( 16 4 ) ii 0
%I: 15 4 0 OM AD CI H
ffi( 156 )® O Ig 111111M2Mall1111111111111111 ■■■■r .
ME I■
' 11 ® 10'116i‘IIEE.1_ d
r ■■� H.. �p.m ■■ .�
o I.�1.�0 EIN11611gib. ..�l1■■1 U ■
.1.11111A4 _ WM MB IN cwsk le FIN 0
0 ...■■ .r.. 1.immargiso �� _�� a - InI6iLiIhi
pa ■
■■o�..:�■—.., ►_ ■
rasiciliorrris■■■ T�� _■
161 ) 111815"11 ■ 1101016MIMSH
FAIIMM
II r • ti ` 4..-4 • 0 111 I
.
vagicar
IL
IRiQUIdR • 165 , ' & _ I
Q.
6 1 1 :. 1 o 1 ® 'O1 ■ ■
•
•.6.2 In 1 1163 • --- 1 ° am ��r.�4,01 ■ _ ■�kkJ- ■ ill ;--; .
■
Qi •_,_ o If 2J
: .
■ Q
I like ';■ ' - . DeLETe ccDED No-re *a
ii i 0� 0_
Oma•E_I)N
PAR"T'IA R IO�.oG'I' R�FrECT 7 ;LSI ?':...AN
V511 =11_011
ADP57UH No, I
r A vi4Lt...eY Ho$p,/IITAL 4 Mev1 +L G.=N-i cg. JQ Na.g003"1 /- A
�.�� + j / SPOK•AN e, YVA. DRAWN S(� V/'1�
I I/ SPRINKLc? i-; .AD -V161U' L6 ::: 5,2�r.c11
1-
•
•
12 GA. HANGER WIRE
- • _ • NOTE: •
• THIS DESIGN IS MINIMUM 3 TURNS
BASED ON UBC •
• • STANDARDS TO FACIUTATE INSTALLATION ON .
47-18 8" MAX 2 ADJACENT WALLS:
•
WALL CONNECTION TO STUD,
CMU, OR CONCRETE
• POP RIVET
PERIMETER SECTION •
WALL ANGLE
WALL UNE
/i. /Iris/i '
4 ACOUSTICAL PANEL
MAIN RUNNER OR CROSS TEE
STRUCTURE ABOVE _
MECHANICAL FASTENER
COMPRESSION POST
1. 1111.
� 4 12 GA. SPLAY BRACE WIRES
90' FROM EACH OTHER •
- - 45' FROM MAIN k CROSS TEES
MAIN RUNNER
LATERAL DESIGN CROSS TEE
SUSPENDED CLG. DETAIL
NOT TO SCALE
•
ADD� Di 4•4 ;moo. I
ip' w VALLEY (400?ITAL 4 MCOICAL. GCN =2 Jos NO.(10°57
`,1 i i GPOKAN^ , WA. n DRAWN 5P GA-G
P/ G�(LI NC SP-,AGE vGTj�(�. DATE 5.24-.91
S
•
MECHANICAL ADDENDUM
VALLEY HOSPITAL
MAY 22. 1991 PAGE 1 •
The additions, omissions, clarifications, and corrections contained herein shall be made
to Drawings and Specifications for the Project, and shall be included in scope of work and
proposals to be submitted. References made below to Specifications and Drawings shall
be used as a general guide only. Bidder shall determine the work affected by Addendum
items.
•
MECHANICAL
SPECIFICATIONS •
• '
15 010
1.01 A. 1. Change "Field verify tank size (approximately 750 gallons)" to "Tank size is •
2,000 gallons".
1.03 A. 1. Add "Or give verbal (telephone) notification to local Washington State
Department of Ecology office within 5 working days of beginning tank •
closure process". -
1.04 A. Add "If excavation zone assessment results in additional excavation being •
required then the additional work shall be done under separate contract".
B. Contractor shall contract Staley Oil Company (922-2700) to remove oil from
existing underground tanks and store oil off site until new tanks have been
installed and passed final inspection. The oil then shall be filled into the new
tanks. If all existing oil cannot be placed in new tanks, the Owner shall pay
the oil company directly for continuing storage cost on the remainder of the
oil.
C. The Owner shall provide oil and day tanks for oil during construction.
15021 •
1.02 A. 2. Approved Balancing Agency: Add "e. Maiani Construction Services".
15 090
3.01 Add "F. Any structural steel work shall be done -by an approved fabricator or
special inspections are required under UBC Section 304 14(G).
15 176.r
1.01 A. "' Add "2. Obtain County permit for tank installations". -'_.
3.01 Add "C. Provide security and signage around tank installations during
construction". . . • .
15 520 0 _ -. r
2.01 C. Add "6. All new fire sprinkler heads shall be fast response type".
15 575 DELETE.
• •
•
MECHANICAL ADDENDUM •
VALLEY HOSPITAL
MAY 22. 1991 PAGE 2
DRAWINGS
•
Sheet M1.1 Plumbing Fixture Schedule:
•
1. P.1 & P.2 - Faucet info should be "Sloan".
2. P.6-First P.6 in schedule should read P.3. Sink manufacturer should read "Elkay".
3. P.4 - Model number should read BCRR-15. Manufacturer should be "Elkay".
4. Add P.10 - Medical Prep. Sink, existing relocated, coordinate rough-in.
5. Add P.11 - Nourishment Station, existing relocated, coordinate rough-in.
Sheet M3.1
1. Existing sprinkler heads shown as beginning relocated on architectural reflected
ceiling plan shall be replaced with new fire sprinkler heads. (All new sprinkler
heads shall be fast response type.) .
Sheet M3.3
1. Provide fuel oil vent from new 300 gallon tank into boiler room and up through roof.
Terminate vent 18" above roof.
2. Provide fuel oil vent for new 300 gallon tank at engine generator building. Run vent
up side of main building and terminate 12" above roof parapet.
3. Delete all Halon fire protection systems in room 156, 157, 158, 159, 163 and 167.
4. Remove existing wet fire sprinkler heads and install new sprinkler heads where
shown on architectural reflected ceiling plan, rooms 156, 1,57, 158, 159, 160, 163
. and 171. (All new sprinkler heads shall be fast response type.)
• Sheet M4.1 •
1. Provide type 2 fire dampers in all new ceiling air outlets in rooms 100 to 119.
-Sheet M5.1
1. Delete treated 4 x 4's for mounting of condensing units CU1 & 2. Mount and bolt
condensing units on 18" high continuous steel curbs. Remove roof insulation at
base of curb and bolt curb directly to roof decking. provide flashing around curbs
and install roofing membrane to match existing on all curb surfaces for complete
roof seal. •
S
• 411
MECHANICAL ADDENDUM
VALLEY HOSPITAL
MAY 22. 1991 PAGE 3
Sheet M7.1
1. Delete "Halon Fire Protection System interlocks with Air Systems".
2. AC-1 and AC-2 shall have automatic shut-down in case of fire under Division 16. .
ACCEPTANCE OF SUBSTITUTIONS
Add the following to accepted list of manufacturers at this time. This is an acceptance of
quality only. No attempt has been made to check each item as to special features,
capacities or physical dimensions especially required by this project. It shall be the
responsibility of supplier, manufacturer and Contractor to check all requirements before
submitting for final approval. Final approval of exact features, sizes, capacities, etc., all
of which must match equipment and materials indicated/specified, will be determined
when submitting shop drawings for approval during construction period.
Section Item Manufacturer
15 050; 2.01 Pipe Hangers PHD Manufacturing, Inc.
15 730; 2.01 Constant Volume Terminal Units Tuttle & Bailey
15 800; 2.02 Medium Velocity Duct &.Fittings Metco, Inc.
15 811; 2.01 Fire Dampers Ruskin
15 840; 2.02 Grilles, Registers & Diffusers Tuttle & Bailey
- 2.04
•
40 S
1rthwest
/ V dun
West 1203 Riverside.Spokane, Washington 99201 509-838-8240 FAX 509-838-8261 ,U `�� f.a'4 y 1'.S. OfJkra in Spokane and Seattle
PRE-BID CONFERENCE
•
•
PROJECT: Valley Hospital and Medical Center
PROJECT NO.: 90057-1Ba
DATE: May 21, 1991 •
IN ATTENDANCE: Kurt Nierenberg, Pro Heating&Air Conditioning
James B. Picken, Riley Engineering
Todd Harnetiaux, Lydig Construction, Inc. •
Robert Askins, Shea Construction, Inc.
Don Davey, Arc Electric
Bert Pickel, Spokane Concrete Cutting
Al Eberhardt, Grinnell Fire Protection
Greg Ripley, Ripley's Plumbing, Inc.
. Dan Rude, C &R Plumbing
Glen Pollock, McClintock&Turk
Don McIntosh, SMK Mechanical •
Terry Goebel, R.B. Goebel, General Contracting Inc.
Tony Bishop, Bouten Construction McIntosh
Waffle Libby, Rainbow Electric --
Peter Smith, Associated Construction, Inc.
Tom Fox, Valley Hospital and Medical Center
Don Evans, Doyle Engineering
Steve Piscitello, Northwest Architectural Company •
The following is a summary of the major items that were discussed during the conference meeting:
1. Steve Piscitello gave a brief overview of the scope of the project along.with the identification of the areas
that are to receive first priority in the construction schedule.
2. Addendum No. 1 will be issued on Friday, May 24, and should be received by all planholders by early
next week.
3. Jim Picken, the mechanical engineer for Riley Engineering, reviewed certain mechanical items that will
be incorporated into the Addendum: •'*'
a. The halon fire protection system will be deleted and replaced with a wet sprinkler system with
quick response sprinkler heads. .
b. The two fuel tanks being removed will have the fuel oil drained, stored off site and refilled by
Staley Oil (922-2700) for a fee. The owner will pay for this service.
•
llrnreE. Blarknrrr.A/�l Dale S. Brookir..41.4 Richard E. Cook.PE Robert J. Gros.,nan.A/A .i.Frrd'hingr..A/A StrrrnJ. .41.4
B.wwa A..\'i.•hrn.A/A B. .41.1 Gregory/. Stark Senior.4 soon t, : Cohn R.Jo,us. CS!. William.41.Podohnrk.A1A
i
Pre-Bid Conference
Valley Hospital and Medical Center, 90057 - lAb
May 21, 1991
Page 2
•
c. Tom Fox asked about a credit for the fuel oil not refilled in the new tanks, as the new tanks are
smaller than the existing ones. Picken will contact Staley Oil.
•
d. Picken indicated the Specifications address what is to be done if the soil surrounding the fuel
tanks is contaminated. The question was asked regarding liability if the fuel oil company spills
oil while draining the tank. This should be the responsibility of the fuel oil company.
•
• e. Fox indicated the hospital will provide the temporary fuel to operate the emergency generators
• during the transition period.
f. Fox also dictated that a "paper trail" should follow the removal and disposal of the fuel tanks for ��.--
liability reasons. The fuel tanks should be destroyed and not resold.
4. Piscitello asked Fox about any requirements for the removal of asbestos. Fox indicated that all asbestos
has been removed under prior contracts.
5. The owner has paid a plan review fee of $1,924.33 to the County. The contractor must reimburse this
amount to the owner, as called for in the Specifications.
6. Fox will identify an area on the hospital site that can be used as a staging area by the contractor. In
addition, a small amount of parking spaces will be provided.
7. A question was asked about the complexity of installation of the equipment that has been identified as
"Owner Furnished - Contractor Installed". Fox will identify any equipment that is unusual or out of the
ordinary.
8. Under Specification Section 13091, X-Ray Protection, the paragraph on "Single Source Responsibility"
was questioned. The consensus was that this requirement will be more costly to the owner. This will be
addressed in the Addendum.
•
9. A second site visit for interested parties will occur on Friday, May 31, at 10:00 a:m. Meet in the main
lobby.
•
10. .Fox indicated he will provide a location within the hospital for the storage of items to be salvaged for the
owner.
11.,; There;was a lengthy discussion on the interruption of existing HVAC, medical gases, power, sprinkler
lines, and other services during the tie-in of the new work. T
Fox confirmed what is already called for in the Specifications with regards to coordinating shut-down of
services with his department. Fox stressed that any shut-down of services for an extended period of time
could not be tolerated. -
12. Fox indicated that an air balancing of the entire hospital will occur after this project is complete but that
each remodeled area should be balanced now under this contract.
; , . I i
Pre-Bid Conference
Valley Hospital and Medical Center, 90057 - lAb
May 21, 1991 .
Page 3
13. A question was asked about the calendar days for completion of work on the proposal form and about
liquidated damages.
There are no liquidated damages and the contractor needs to fill in the blank number of days to complete
the project. While the owner is anxious to have the project completed as quickly as possible, no
completion date has been established. .
This concluded the Pre-Bid Conference meeting. Upon adjournment, the attendees toured the facility to view the
areas being affected by the remodel.
•
Submitted by Steven Piscitello, AIA8p .
cc: Planholders •
Ben Nielsen, Northwest Architectural Company
•
kp/PBC52191