SF-05-01 MISC DOCUMENTS
S 06koaone
,,;oOValley 11707 E. Sprague Ave., Suite 106 ♦ Spokane Valley WA 99206
509.688.0239 ♦ Fax: 509.688.0295 ♦ hr@spokanevalley.org
Memorandum
Date: June 23, 2009
To: File ~ ~V-)
From: Carrie A1ssAta, Deputy City Clerk
Re: Moldy documents: Mica View C of E; Street and Drainage Plans
Due to a water pipe breaking in City Hall's basement sometime last year, we are now
discovering that several files contain documents with mold on them.
The State Archivist Office confirmed with our City Clerk that we should make copies of, then
destroy all moldy documents and make a not in the file; that is the purpose of this
memorandum.
The documents within this file are merely copies of documents which had mold and are now
clean and can be handled without concern of contamination. In addition, the documents were
moved from a 6-tab file to a 4-tab file, so some have been combined.
The following lists the documents which were copied, then destroyed:
• Submittal No. 4 for Review for Mica View - Certificates of Exemption Pierce Lane
Private Road and Storm Drainage Plan, from WCE, dated September 15, 2005
• Preliminary Street and Drainage Plans Mica View C. of E., dated 9/16/04, Sheets 1, 2, 3,
41 51 61 71 8A, 813, 9, 10, 11, 12, 13, 14 of 14
YQ ze
A AWCE,
I
. tembr 15, 2005
Sep
W.O. No. 04-19 D~~ R ~
~
Spokane County SEP 1 s ZD ~
Department of Public Works - Transportation D 05
1026 W. Broadway
Spokane, WA 99260 V/Yo g~
. Attn: Tim Schwab, P.E. and Matt Zarecor, P.E.
Development Services Engineers
.cs~~CMLmmLIC DOCU11ffif` ;
~~°S
,y
Re: Mica View - Certifcates of Exemption gPa~= ~1~11z
Pierce Lane Private Road and Storm Drainage Plan ✓=-:s~ 0~~~~~`~'~`~
Submittal No. 4 for Review PROJECT f SUMINTA9. 0
~ Dear Tim and Matt,
Enclosed are one set of private road and drainage plans for review and approval. Also
enclosed with this submittal are a revised Drainage Report and supplemental or revised
calculations, of which a full document will be provided with mylars at final submittal.
Below are responses to comments received from Spokane County in Tim's transmittal .
of August 31, 2005 as well as responses to the City of Spokane Valley's comments from
Sandra Raskell's, September 6, 2005 letter.
Response to Spokane County Comments on 3rd Submittal
County comments are bold and paraphrased with responses in normal text.
PLANS
1. Side slope detail needs to be changed as the 5:1 slope cannot be
maintained with the pond designs shown
The detail for this has been revised to indicate that side slope will vary between 3:1 and
5:1 between the pond bottom and edge of road.
2. Provide trash rack for pipes larger than 18-inches
This has been added . . .
WHIPPLE CONSULTING ENGINEERS • CIVILAND TRANSPORTATION ENGINEERING
13218 E SPRAGUE AVENUE • SPOKANE VALLEY, WASHINGTON 99216 • PH: 509-893-2617 FAX: 509-926-0227
.
'.3pokane County - Engineers
.
Submittal
September 15, 2005
Page 2
3. Plans show inadequate treatment for Ponds J and K.
We have reviewed this and believe the bottom area to be correct, the required pond
bottom square feet for J and K from the GSM spreadsheet is 375 sf and the provided
area from sheet 8A of 14 is 398 sf. This also includes the area of the cul-de-sac,
however to better treat the water an additional 208 type swale was added to the end of
the cul-de-sac to satisfy another comment, this pond is Pond L and has 600 sf of pond
bottom area.
,4. Show the cut-off ditch in the typical section
This has been added
~
~s J
5. We recommend that you record a blanket drainage easement for the
: natural drainage areas.
This will be provided
6. Incorrect centerline elevation between 61+25 and 62+50
This has been checked and revised
C .
7. The acceptance blocks should not show no preliminary plans
These have been moved to "def points" and will only be printed on the mylars
DRAINAGE REPORT
8. Add the pre and post 2 and 10 year storm information to the table in the
report.
t
This has been added and the appropriate sheet attached for reference.
° 9. CN value comment
Comment noted
10. Storrn water treatment for the cul-de-sac which is north and west of
° ponds J and K?
A 208 pond has been added to the end of the cul-de-sac, calculations are attached for review
- Spokane County - Engineers
. 2"a Submittal
September 15, 2005
Page 3
11. In the final drainage report malce sure all items are included or delete
from the appendix list.
Comment noted
12. Review and revise pond sizes between drainage report and plans
Revised pond volume sheets have been provided and tables added in the revised
Drainage Report
13. Comment on City of the Valley comments for that portion in the City of
Spokane Valley.
~ Comment noted.
- ~ MISCELLANEOUS
14. Question on work around the 70-foot easement at entrance from Pierce
Road
~ This was discussed in a meeting and additional detail was added to the plans to more
clearly define work effort and limits of such.
15. The drainage facilities lay outside the 70-foot private road easement,
new easements shall be required. Please provide the following:
a. Plat certificate, deed, deed of trust or conveying instrument
b. List of signers
c. Legal descriptions, exhibit of the easement area titled "Exhibit A", etc..
- d. Easement area drawing exhibit, titled "Exhibit B"
e. Blanket Easement for the project drainage areas .
We have requested these from the project surveyor and they will be provided under
separate cover.
16. Provide a fire district approval letter
This will be provided with final mylars
17. Provide a maintenance Manual and sinking fund calculations
This will be provided with final mylars
18. Provide a draft copy of the CC&R's along with the HOA - UBI # ~
°Spokane County- Engineers
- 2nd Submittal
September 15, 2005
Page 4
This has been requested from the owner and wiil be provided upon receipt
Citv of Spokane Valley Comments
Below are comments from the City of Spokane Valley and their respective comments
following each comment.
, Plan Sheets
~ 1. Further detail the swale shown on Sheet 5
This has been added on Sheet 8B
2. Remove approval stamps
. These have been turn off and will only be turned on for mylar use
Drainage Report
1. Your report indicates a required volume for each swale to be 49 cf, but
page 19 only lists 40 cf, please udate.
This has been updated and the appropriate page included in this submittal. Essentially
: the solution was to create a 40-foot by 1-foot flat swale (slope less than 2-percent) at
the base of the hill to provide storage per the City of Spokane Valley technique of
V=1133A, wherein, 40 cf of storage is required and 78 cf of storage is provided below
the top back of curb along Pierce Road in the cul-de-sac, additional storage has also
been provided in the cascading ponds throughout this reach by adding swales. Since
the bottom swales alone store the required storage this additional storage has not been
calculated and should help alleviate any potential problems associated with this reach.
2. Please submit drywell testing information
A drywell was inadvertently added to this location which has since been removed
3. Report states galleries are to be used in svvales and ponds, however
none shown.
The report mis-spoke, under drains are used in the 208 ponds, not galleries
.
'Spokane County - Engineers
2nd Submittal
September 15, 2005 Page 5
4. It appears that there are numerous manholes/catch basins with less
than the required 0.75 feet of freeboard.
After a review of the plans we could not locate these freeboard issues. If it is in the
pond volume sheet, it is only a reference elevation to determine elevations at the 0.8-
foot mark from pond bottom for 208 ponds and is not specifically indicative of the design
and construction contemplated.
After your review should you have any questions related to this submittal please do not
hesitate to call at 893-2617 or when your comments are ready for pick up so that this
process can move along smoothly to approval/acceptance.
SincereL 6
~ ~ .
~ f
.
Todd R. Whipple, P.E.
Enclosures - Plans and attachments as noted
Cc: File
DMINAGE REPORT
FoR
MiCAViEw CERTIFICATE OF EXEMPTION
:-Spokane, Washington
March, 2005
Revisec8 July, 2005
Revised August, 2005
Final Revision September, 2005
W.O. No. 2004-19
Prepared by:
Whipple Consulting Engineers, Inc
A Civil and Transportation Engineering Company
13218 E. Sprague
Spokane Valley, WA 99216
Ph 509-893-2617 Fax 509-926-0227
This report has been prepared by the staff of WCE under the direction of the un rsigned professional
engineer whose seal and signature appear hereon. _
°~wA
,
2sas2
~~s1~~~
EXPIRES 09-24-':Za(0'
Todd R. Whipple, P.E.
, -
Final Response to Comments from 3rd Submittal and Final Submittai
This is the 4th and final submittal of the Mica View C of E Drainage Report. The following are
responses to comments received from Spokane County as well as the city of Spokane Valley
(for that portion of Pierce Road in the City) which pertain to the storm drainage report. The
cover letter detailing additional comments is a part of this resubmittal is attached for reference.
Below are responses to comment received from Spokane County in Tim's transmittal of August
31, 2005 as well as responses to the City of Spokane Valley's comments from Sandra Raskell's,
September 6, 2005 letter. Response to Spokane County Comments on 3rd Submittal
County comments are bold and paraphrased with responses in normal text.
PLANS
1. Side slope detail needs to be changed as the 5:1 slope cannot be maintained
with the pond designs shown
The detail for this has been revised to indicate that side slope will vary between 3:1 and 5:1
along the pond bottom and edge of road.
2. Provide trash rack for pipes larger than 18-inches
This has been added
3. Plans show inadequate treatment for Ponds J and K. We have reviewed this and believe the bottom area to be correct, the required pond bottom
square feet for J and K from the GSM spreadsheet is 375 sf and the provided area from sheet
8A of 14 is 398 sf. This also includes the area of the cul-de-sac, however to better treat the
water an additional 208 type swale was added to the end of the cul-de-sac to satisfy another
comment.
4. Show the cut-off ditch in the typical section
TFiis has been added
5. We recommend that you record a blanket drainage easement for the natural
drainage areas.
This will be provided
6. Incorrect centerline elevation between 61+25 and 62+50
This has been checked and revised
Whipple Constelting Engineers Page 2 of 26 Mica view C of E- Drainage Report
a
7. The acceptance blocks should not show no preliminary plans
These have been moved to "def points" and will only be printed on the mylars
Drainaqe Report
8. Add the pre and post 2 and 50 year storm information to the table irr the report.
This has been added and the appropriate sheet attached for reference.
9. CN value comment
Comment noted
10. Storm water treatment north and west of ponds J and K
A 208 pond has been added to the end of the cul-de-sac, calculations are attached for review
11. In the final drainage report make sure all items are included or delete from the
appendix list.
Comment noted
12. Review and revise pond sizes befinreen drainage report and plans
Revised sheets have been provided and these will be inserted in the final drainage report
13. Comment on City of the Valley comments for that portion in the City of
Spokane Valley.
Comment noted.
MISCELLANEOUS
14. Question on work around the 70 easement at entrance from Pierce Road
This was discussed in a meeting and additional detail was added to the plans to more clearly
define work effort and limits of such.
15. The drainage facilities lay outside the 70-foot private road easement, new
easements shall be required. Please provide the following: -
a. Plat certificate, deed, deed of trust or conveying instrumerrt
b. List of signers
c. Legal descriptions, exhibit of the easement area titled "Exhibit A", etc..
d. Easement area drawing exhibit, titled "Exhibit B"
e. Blanket Easement for the project drainage areas
Whipple Consulting Engineers Page 3 of 26 Mica Vietiv C of E- Drainage Report
. We have requested these from the project surveyor and they will be provided under separate
cover.
This has been requested and will be transmitted under separate cover.
The following comments are from the Citv of Sookane Valley, we have only responded to those
comrnents that are generally not duplic.ate comments from Spokane County or were comments
based on the original 208 presentation.
16. Provide a fire district approval letter
This will be provided with final mylars
17. Provide a maintenance Manual and sinking fund calculations
This will be provided with final mylars
18. Provide a draft copy of the CC&R's along with the HOA - UBI #
This has been requested from the owner and will be provided upon receipt
City of Spokane Vallev Comments
Below are comments from the City of Spokane Valley and their respective comments following
each comment.
Plan Sheets 1. Further detait the swate shown on Sheet 5
This has been added on Sheet 8B
2. Remove approval stamps
These have been tum off and wi11 only be turned on for mylar use
Drainage Report
1. Your report indicates a required volume for each swafe to be 49 cf, but page 19
only lists 40 cf, please udate.
This has been updated and the appropriate page included in this submittal. Essentially the -
solution was to create a 40-foot by 1-foot flat swale (slope less than 2-percent) at the base of
the hill to provide storage per the City of Spokane Valley technique of V=1133A, wherein, 40 cf
of storage is required and 78 cf of storage is provided below the top back of curb along Pierce
Road in the cul-de-sac, additional storage has also been provided in the cascading ponds
throughout this reach by adding swales. Since the bottom swales alone store the required
storage this additional storage has not been calculated and shou{d he{p alleviate any potential
Whipple Consulting Engineers Page 4 of 26 Mica View C of E- Drainage Report
problems associated with this reach.
2. Please submit drywell testing information
A drywell was inadvertently added to this location which has since been removed
3. Report states galleries are to be used in swales and ponds, however none
shown. The report mis-spoke, under drains are used in the 208 ponds, not galleries
4. It appears that there are numerous manholes/catch basins with less than the
required 0.75 feet of freeboard.
After a review of the plans we could not locate these freeboard issues. If it is in the pond
volume sheet, it is only a reference elevation to determine elevations at the 0.8-foot mark from
pond bottom for 208 ponds and is not specifically indicative of the design and construction
contemplated.
Response to Comments from 2"d Submittal
This is the third submittal of the Mica View C of E Drainage Report. The following are
responses to comments received from Spokane County as well as the city of Spokane Valley
(for that portion of Pierce Road in the City) which pertain to the storm drainage report. The
cover letter detailing additional comments is a part of this resubmittal is attached for reference.
Below are responses to the comments from the Agencies, which were very similar and many of
which were the same comments, which were resubmitted a second time Agency .
comments are in bold and generally paraphrased and responses in normal type font as
required.
Major changes in the design and documentation as it relates to this submittal area as follows:
• 208 Treatment for CARA and ASA were added to the ponds, which changed the
overall design concept of the ponds by adding under drains for discharge.
Generally, there is no discharge for the 2 year at all as it will be maintained within
the ponds below the discharge pipe.
• Discharge at the base of Pierce Road was revised to not flow freely from the
edge of the road into the cul-de-sac. Instead a level ditch was added to control
runoff. For this installation, 48 cf of volume was required and 78 cf of volume was
provided below the top of curb into Pierce Road, as discussed with Sandra
Raskell, City of Spokane Valley (COV).
Response to Spokane County and COV Comments on 2nd Submittal
County comments are bold and paraphrased with responses in normal text.
Whipple Consulting Engineers Page 5 of 26 Mica View C of E- Drainage Report
~
PLANS
14. Provide larger and more easily read Bearings for the roactway centerline
These have been added
15. Provide BCR, MCR and ECR station on the curb returns
For this project the only curb returns that we now have are on the curb returns at both cul-de-
sacs, and these have been added as well as stationing around the new/proposed cul-de-sac.
16. Provide a profile for the cul-de-sac.
In speaking with Tim, we noted that Wendy had indicated that points with elevations were
acceptable, which is why we presented what we did, also for the 2"d submittal we added a table
to list slope between points, in checking with Tim, he indicated that the table would be fine.
17. Specify dryland grasses for the bioswales and ditches
As with the previous submittal, the ditches are to be irrigated and mowed, we have tried to note
this better
18. Sheet 6 has incorrect name in title block
This has been revised
19. Update curve data table on sheet 2
This has been checked and revised
20. The radius of the cul-de-sac should be 50-feet
This has been revised by enlarging the gravel shoulder to 5-feet from the proposed 2-feet,
which takes the sac to 50-feet.
21. Show existing and/or proposed utilities for the project
This project only proposes public water service which is shown on the plan, sewer will be on site
septic.
22. Show proposed finish grade contours for the proposed road.
These have been significantly revised and reviewed for adequacy and consistency
23. The edge of asphalt was not updated for deletion of the thickened edge, please
revise.
These have been lowered 0.30 feet
Whipple Consulting Engineers Page 6 of 26 Mica Yietiv C of E- Drainage Report
24. The edge of asphalt was not revised from the deletion of the original cul-de-
sac.
This has been revised
25. Stopping construction stationing conflicts between 64+00 and 63+25
This has been revised to 64+00
26. Pierce LanelRoad connection detail, notes do not match or are missing
This has been revised.
27. Add pipe profiles, show invert elevations, existing and proposed ground, other
utilities, etc.
These have been added
28. Minimum pipe size is 10-inch for u-uns less than 44', or use 12-inch.
All pipe has been revised to 12-inch except for the control pipes from the proposed ponds which
are 6-inch.
29. Storm drainage tees are not allowed, add structures or modify discharge point.
Structures and/or discharge locations have been revised.
30. Pond bottom and side slope along with offset distance conflicts. The corresponding detail has been revised as there was conflicting information
31. Provide trash racks for all pipe over 18-inches
These have been added
32. For locations with rip rap, indicated material gradation and thickness on plans.
Add a filter blanket per Section 4 of the GSM Addendum
These have been checked and calculations added
33. Provide a sump in the ponds and rotate the weir 90-degrees, also the 3-inch
depth may be excessive. °
Based upon the plan revisions and 208 storage, this comment does not apply
34. In the typical ditch and pond section, distances and slope conflicts, etc.
The corresponding detail has been revised as there was conflicting information.
Whipple Consulting Engineers Page 7 of 26 Mica Yiew C of E- Drainage Report
r
35. Construction outside the 70-foot road and utility easements, please provide
copy of the easement to allow this construction to occur or revise plans.
These have been requested from the project surveyor Pat Moore and will be provided when
plan revisions have been accepted by the County.
36. The drainage facilities lay outside the 70-foot private road easement, new
easements shall be required. Please provide the following:
f. Plat certificate, deed, deed of trust or conveying instrument
g. List of signers
h. Legal descriptions, exhibit of the easement area titled "Exhibit A", etc..
i. Easement area drawing exhibit, titled "Exhibit B"
We have requested these from the project surveyor and they will be provided under separate
cover.
DRAINAGE REPORT
37. The drainage report states that the project is outside the ASA, this is incorrect,
per the GSM the project is in the ASA and treatment is required prior to
discharge
- Treatment has been provided by the following raising the discharge pipe 6-inches off the pond
bottom and allowing for discharge through the pond bottom via under drain pipes to the outlet .
structures.
38. A 10 year design storm must be evaluated as well as the 2 and 50
This has been added as required.
39. Pass through basins will still reach the road, either provide cut off swales or
include in pond calculations
Cut off swales have been added to the plans.
40. CN Value of 78, how was this determined.
The value of 78 was an average of the 30-feet of developed roadside swale of CN=68 and the
asphalt section CN=98 by using the following equation ((2x68)+98))/3 = 78.
41. Show/provide time of concentration calculations for the post-developed basins
These have been included.
Whipple Consulting Engineers Page 8 of 26 Mica Vietiv C of E- Drainage Report
21
42. Revise the plans and calculations to show that the 2-year pre-developed is not
exceeded by the 2-year post development fiow rates.
Discharge rates have not been revised due to the requirement for 208 type treatment and with
the exception of very slow release rates through the pond bottoms to the infiltration pipes, little
to no flow is expected from the 2-year storms.
43. Revise detention areas to match pond areas that can be built.
We are confused by this comment, but in discussions with Tim, believe that this relates back to
the 3:1 vs 5:1 and some dimensional problems with a detail and or section which has been
revised.
44. Use rational formula to check ditch velocities
These have been revised and re-calculated and remain within acceptable limits.
45. Show how storm water at the end of Pierce Lane at Pierce Road is treated and
detained.
Prior to submittal of this 2"d package, this issue was discussed with Sandra Raskell at the City
of Spokane Valley and it was indicated that because of the existing easement and right of way
conditions and some of the changes made by the adjacent land owners the last 100-feet of
roadway could not be stored, however, it would be routed to the roadside ditches and
discharged from the swales to Pierce Road with as much detention as could be provided. The
design includes the design for this comment.
46. Provide rip rap calculations
These have been provided.
MISCELLANEOUS
34. Provide a fire district approval letter
This will be provided upon acceptance of the drainage plans
35. Provide an O&M Manual and Sinking Fund calculations.
These will be provided after initial review of this 3rd submitta)
36. Provide a draft copy of the CC&R's along with the HOA- UBI #
This has been requested and will be transmitted under separate cover.
The following comments are from the Citv of Spokane Vallev, we have only responded to those
comments that are generally not duplicate comments from Spokane County or were comments
based on the original 208 presentation.
Whipple Corrsulting Engineers Page 9 of 26 Mica View C of E- Drainage Report
9.Verify how runoff downstream of 62+50 will be treated and disposed, prior to
entering the City of Spokane Valiey.
As shown on the basin map and plans, this project proposes to intercept all storm drainage at
about station 62+50 via Ponds A1 and A2 which discharge to the east. Below or northerly of
62+50, and currently within the City of Spokane Valley, the adjacent homeowners have
disturbed the soil and surrounding area of the private road easement to a point that drainage
treatment and discharge are nearly impossible if not completely impossible to treat and dispose.
We have spoken with Sandra Raskell at the City of Spokane Valley and have indicated that we
can cut off all upstream water south of 62+50 so that only that water downstream of that point
will continue to run within the City and that our ability to treat and dispose is nearly impossible.
Therefore, we have requested relief that the that area between 62+50 and 63+50 be allowed to
run free as the existing slopes do now with no other upstream contributing basins being allowed
to run to the cul-de-sac.
Essentially the solution was to create a 40-foot by 1-foot flat swale (slope less than 2-percent) at
the base of the hill to provide storage per the City of Spokane Valley technique of V=1133A,
wherein, 40 cf of storage is required and 78 cf of storage is provided below the top back of curb
along Pierce Road in the cul-de-sac.
12. Specify a grassy cover for the roadside swale
This has been added; the grassy swale will be irrigated and mowed.
Response to Comments from Original Submit#al
This is the second submittal of the Mica View C of E Drainage Report. The following are .
responses to comments received from Spokane County as well as the City of Spokane Valley
(for that portion of Pierce Road in the City) which pertain to the storm drainage report. The
cover letter detailing additional comments is a part of this resubmittal is attached for reference.
Below are responses to the comments from the Agencies, which were very similar in nature and
therefore will be answered in a very generic format. Agency comments are in bold italics and
generally paraphrased and responses in normal type font as required.
It should be noted that the overall design methodology for this project has been revised to move
to a detain and release concept as the C of E's and associated road construction are being
developed at a 1 per 5 Acre density, with the exception of the roadway, little if any additional
runoff will be generated by the total development. Therefore, this project has been substantially
revised along two major categories; first, the runoff from the road way will be treated and
detained in swales and ponds along the roadside ditch and discharged at pre-developed 2 year
and 50 year rates; second, pass through pipes have been included to discharge pre-developed
rates under the proposed road along existing and defined drainage ways.
Plans - General Comments
• Drywell discharge issues with depth in ponds, geotech information etc.
Whipple Consulting Engineers Page 10 of 26 Mica View C of E- Drainage Report .
The concept for this project has been significantly revised to be similar to a large lot project,
made up of C of E parcels where no specific drainage conditions have been imposed. Based on
this the concept for this project has been revised to a detain and release design, where all curbs
have been removed so storm water can move directly from the roadway into the grass lined
swale and be directed via the swale to the individual detention ponds. From there the storm
water will be stored to varying depths, and released at pre-developed rates at either the 2 or 50
year discharge intervals. This is accomplished via pipes, and weirs. Therefore, please note
that NO DRYWELLS ARE PROPOSED AT THIS TIME.
• Pond with berms 4-feet or higher wild require key-way and special consfruction,
per Figure 47 of fhe Standard Plans.
This has been noted and added to the plans
~ Easements for ponds outside of the existing easements
This has been forwarded to the surveyor and will be provided when ready for easement preparation.
• Remove the public roadway portion of this project, both agencies have requested
that the access to this project from the existing cul-de-sac at Pierce Road be
make private.
This revision has been made and the singular access to this project has been made a private
road.
The following are more specific responses to comments received from Spokane County.
Drainaqe Report
16. Discrepancies between plans and drainage report
Because of the significant drainage plan and report changes these have been checked and
verified prior to submittal of this plan set.
17. Provide a pre-developed basin map
This has been included within the plans set and used for the crossing/pass through pipe
construction as an exhibit.
18. More clearly define sub basins
This has been provided on a revised post-developed basin map.
19. Detention facilities not storing enough, issues with rines and drywell outflow
rates.
Whipple Consulting Engineers Page 11 of 26 Micu Yiew C of E- Drainage Report i
~ t
The drainage scenario has been revised and the drywelis omitted as well as new pond
calculations and designs have been incorporated.
20. Verify the calculations for 208 area being provided.
We have revised the drainage calculations and moved to a swale catchment, with discharge to
a detention pond and then release at the 2 and 50 year release rates and no 208 calculations
are provided.
21. Provide further explanation of the calculation table in the drainage report, etc.
This has been added, modified or changed where required
Miscellaneous
22. Provide a fire district approval letter.
Requested at the time of this submittal will be provided prior to final plan approval
23. Provide a mainfenance manual and sinking► fund calculations
This will pre provided with the next submittal, be that paper or mylar as this proposed drainage
solution has not been reviewed yet. ,
24. Provide a draft copy of the CC&R's along with the Homeowners Association
UBI
This has been requested from the owner and will be provided prior to final plan approval.
Whipple Consulting Engineers Page 12 of 26 Mica View C of E- Drainage Report
REVISED DRAINAGE REPORT
GENERAL
The proposed Mica View Certificate of Exemption development consists of fourteen 5±
acre residential lots located on approximately 87.95 acres. The site is located in the
Dishman-Mica area west and south of Ponderosa Drive, approximately one-third of a
mile northwest of the Dishman-Mica Road and Hallet Drive intersection in Spokane
County. The intent of the storm drainage facilities for this project is to capture treat and
discharge the runoff from Pierce Lane, a 3,300 If PRIVATE Road. The site lies within
portions of sections 4 and 5 of T 24 N., R 44 E., W.M., and this project is not within the
aquifer sensitive area, therefore treatment is required. A vicinity map is attached.
PURPOSE
The purpose of this drainage report is to determine the storm drainage facilities that will
be required to treat and dispose storm water runoff for the new roadway provided for
this project. The facilities, as proposed, will be designed to treat and dispose of the 2,
10, 50 and 100 year storms through a combination of swales, detention ponds and
outlet structures which will be used to convey, store treat and dispose of the storm
water runoff from this project.
ANALYSIS METHODOLOGY
The Rational Method with the Intensity, Duration and Frequency (IDF) curves from the
Spokane, Medical Lake, Reardon, Cheney and Rockford intensity curve were used in
the runoff and bowstring calculations for the peak flows for this project where required.
Generally, most of the design has been completed using Hydraflow Hydrographs,
version 8.0.0.1 by Intelisolve which have been used to implement the HEC-22, TR-20
and TR-55 drainage calculations and methods.
TOPOGRAPHY
The site has a rolling terrain with existing slopes varying from approximately 1% to over
18%. The future terrain of the project will match existing slopes as much as possible.
The PRIVATE roadway will have a maximum slope of 10-percent.
SOILS
As can be seen from the accompanying soils map from the Spokane County Soils
Survey as performed by the USDA, Soil Conservation Service (SCS), the site consists
of three types of soils all generally within the Class B and Class C soil types. They are
Clayton sandy loam (Cu6), Spokane complex (SsC), and Spokane very rocky complex
(StC). The soil descriptions are as follows.
Whipple Consulting Engineers Page 13 of 26 Mica view C of E- Drainage Report
I
i
CuB - Clayton sandy loam, 0- 8 percent slopes: Within this complex the clayton
soils are very deep, well-drained, moderately coarse textured soils formed from
glaciofluvial material on broad, nearly level gently sloping terraces, with loam forrning
the top 20 to 40 inches of surface layer.
Hydrologic Soil Classirication - B
SsC - Spokane complex, moderately shallow, 0 to 30-percent slopes: The
Spokane complex series of soils are generally well drained and moderately coarse
textured. These soils are similar to Spokane loam soils except that the depth of soil to
bedrock varies from 20 to 30-inches with this soil type. These soils have a slight
susceptibility to frost action, moderate to rapid permeability, and moderate resistance to
erosion.
Hydrologic Soil Classification - C
StC - Spokane very rocky complex, moderately shallow, 0 to 30-percent slopes:
The Spokane very rocky complex series of soils are generally well drained and
moderately coarse textured. These soils are similar to Spokane loam soils except that
the depth of soil to bedrock varies from 20 to 30-inches with this soil type and rock
outcrop is included in these complexes. These soils have a slight susceptibility to frost
action, moderate to rapid permeability, and moderate resistance to erosion.
Hydrologic Soil Classification - C
DRAINAGE NARRATI!!E
BASIN SUMMARY
Pre-Developed - Offsite Pass Through Basins
Based upon comments received, an overall aerial topography map at 2-foot contours
was ordered from Spokane County and supplied by John Bottelli, GIS manager. This
additional documentation indicated that this site was subject to up gradient offsite pass
through storm drainage. Therefore, attached to this report and included within the plan
set, sheet 11 of 14 shows the 5-offsite basins that flow through this site. Theses
upstream basins will generally be unaffected by the development of this property.
Based upon comments received cut-off ditches/trenches have been added to keep the
upstream offsite water and developed storm events separate. As to a pre developed
basin map, the site generally lays along the ridge line of the hill with the exception of the
pass through basins, storm drainage as it currently does will head to the north or south
down hill along existing drainage ways.
Pass Throuqh Basins
As noted above, the aerial contours received from Spokane County have indicated that
Whipple Consulting Engineers Page 14 of 26 Mica View C of E- Drainage Report
r
five basins A, B, C, D and E as shown on sheet 11 of 14 are generally up gradient .
basins and may require cut-off ditches and pass through pipes to continue the flow of
water from up gradient to down gradient. A brief description of each basin follows.
Pass throuqh Basin A
This basin is the westerfy pass through basin with the following characteristics
• Area = 8.16 Acres
• CN Value = 66
• Tc Length = 1100 If
• 100-Year Discharge = 5.49 cfs
• Solution for Pass Through = 24-inch Culvert with varying slopes
• Velocity = 4.46 fps
• 24-inch Capacity = 17.33 cfs @ 2%+/-
Pass throuqh Basin B
This basin is the second basin from the west with the following characteristics
e Area = 6.68 Acres
0 CN Value = 66
o Tc Length = 1400 If
• 100-Year Discharge = 2.89 cfs
• Solution for Pass Through = 24-inch Culvert with varying slopes
• Velocity = 3.63 fps
• 24-inch Capacity = 17.33 cfs @ 2%+/-
Pass throuQh Basin C
This basin is the middle of the five upgradient basins with the following characteristics
• Area = 5.77 Acres
• CN Value = 66
• Tc Length = 1000 If
• 100-Year Discharge = 2.70 cfs
• Solution for Pass Through = 24-inch Culvert with varying slopes
• Velocity = 3.55 fps
• 24-inch Capacity = 17.33 cfs @ 2%+/-
Whipple Consulting Engineers Page 15 of 26 Mica Yiew C of E- Drainage Report
Pass throuqh Basin D
This basin is the second basin from the east with the following characteristics
• Area = 3.21 Acres
• CN Value = 66
• Tc Length = 750 If
• 100-Year Discharge = 1.50 cfs
• Solution for Pass Through = 24-inch Culvert with varying slopes
• Velocity = 1.50 fps
• 24-inch Capacity = 17.33 cfs @ 2%+/-
Upstream/Uqaradient Basin E
This basin is the last basin to the east and it should be noted that while this is an
upstream/upgradient basin, it generally does not reach the roadway and rather makes a
characteristic semi-circular tum back to the main channel which lies south of the project
area. This basin was modeled because a site visit will reveal that it appears upgradient
but the contours do not lend themselves to this issue. Therefore, this information is
provided for consideration, with the following basin characteristics,
• Area = 4.87 Acres
o CN Value = 66
• Tc Length = 900 If
• Discharge = 2.11 cfs
• Solution for Pass Through = does not pass under the road, ditch continues east
• Velocity = 2.11 fps
• 24-inch Capacity = 24.42 cfs @ natural contour
Post-Developed - Basin Summaries
Generally the site has been divided up into 13 basins with Basin A encompassing both
sides of the road into A1 and A2, with a shared discharge. Additionally, comments
received from the City of the Valley regarding Pierce Lane have resulted in the creation
of two new basins for the 3rd submittal. These basins are A1 A and A2A which
encompase that area north of Basins A1 and A2 as well as ponds A1 and A2, which cut
off all water at 62+50. As noted eariier, this project is in the aquifer sensitive area and
also within the "high" susceptibility area of the CARA map thereby requiring treatment of
storrnwater prior to discharge. As this area has soils that are not conducive to drywells,
see geotech reports attached in the appendix. The previous drainage report and
geotechnical information make groundwater discharge very difficult due to somewhat
poor soils and the presence of shallow rock. Therefore, and as noted earlier, it was
Whipple Consulting Engineers Page 16 of 26 Mica Yiew C of E- Drainage Report
determined to revise this drainage report and revise the site design from drywell
discharge and 208-type swale/ponds to detention ponds using the natural drainage
inrays as discharge locations. Once captured, stormwater will be treated by the pond
bottoms with assistance from under drain pipes place 1 to 2 feet below the pond bottom
to insure that these ponds, as required will drain within the required 72 hours.
Therefore, this analysis considers the following.
• That building 14 houses on 88 acres will have little to no impact to existing
runoff characteristics or require enough change between the pre and post
developed CN values to warrant specific analysis. .
• That the single largest contributor to a change in runoff pattems, volumes and
rates will be the presence of the 30-foot wide PRIVATE asphalt roadway.
• Therefore, the limits of the basins are to the extents of the proposed
improvements along the roadway including the proposed swales and ponds, this
would require detention for the development of the 60-foot wide roadway and
swale prism throughout the length of the roadway.
• Because of this revision in drainage philosophy and in trying to determine better
and more reasonable ways to control runoff from the streets, the Type "C" curbs
that were originally proposed have been omitted so that straight sheet flow from
the roadway along its entire length will run into the swales which will direct all
runoff to the proposed ponds, where the storm water will be treated in the 6-inch
sump that has been introduced into 'each pond with this 3rd submittal. The
stormwater within this 6-inch sump will then be discharged via either evaporation,
evapotranspiration or infiltration through the pond bottoms.
• Based upon these basic concepts the basins were divided by existing drainages
or drainage ways within the overall property so that discharges will follow
historical drainage paths with maximum discharge from each pond limited to the
pre-developed 50-year storm event, and in all cases below the pre-developed
discharge rate.
Basins A1 A and A2A
This basin represents that portion of Pierce Lane from the City Limits to the existing
Pierce Road cul-de-sac. As noted in the description for Basins A1 and A2 treatment
options for this basin are difficult because Pierce Lane is on a 50-foot easement
where room for ponds are none existent. Additionally, the adjacent neighbors have
changed the land form so that overland discharge to historical drainage ways is not
applicable. This is all compounded by the presence or rock and shallow silty/clayey
soils that are not conducive to groundwater discharge. Based upon eady discussion
Whipple Consulting Engineers Page 17 of 26 Mica Vietiv C of E- Drainage Report
a
with the COV these constraints were discussed and originally, it was thought that
discharge directly to Pierce Road for this 125 foot segment could be accommodated.
However, in this last review this has been modified to require storage behind the
curb of the runoff from this area. Therefore, runoff volume from this basin has been
calculated using the COV method of V=1133A to determine the extent of ponds.
Additionally, and as a precautionary measure, a gravel gallery has been installed
under the pond bottom with dimensions of 2' x 3' with a grate 6-inches above the
pond bottom to facilitate some discharge to the underlying soils. Ultimately
discharges from these two swales are either through, evaporation,
evapotranspiration or infiltration. Highlights for this basin are as follows:
• Basin (imits - 62+50 to 63+75 (125 feet)
• Area = 0.27 / 0.41 Acres
• Pre Developed CN = 66
• Post Developed CN = 78
• Weighted "C" = 0.27 / 0.41
• 2 year Discharge Rate (rational) = 0.15 / 0.10
• 10 year Discharge Rate (rational) = 0.23/ 0.16
• 25 year Discharge Rate (rational) = 0.30 / 0.20
• 50 year Discharge Rate (rational) = 0.34 / 0.23
• 100 year Discharge Rate (rational) = 0.38 / 0.26
e In all instances, the higher rate was used for analysis
• Total Storage Volume @ 1.0 feet = 78 cf
Basin A (A1 and A2)
This basin is located above the existing Pierce Road and utilizes an existing drainage
- way to the east as its discharge point. Highlights for this basin are as follows:
• Basin limits - 58+50 to 62+50
• For this basin the length of asphalt for design was assumed to be 500 If rather
than 400 If to compensate for the inability to detain the discharged water from
62+50 to 63+50 (at existing Pierce Road) because of existing home construction
and driveway irnprovements associated with the properties 'along the right of way
that have modified the existing terrain to preclude use of any discharge to an
existing drainage way. See photos in the appendix.
• Area = 0.78 Acres
• Pre Developed CN = 66
• Post Developed CN = 78
• Pre Developed Discharge Rate, 2 year = 0.00 cfs
• Pre Developed Discharge Rate, 50 year = 0.17 cfs
• Post Developed Discharge Rate, 2 year = 0.12 cfs
• Post Developed Discharge Rate, 50 year = 0.94 cfs
Whipple Consulting Engineers Page 18 of 26 Mica Vieiv C of E- Drainage Report
• Total Storage Volume @ 0.5 feet = 395 cf
0 "208" Required Bottom Area = 710 sf
0 "208" Bottom Area Provided = 710 sf
Basins B and C
These basins are identical in nature each discharging to their respective sides of the
roads to the existing drainage ways. Highlights for each individual basin are as follows,
please keep in rnind that these are duplicate basins:
• Basin limits - 53+00 to 58+50
• Area = 0.39 Acres
• Pre Developed CN = 66
• Post Developed CN = 78
• Pre Developed Discharge Rate, 2 year = 0.00 cfs
• Pre Developed Discharge Rate, 50 year = 0.10 cfs
• Post Developed Discharge Rate, 2 year = 0.06 cfs
~ Post Developed Discharge Rate, 50 year = 0.26 cfs
• Total Storage Volume @ 0.5 feet = 390 cf
0 "208" Required Bottom Area = 700 sf
0 "208" Bottom Area Provided = 700 sf
Basins D and E
These basins are identical in nature each discharging to their respective sides of the
roads to the existing drainage ways. Highlights for each individual basin are as follows,
please keep in mind that these are duplicate basins:
• Basin limits - 46+00 to 53+00
• Area = 0.51 Acres
• Pre Developed CN = 66
• Post Developed CN = 78
• Pre Developed Discharge Rate, 2 year = 0.00 cfs
• Pre Developed Discharge Rate, 50 year = 0.09 cfs
• Post Developed Discharge Rate, 2 year = 0.05 cfs
• Post Developed Discharge Rate, 50 year = 0.43 cfs
• Total Storage Volume @ 0.5 feet = 513 cf
0 "208" Required Bottom Area = 933 sf
•"208" Bottom Area Provided = 933 sf
Whipple Consulting Engineers Page 19 of 26 Mica Vievv C of E- Drainage Report
f
Basins F and G
These basins are identical in nature each discharging to their respective sides of the
roads to the existing drainage ways. Highlights for each individual basin are as follows,
please keep in mind that these are duplicate basins:
• Basin limits - 42+50 to 46+00
• Area = 0.25 Acres
• Pre Developed CN = 66
• Post Developed CN = 78
• Pre Developed Discharge Rate, 2 year = 0.00 cfs
• Pre Developed Discharge Rate, 50 year = 0.05 cfs
• Post Developed Discharge Rate, 2 year = 0.02 cfs
• Post Developed Discharge Rate, 50 year = 0.21 cfs
• Total Storage Volurne @ 0.5 feet = 263 cf
0 "208" Required Bottom Area = 449 sf
0 "208" Bottom Area Provided = 462 sf
Basins H and I
These basins are identical in nature each discharging to their respective sides of the
roads to the existing drainage ways. Highlights for each individual basin are as follows,
please keep in mind that these are duplicate basins:
• Basin limits - 34+00 to 42+50
• Area = 0.62 Acres
• Pre Developed CN = 66
• Post Developed CN = 78
• Pre Developed Discharge Rate, 2 year = 0.00 cfs
• Pre Developed Discharge Rate, 50 year = 0.10 cfs
• Post Developed Discharge Rate, 2 year = 0.06 cfs
• Post Developed Discharge Rate, 50 year = 0.52 cfs
• Total Storage Volume @ 0.5 feet = 610 cf
•"208" Required Bottom Area = 1117 sf
•"208" Bottom Area Provided = 1126 sf
Basins J and K
These basins are identical in nature each discharging to their respective sides of the
roads to the existing drainage ways. This basin includes the storage for the cul-de-sac
which is below grade of the ponds and allows for the cul-de-sac runoff to be captured in
the swales and discharged directly to the respective drainages. Highlights for each
individual basin are as follows, please keep in mind that these are duplicate basins:
Whipple Consulting Engineers Page 20 of 26 Mica Vieiv C of E- Drainage Report ~
0
0 Basin limits - 29+50 to 34+04
• Area = 0.21 Acres
• Pre Developed CN = 66 • Post Developed CN = 78
• Pre Developed Discharge Rate, 2 year = 0.00 cfs
• Pre Developed Discharge Rate, 50 year = 0.06 cfs
• Post Developed Discharge Rate, 2 year = 0.03 cfs
• Post Developed Discharge Rate, 50 year = 0.25 cfs
• Total Storage Volume @ 0.5 feet = 229 cf
0 "208" Required Bottom Area = 375 sf
0 "208" Bottom Area Provided = 398 sf
Tabie 1 A- SCS Basin Summary Table - 50 - Year Data
SP4KANE COUNTY BASIN INFORMATiON - - `
50 YEAR QATA . . , -
~ ~ . : 50-YEAR 50-1(EAR ' MINIMUM . CN VALUES CN VALUES PRE POST .50-YEAR _
BASINS QREA (AC) :PRE , POST DEVELOPED DEVELOPED DETENTION
. DEVELbPED DEVELOPED RUNOFF RUNOFF VOLUME RATE (CFS) RATEJCFS) ~CfL.= -
A1 ~ 0.39 ~ 66 ~ 78 ~ 0.17 ~ 0.94 ~ 1083
A2 ~ 0.39 ~ 66 ~ 78 ~ 0.17 + 0.94 ~ 1083
B ~ 0.39 ~ 66 78 ~ 0.10 ~ 0.47 ( 483
C ~ 0.39 ~ 66 + 78 ~ 0.10 ! 0.47 ~ 483
D ~ 0.51 ~ 66 ~ 78 ~ 0.09 0.48 ~ 758
- E ~ 0.51 ~ 66 N 78 ~ 0.09 0.48 ~ 758
F ~ 0.25 ~ 66 ~ 78 ~ 0.05 ' 0.21 ~ 292
G ~ 0.25 ~ 66 ~ 78 ~ 0.05 ( 0.21 ~ 292
H ~ 0.62 ~ 66 ~ 78 ~ 0.10 ~ 0.52 ~ 830
' I ~ 0.62 ~ 66 ~ 78 ~ 0.10 ~ 0.52 ~ 830
J ~ 0.21 ~ 66 ~ 78 J 0.06 ~ 0.25 ~ 232
K ~ 0.21 ~ 66 ~ 78 ~ 0.06 j 0.25 ~ 232
T-otal .s 4 . ~74- --66 78
-
Whipple Consulting Engineers Page 21 of 26 Mica View C of E- Drainage Report
Table 1 B- Supplemental SCS Basin Summary Tabie - 2- Year Data
SPOKANE COUNTY BASIN SUPPLEMENTAL INFORMATION 2 YEAR DATA . .
2-YEAR 2.-1(EAR 2-YEAR 2-YEAR - DETENTION
PRE POST POST VOLUME
ST4RAGE
BASINS. AREA (AC) DEVELOPED DEVELOPED DEVELOPED • TO 208
. RUNOFF RUNOFF DISCHARGE VOLUME DEPTH
_ RATE CFS RATE (CFS) RATE (CFS) (CF) (CF) _ ; .
A1 ~ 0.39 ~ 0.00 ~ 0.12 ~ 0.02* ~ 385 ~ 395
A2 ~ 0.39 ~ 0.00 ( 0.12 ~ 0.02* ~ 385 395
6 ~ 0.39 ~ 0.00 0.06 ~ 0.01 192 ~ 390
C ~ 0.39 ~ 0.00 0.06 ~ 0.01 ~ 192 ~ 390
D ~ 0.51 ~ 0.00 ~ 0.05 0.01281 ~ 513
E ~ 0.51 ~ 0.00 ~ 0.05 0.01 281 ~ 513
F ~ 0.25 ~ 0.00 ~ 0.02 ~ 0.00 ~ 123 ~ 263
G ~ 0.25 ~ 0.00 ~ 0.02 ~ 0.00 ~ 123 263
H ~ 0.62 ~ 0.00 ~ 0.06 ~ 0.01 306 ~ 610
I ~ 0.62 ~ 0.00 ~ 0.06 ~ 0.01 306 ~ 610
J ~ 0.21 ~ 0.00 ~ 0.03 ~ 0.00 ~ 104 ~ 229
K ~ 0.21 0.00 ~ 0.03 ~ 0.00 ~ 104 ~ 229
Totals~ 4.74 ~ ~ 7,356
calculated rate shown is not consistent with the requirement for storage for the 208 event and
the pipe at 6-inches in depth, rate should be zero.
Whipple Consulting Engineers Page 22 of 26 Mica Vieiv C of E- Drainage Report
1
Table 1 B- Supplemental SCS Basin Summary Table - 10 - Year Data
SPOKANE COUNTY BASIN SUPPLEMENTAL INFORMATIO{V 10 - YEAR DATA
1 O YEAR ' 1 O-YEAR 1 O YEAR 1 O-YEAR MINiMUM
PRE POST POST . 5 0 YEAR
STORAGE
BASINS AREA (AC) DEVELOPED DEVELOPED DEVELOPED DETENTION
RUNOFF RUNOFF DISCHARGE VOLUME VOLUME
. . . RATCFS~ RATE (CFS _ RATE (CFS) _ (CF) . . _(CF) _
- I - I - I I
A1 ~ 0.39 0.04 ~ 0.54 ~ 0.17* ~ 937 ~ 1083
A2 ~ 0.39 0.04 ~ 0.54 ~ 0.17* ~ 937 ~ 1083
B ~ 0.39 ~ 0.02 ~ 0.27 ~ 0.04* ~ 419. ~ 483
C ~ 0.39 ~ 0.02 ~ 0.27 0.04* ~ 419 ~ 483
D ~ 0.51 0.02 ~ 0.27 0.02 ~ 657 ~ 758
E 0.51 ~ 0.02 ~ 0.27 ~ 0.02 ~ 657 ~ 758
F 0.25 ~ 0.01 ~ 0.12 ~ 0.01 ~ 252 ~ 292
G ~ 0.25 ~ 0.01 ~ 0.12 ~ 0.01 252 * ~ 292
H ~ 0.62 ~ 0.03 ~ 0.29 ~ 0.02 ~ 718 ~ 830
I 0.62 ~ 0.03 ~ 0.29 ~ 0.02 ~ 718 ~ 830
J 0.21 ~ 0.01 ~ 0.15 0.01 ~ 200 ~ 232
K ~ 0.21 ~ 0.01 ~ 0.15 ~ 0.01 ~ 200 ~ 232
_Totals l 4.74 7,356
* = rate shown is inconsistent with options for discharge, a 0.01' change in outlet elevation results in 0.00
cfs as discharge, therefore, we believe that the rate should be the same or equal to the pre-developed
level.
Table 1 D- City of Valley Basin Summary Table
` CITY OF THE VALLEY BASIN INFORMATION 10-YEAR 50 YEAR 100-YEAR STORAGE
WEIGHTED - ' VOLUME @
BASINS AREA (AC) «C„ DEVELOPED DEVELOPED DEVELOPED V-1133A
RATE (CFS). RATE (CFS) RATE (CFS) ~CF
_
I - ` _ - I ~
I
A1 A ~ 0.28 ~ 0..27 ~ 0.23 ~ 0.34 ~ 0.38 ~ 48.7
A2A ~ 0.12 ~ 0.41 ~ 0.16 ~ 0.23 ~ 0.26 48.7
Whipple Corrsulting Engineers Page 23 of 26 Mica View C of E- Drainage Report
POND DESIGN
Ponds and outflow structures for this project were generally designed and sized using
the Hydraflow program noted earlier. In some instances pond configurations were
rnodified to better accommodate the existing site topography, but required volumes and
outflow structures were maintained to meet minimums in any case. Generally, the
ponds were sized to hold the 50 and 100 year storms with 1-foot of freeboard above the
100-year event. The ponds are summarized in Table 2.
Table 2. Pond Summary Table
. . : ~SPOKANE COUNTYPOND INFORMATION
. TOPOF PROVIDED ° MINIMUM BERM
OTTOM BOTTOM TOP OF 50 YEAR
B 50 YEAR DETENTION
POND AREA . ELEVATION STRUCTURE DETENTION DETENTION VOLUME
ELEVATION ELEVATION (SF) . ' VOLUME PROVIDED (CF -=A1 ~ 675 ~ 2181.83 ~ 2182.28-1 2182.83 ~ 1083 ~ 1425_
A2 ~ 675 ~ 2181.83 ~ 2182.28 ~ 2182.83 ~ 1083 ~ 1425
B ~ 450 ~ 2207.00 ~ 2207.47 . ~ 2208.10 ~ 483 2035
C ~ 450 ~ 2207.00 ~ 2207.47 ~ 2208.10 483 ~ 2035
D ~ 415 ~.2226.50 ~ 2227.63 ~ 2227.60 ( 758 ~ 1815
E ~ 415 ~ 2226.50 ~ 2227.63 ~ 2227.60 ~ 758 ~ 1815
F ~ 462 ~ 2221.46 ~ 2221.99 ~ 2222.66 ~ 292 ~ 1158
G ~ 462 ~ 2221.46 ~ 2221.99 ~ 2222.66 ~ 292 1158
H ~ 462 ~ 2186.16 ~ 2187.26 ~ 2187.26 ~ 830 2484
I ~ 462 ~ 2186.16 ~ 2187.26 1 2187.26 ~ 830 2484
J ~ 398 ~ 2161.75 ~ 2162.25 1 2162.85 ~ 232 ~ 943
K ~ 398 ~ 2161.75 ~ 2162.25 ~ 2162.85 ( 232 943
L ~ 600 ~ 2157.47 ~ 2157.97 ~ 2159.37 ~ ~ 1671
. - ~ ~ ~ . F - I ~
- . . -CITY,OF SPOKANE VALLEY PONb INFORMATION REQUIRED DETENTION, BOTTOM BOTTOM STRUCTURE TOP BACK DETENTION VOLUME
POND AREA ELEVATION ELEVATION OF CURB VOLUME AT PROVIDED
(SF) STRUCTURE AT CURB
(CF)-~ (CF) ,
A1 A ' 98 ~ 2175 ~ 2175.5 ~ 2176 ~ 49+ ~ 49+
A2A ~ 98 ~ 2175 ~ 2175.5 ~ 2176 ~ 49+ ~ 49+
Whipple Consulting Engineers Page 24 of 26 Mica vieiv C of E- Drainage Report
HYDRAULICS
As noted eariier, the pass through pipes on this project were sized to accommodate the
full 100-year event. Discharge from the pond structures are sized for the 2 and 50-year
release rates. While the minimum culvert pipe size for Spokane County is 12-inch,
discharge pipes are sized according to the Hydraflow program and generally are 4-
inches in diameter. As the storm water catchments on this project are the roadside
swales, velocities for the 50-year storm for each basin were checked at the steepest
slope along the roadway reach and are included for reference and summarized in Table
3 below.
Table 3 Roadside Swale 50-year Velocities
. : ::-SPOKANE COUNTII IfVFORMATION
POND RATE (CFS) ' SLOPE (FT/FT) - DEPTH OF FLOW RESULTING
~ ' . - - (FT) VELOCITY (FPS)
A1 ~ 0.47 ~ 0.0941 0.20 ~ 2.41
A2 0.47 ~ 0.0941 0.20 ~ 2.41
B 0.47 ~ 0.0737 ~ 0.21 ~ 2.19
C ~ 0.47 ~ 0.0737 ~ 0.21 ~ 2.19
D ~ 0.48 ~ 0.0267 ~ 0.25 ~ 1.51
E ~ 0.48 ~ 0.0267 ~ 0.25 ~ 1.51
F ~ 0.21 0.0153 0.21 ~ 0.99
G ~ 0.21 ~ 0.0153 0.21 ~ 0.99
H ~ 0.52 ~ 0.0500 ~ 0.23 ~ 1.95
I ~ 0.52 ~ 0.0500 ~ 0.23 ~ 1.95
J ~ 0.25 ~ 0.0800 0.16 1.94
K ~ 0.25 ~ 0.0800 0.16 ~ 1.94
Whipple Corrstclting Engineers Page 25 of 26 Miccr View C of E- Drainage Report
c
CITY OF.SPOF(ANEYALLEY. INFORMATION POND RATE (CFS) SLOPE (FT/FT) DEPTH OF FLOW~ RESULTING
(FT) . VELOCITY (FPS .
A1 A ~ 0.34 ~ 0.0941 ~ 0.17 ~ 2.22
A2A ~ 0.34 ~ 0.0941 ~ 0.17 ~ 2.22
Based upon Tab(e 24-2, page 6-56 af the Spokane County Guidelines for Storm Water
- Management, the resulting velocities shown in Table 3 of this document are below the
permissible velocities for the Cover noted as Grass Mixture which has permissible
velocities of befinreen 3 and 4 fps.
CONCLUSION .
Based upon the information provided and the calculations performed we believe that
this report surnmarizes and demonstrates that the detention and release design method for this project is adequate to detain and release the increase in storm water runofffrom
this project. Based upon these assertions, we believe that the implementation of the
storrn water control systems discussed here and as shown on the accompanying plans
will meet or exceed the storm water requirements of Spokane County.
Whipple Consultirrg Engineers Page 26 of 26 Mica Vieiv C of E- Drainage Reporl
O
APPENDIX
1. Vicinity Map
2. Soil Conservation Service, Spokane County, Site Exhibit (Soils
map)
3. Offsite Pass Through Basin Map (11x17)(Full Size in Jacket at End)
4. Pre Developed Basin Map (11x17)(Full Size in .lacket at End)
5. Post Developed Basin Map (11x17)(Full Size in Jacket at End)
6. On Site Basin Summary Sheet
7. Basin Calculation Worksheets (Spokane County / COV)
8. Pass Through Basin - Hydrograph Calculations
9. Pass Through Basin - Pipe Calculations
10. On Site Pre Developed - Hydrograph Calculations
11. On Site Post Developed - Hydrograph Calculations
12. On Site Post Developed - Pond Reports
13. On Site Post Developed - Pond Volume Calc Sheet - 50 Year
Elevation Volumes
14. On Site Post Developed - Pond and Outlet Structure Design
Sheets
15. Roadside Svvale - Triangular Channel Worksheets for Velocity
and Depth .
16. Pipe Calculations for Froude Number and Velocity for Rip Rap
Design
17. Rip Rap Design Spreadsheets
18. All West - Geotechnical Evaluation
19. All West - Proposal for Construction Inspection
20. Copy of Letters in Response to Comments Received on
Submittal No. 1
21. Copy of Letters in Response to Comments Received on
Submittal No. 2
22. Copy of Letters in Response to Comments Received on
Submittal No. 3
~UL't:/31/'LUU.ti 15: `33 !''Ab 5094't7765`J sYUtlA1VL{ (:UU1V1'Y t:1Vla1Nt,L:Kb lfLj UUt
. ~ .
.
Fai Transmittal
o ~
SwIfQW.
Development Services Departnent
Division of Engineering and Raads
. (509) 477•3600
' Fax (509) 477-7655
Date: August 31, 2005
, To: Todd Vhipple, P.E. Fax-No: 926-0227
Company: WCE
cc: Bruce Howard Faz No: 924-9728
From: Tim Schwab Number of Pages: 3 incl. cover
Subject: CE9105 - Mica'tTiew Certificafe of Exemption
Attached i.s our comment letter for the Mica View Certif cate of Exemption, 3rd submittal. If you
want, we can meet with you to discuss these comments.
If you have any questions please give me a call.
Tim Schwab
cc: Project File
U25/31/'LUUS 15:53 r'A.2i 5U94'17'1655 ,YURAlvrl I:UUN'1'Y tivvltvhhtcJ ttxj uuz
. °
. ;
. '
~ gP O g{ A l~T 1-:7 , CC) U N T Y
~ DMSION OF FNaNEERIHG AND ROADS ` A DMSION OF THE PUBLIC WORKS DEPARTMiEiVT
i
. ~
August 31, 2005 '
~
Mr. Todd Whipple, P.E.
Vahipple Consulting Engineers
13218 East Sprague Ave. '
Spokane Valley, WA 99216 ~
~
~
Subject CE 91-05 1Vlica'View Cet '-tifiicaYe of txemption
Road and.Drainage Plan Submittal #3 !
s
Mr. Whipple, ~
. ;
We have reviewed your subnuttal of fihe road and drainake design documents we received on August 23,
2005 for the Mica View C. of E. project. Before the Cettif cate of Exernption can be accepted, the private .
road proposed to serve the lots must meet the current de4ign standards. 3'hc following items need to bs .
addressed or resolved prior to acceptance of the plans: '
PLANS :
1, The pand bottoms as shown in the plans will not wark with the constant 5:1 -slope from edge of :
pavement to bottom of swale alang with the grade of the road. Either show that the slopes vary or revise pond bottom area to show tb.e flat area thit can be constructed.
2. Provide a trash rack far all culverts greater than 18". Include a detail. '
. ;
3. The plans show inadequate volume for 208 trea ent for Basins J& K.
4. In the typical section detail, show the cut-off di h. :
5. We recommend that you record a blanket drainAge easement for the natural drainage areas. :
fi. On Sheet 3, the centerline station elevation list is incorrect. The edge of asphalt grades le$ and :
. right at Sta. 61+25 and Sta. 62+50 don't match e 2% slope from the centerline grade. 7. The Spokane County acceptance block should ave preliminary an it or be put on a non printing. :
layer until ready for mylars to avoid potential nfusion over acceptance of plans. ;
0
pRAINAGE REPORT •
8. Per requirements for detention basins on page 3 6 of the GSM, a 10 year storm design storm is to .
be evaluated as weil as the 2 year and 50 year design storms. It appears most of the calculations •
have been performed. Include in your report turrative a summary table wifh the 2,10 and 50 year design storms, pre-developed vs. post-develop from the pond for each basin so it is shown that ~
for each of these de+sign starms in each of the b ins, the rats in the post-developed conditivn is less than or equal to the rate in the pre-develaped c ndition. - 9. The predomitnant soil type for this site is Type soil. From Table 5 on page 6-8 of the GSM, the ;
lawest value for Type C soil is 70 fbr forest la it with good ground cov+er. The Drainage Report
,
claims a CN value for existing of 66. Also we lieve your post-developed CN value is calculated I
incorrectly and is also low. However, the diff nce beivveen CN values is rougbly similar and .
. therefore we will accept you're the calculatiousing these CN values. In future submittals, • `
consider CN values that more appropriately fit soil types and land uses.
1026 W. Sroadway Ave. m Spokane, WA 99260-0170 s(509) 477-3600 FAX: (549) 477-7655 (2nd Floor) 4717478 (3rd Floor) o't'pD; (509) 477-7133
09/31/2005 15:54 FA% 5094777655 WYUxAtvZ I:UUN'1']f L'1Vli1Nrt3Ko ~uua
10. Show how storm water at the end of Pie3rce Lane'north of Basins J& K is treated and detained.
Include drainage calculations and plan edits.
11. In final Drainage Regort, include alI items as listed in the Appendix and are mentioned in the
report such as full sized basin maps and photos.
12. The ponds sizes shown in the drainage report and:the plans do not agree in size. Check all prnnds
to make sure the size of jond in the arainage report, the size claimed on the swale detail block
and the actuai size of the pond shown in the plans all agree. ,
13. For the raad and impervious axea north of Basins A1 and AZ, we will accept the
recomsnendations regarding treatrnent and disposal from the City of Sgokane Valley.
MLSCELLANEOUS '
You have indicated that these wili be submitted at a tater date, but are mentioned for reference.
14. It appears that construction is proposed in these plans for the.connection to Pierce Road that is
outside the existing 70' Road and Utility easement area. P7ease provide a copy of the easements to
allow this construction ar revise the plans to fit within existing easement
15. 'i'he drainage facilities that lie outside of the existing 70' private road and utility easement
(Auditor's Document Number 5194998) axe required to be placed within easernents. The
easements shall meet the requirements of the Stornawater Guidelines. Pleas$ provide the
following docunaentation so we can prepare the easements:
a. Plat certificate: Deed, Deed of Trust, or Conveying Instrument (recorded copy);
b. List of signatory names;
c. Legal description exhibit of the easement area: Include a title "Exhiibit A", it shall be .
stamped by a licensed Suiveyor, aIl margins shall be I " or greater, 8 point rninimum fant
sizs, and the text shall be reproducible; and, d. Easement area exhibit Include a title "Exhibit B" and meet the requirements of the legal
description exhibit.
16. Provide afire district approval letter. 17. Provide a maintenance rnanual and sinking fund calculation.s.
18. Provide a draft capy of the CC&Rs along with the Homeowner's Association UBI#.
If you have any questions aboufi this review, please contact us at 477 3b00.
Sixmcerely, . Matt Zarecor, P.E.
Developm,ent Services EngineerlManager
A zja
Ti.m Schwab, P.E.
Plan Review Bngineer
ce: Bryan Walker, Ovvner
File
z~ ~ ►re +I ;t!
• • ~ l3
• CiT1' ,~r ~~^_N : ~ w _ ' `
Ulley 11707 E Sprague Ave Suite 106 ♦ Spokane Valley WA 99206
509.921.1000 ♦ Fax: 509.921.1008 ♦ cityhall@spokanevalley.org
September 6, 2005
Todd Whipple, P.E.
Whipple Consulting Engineers
13218 E. Sprague Avenue
Spokane Va11ey, WA 99216 .
Re: Mica View C of E(SF-OI-OS)
Street & Drainage Submittal #3 Comments
Todd, .
On August 23, 2005 Public Works received your third submittal of the street and
drai.nage plans. Please update the following items on your next submittal:
Plan Sheets 1. On Sheet 5, please further detail the swale. This sha11 include the width, length,
and top of berm elevations. I suggest you add berms in the swale to slow the flow
and allow further treatment.
2. Please remove the approval starnp from plan subrnittals. This is reserved for the
FINAL mylar only. ~ Drainage Report 1. Your report indicates a required volume of each swale to be 49 c.f.; however on
page 19 it states 40 c.f. Please upda.te.
2. Please submit drywell testing i.nformation for the proposed Type A drywells
located in the swales. The only soil testing information given near the proposed
location is not acceptable for drywells. Prior to acceptance this information shall
be subnutted, reviewed and accepted,
3. Your report states galleries are to be used in the swales a.nd ponds; however they
are no indicated in the pia.ns. Please update the plans or the drai.nage report.
4. It appears there are numerous manholes/catch basins that do not have the required
0.75 feet freeboard. Please revise to meet this requirement.
Once this information is submitted, further review can occur. Other items may occur at
the review of the next submittal. An entire drainage report is not required, only the items
changed from the previous submittal. Please contact me at 688-0174 for any additional
questions.
SinceAely,
Sandra R.askell, P.E.
Development Engi.neer
cc: Bryan Walker - Property Owner .
Matt Zarecor - Spokane County Engineeri.ng Division
Department of Public Works - Development Project File
WHIPPLE CONSULTING ENGINEERS ,
POND VOLUME CALC SHEET
911512005
2004-19 Mlca View C of E's 16
by TRW
Besins Ponds Boliom (do of Ddvewey Bottom Squared.. Pond. Outiet Top of , Conic . Side Total • CoNc Side Total ,
. Area Driveways Area:@, Area : Side' • Bottom ' Pipe IE Berm • Volume to Slope Volume to . Volume Slope Valume •
.160 sf: less Drive . Elevatiorr: Elevation ElevaUon IE of Ouilet Pipe Volume. Pipe IE Elev. to Top of Berm Volume to Top of Berm
• sf ea sf sf . If- . ' ' . cf cf cf cF cf cf
I I I~~ I I 7~ I I I I I I I
A1A I swale . I 80 I 0 I 0 I 601 7.751 2175.001 2175.501 2178.001 301 121 421 601 461 106
I I I I I ~ I I I I I I I I I
A2A I swale I BO I 0 I 0 I 601 7.751 2175.001 2175.501 2178,001 .301 121 42 601 461 106
I I I I I I I I I I I I I I
A1 I A1 I 710 I 0 I_ 0 I 7101 26.651 2183.541 2184.041 2185,041 3551 401 3951 10851 3601 1425
I I I I I I I I I I I I I I
A2 I A2 I 710 I 0 I 0 I 7101 26.651 2183.541 2184.04 -2185,041 .3551 40I 3951 10851 3601 1425
I I I I I I I I I 1 I I I I I
6 I -B I 700 I 0 I 0I 7001 26.461 -2207.00I:- 2207.50I 2209,001 3501 401 3901 14001 6351 2035
I I I I I I I I I I I I I I I
C I C I 700 I 0 -I 0 I 700I 26.461- 2207.001 2207.501 2209.001 350I 401 3901 14001 8351 2035
I I I I I I I I I 1 I I I I I
0 I D 935 I 0 I 0 I 9351 30.581 2228.50 2227,00 2228.001 4681 461 5131 14031 4131 1815
I I I I I i I I I I I I
E I E ~ 935 I0 I 0I 9351 30.581 2226.50 2227,001 2228.00 .4681 46I 5131 14031 4131 1815
I I I I I I I I I I I I I I
F I F I 462 I 0 I 0 I 462I. 21,491 2221.481 2221.961 2223.181 2311. ,321 2631 7851 3731 1158
I I I I I I I I I I I I I I I
G I G I 462 I. 0 I 0 I 4621 21.491 2221.461 2221.961 2223.161 2311321 263I 7851 3731 1158
I I I I I I I I I I I I I I I
H I H.I 1120 I 0 I 0.1 11201 33.47I 2186,16 2166.661 2187.861. 5601 501 6101 19041 5801 2484
I I I I I I I I l I I I I I
I I I I 1120 I 0 I 0:I 11201 33,471 -2186.161. 2186.661 2187.861 5601 501 6101. 19041 5801 2484
I I I I I I I I I I I I I ~
J I J ~ 398 1 .0' 1 0 1 . 3981 19,951 2160.951' 2161.461 ' 2162.561 ' 1991 301 2291 6371 308 943
I I I I ( I ~ I I I I I I I I
K I K I 398 I 0 I 0 I 3981 19.951 2160.951 '-2161.451 2162.55 1991 301 2291 6371 3061 943
1 I I I I I I I 1 I I I I I
Cul-de•sac I L I 800 I 0 I0 I • 600I 24.491 2157.471 2157.871• 2159.371 3001 371 3371 11401 5311 1671
1 I I I I I I I 1 I I I I I ~
Tofals ( I I I I 9.370.001 1 I I I 4.685,001 535.761 5.220.761 15,647.4015.957.401 21,604,80
1 11
PEAK FLOW CALCULATION PROJECT; Mica View C of E BOWSTRING METHOD PROJECT: Mlca View C of E
50-Year Design Storm °DETENTION BASIN DESIGN BASIN: End Cul-de•Sac
DESIGNER BNG '
BASIN: End Cul-de•Sac DATE: 12-Sep-05 .
Tot. Area 11,642 SF 0.27 Acres .Time Increment (min) 5
Imp. Area 6,930 SF C= 0.9 Tfine of Conc. (min) 5.00
Perv. Area 4,712 SF C= 0.15 Outflow (cfs) 0.3
Wt. C= 0.60 208 Area = 6930 Design Year Flow 50
Area (acres) 0.27
CASE 1 .~-Impervious Area (sq ft) 6930
' - . 'C' Factor 0.60
10 ft. Overland Flow . •~Area' C 0.159
' Treatment Area 6,930
Ct = 0.15
L= 10 ft. . Tfine Time Inc. Intens. Q Devel. Vol.ln Vol.Out Storage
n = 0.40 • (min) (sec) (inlhr) (cfs) (cu ft) (cu ft) (cu ft)
S= 0.0200 5.00 300 4.58 0.73 293 90 203
Cul Tc = 1.11 min., by Equation 3•2 of Guidelines 5 300 4.58 0.66 264 90 174
10 600 3.21 0.46 322 180 142
50 ft. Gutter flow ••15 900 2.44 0.35 350 270 80
20 1200 1.98 0.28 -369 360 9
Z1 = 50.0 ForZ2 . 25 1500 1.68 024 385 450 •65
Z2 = 50.0 Type 6=1.0 30 1800 1.46 021 397 540 -143
n= 0.016 Rolled = 3.5 35 2100 1.30 0.19 409 630 •221
S= 0.0300 40 2400 1.18 0.17 422 720 -298
45 2700 1.08 0,16 435 810 -375
d= 0.0860 ft. Flow Width 4.3 ft. 50 3000 1.01 0,14 447 900 -453
55 3300 0.94 0,13 458 990 -532
. 60 3600 0.88 0.13 467 1080 -613
A R Q Tc Tc total I Qc 65 3900 0.83 0,12 477 1170 -693
0.37 0.04 0.73 0.42 5.00 4.58 0.73 ..~70 4200 0,79 0,11 489 1260 -771
75 4500 0.77 0.11 507 1350 -843
Qpeak for Case 1= 0.73 cfs . r 80 4800 0.75 0,11 529 1440 -911
85 5100 0,73 0.11 547 1530 -983
" .90 5400 0.70 0.10 550 1620 -1070
, .95 5700 0.68 0.09 546 1710 -1164
CASE 2 ' 100 6000 0.88 0.10 594 1800 -1206
Case 2 assumes a Time of Concentratlon less than 5 minutes so that the "208" TREATMENT REQUIREMENTS
peak flow =,90(Tc=5 intensity)(Imp. Area) = 0.86 cfs Minimum "208" Volume Required 289 cu ft
Provided Treatment Volume - Minimum 300 cu ft
DRYWELL REQUIREMENTS - 50 YEAR DESIGN STORM
So, the Peak flow for the Basin is the greater af the lwo flows, ; Maximum Storage Required by Bowstring 203 cu ft
0.73 cfs ;Provided Storage Volume to Inlet - Minumum 300 cu ft
' Number and Type of Drywells Required 1 Single
• • 0 Double
r ' •
PEAK FLOW CALCULATION PROJECT: Mica View C of E :BOWSTRING METHOD PROJECT: Mica View C of E °
10-Year Design Storm DETENTION BASIN DESIGN BASIN: End Cul-de-sac
DESIGNER; BNG '
BASIN: End Cui-de-sac DATE: 12-Sep-05
Tot. Area 11,642 SF 0.27 Acres Imp. Area 6,930 SF C= 0.90 , Time Increment (min) 5
Per, Area 4,712 SF C= 0.15 Time of Conc. (min) 5.00
Wt, C 0.60 208 Area = 6930.00 . Outflow (cfs) 0.3
- . Design Year Flow 10
CASE 1 : Area (acres) 0.27
. , Impervious Area (sq ft) 6930
10 ft. Overland Flow :'C Factor 0.60
. Area' C 0,159
Ct = 0.15 - . Asphaltic Area 6,930
,
L = 10 ft. • '
n= 0.40 Time Time Inc. Intens. Q Devel. Vol.ln Vol.Out Storage
S = 0.0200 . (min) (sec) (inlhr) (cfs) (cu ft) (cu ft) (cu ft)
5.00 300 3.18 0.51 204 90 114
Tc = 1.11 min., by Equation 3-2 of Guidelines
5 300 3.18 0.45 183 90 93
50 ft. Gutter flaw ..10 600 2.24 0.32 225 180 45
15 900 1.76 025 252 270 -18
Z1= 50.0 For Z2 - 20 1200 1.45 0.21 271 360 -89
Z2 = 50.0 Type B=1.0 . 25 1500 1.23 0.18 282 450 -168
n= 0.016 Rolled = 3.5 30 1800 1.05 0.15 286 540 -254
S= 0.0300 35 2100 0.91 0.13 287 630 -343
40 2400 0.81 0.12 290 720 -430
d= 0.0750 ft. Flow Width 3.8 ft. 45 2700 0.74 0.11 297 810 -513
50 3000 0,69 0.10 306 900 -594
55 3300 0,65 0.09 316 990 -674
A R Q Tc Tc total I Qc .~'60 3600 0.61 0.09 325 1080 -755
0.28 0.04 0.51 0.46 5.00 3,18 0.51 65 3900 0,58 0.08 335 1170 -835
~ 70 4200 0,56 0.08 348 1260 -912
Q peak for Case 1= 0.51 cfs 75 4500 0.55 0.08 365 1350 -985
80 4800 0.55 0.08 385 1440 -1055
' 85 5100 0.53 0.08 398 1530 -1132
' 90 5400 0.50 0.07 392 1620 -1228
CASE 2 95 . 5700 0.45 0.06 375 1710 -1335
100 6000 0.49 0.07 429 1800 -1371
Case 2 assumes a Time of Concentratlon less than 5 minutes so that the
peak flow =.90(Tc=5 intensity)(imp. Area) = 0.45 cfs '"208" TREATMENT REQUIREMENTS
• Minimum "208" Volume Requiretl 289 cu ft
Providetl Treatment Volume - Minimum 300 cu ft
,
So, the Peak flow for the Basin is the greater of the two flows, DRYWELL REQUIREMENTS -10 YEAR DESIGN STORM
0.51 cfs ` Maximum Storage Required by Bowstring 114 cu ft
Provided Storage Volume - Minimum 300 cu ft
Number and Type of Drywells Requlred 1 Single
' 0 Double
, ~ .
,
Hydraflow Plan View p
Ousfall Oidfafl Oultali Ouifail autfall
1
5 11
2 14
G
3
7 8
9
10
Project file: Pass Through Basins.stm No. Lines:11 09-13-2005
HydraDow Slorm Sewers 2003
. • ~
Page 1
- ~ Storrn Sewer Summary Report
• Line Line ID Flow Line Line Invert Invert Line HGL HGL Minor Dns
No. rate size length EL Dn EL Up slope down up loss line
(cfs) (in) (ft) (ft) (ft) N (ft) (ft) (ft) No.
1 Pass Through A 6.49 24 c 24.0 175.33 177.10 7.375 176.23 178.00 0.05
Eqa
2 Inserted Line 5.59 24 c 62.0 177.10 177.41 0.500 178.33 178.63 0.02
1
3 inserted Line 5.49 24 c 19.0 177.41 180.00 13.632 178.66 180.83 0.31
2
4 Pass Through B 2.89 24 c 122.0 203.44 204.05 0.500 204.04 205.18 0.04
End
5 Pass Through C 3.70 24 c 40.0 205.89 209.61 9.300 206.57 210.29 0.04
End
6 inserted Line 3.20 24 c 62.0 209.61 209.91 0.484 210.46 210.76 0.01
5
7 Inserted Line 2.70 24 c 18.0 209.91 215.00 28.278 210.78 215.58 0.20
6
8 Pass Through D 2.50 24 c 210.0 217.29 218.36 0.510 217.85 219.59 0.00
End
9 Inserted Line 2.00 24 c 90.5 218.36 218.76 0.442 219.60 219.67 0.00
8
10 Inserted Line 1.50 24 c 15.9 218.78 222.91 25.975 219.67 223.34 0.14
9
11 Pass Through E 2.11 12 x 60 b 100.0 100.00 102.00 2.000 100.18 102.18 0.09
End
Project File: Pass Through Basins.stm Number of lines: 11 Run Date: 09-13-2005
NOTES: c= circular, e= ellipUcal; b= box; Return period = 100 Yrs.; " Indicates surcharge condition.
Hydraflow Storm Sevrers 2003
Storm Sewer Profile Proj, file: Pass Through Basins.stm ~
d
Elev. (ft) ~ Lr
197.00
. . , „ . . . . . , . _
192.00
Ln:
~ . . ____,._,.A_,..,.
(M)
~
157.00 Ln:1 Ln- ~I
24 (in) 24
/
182.00
„ . _
~j_.~...~_~,.• j._.._.._.._._....,,,__.,
177.00
172.00
0 10 20 30 40 50 60 70 80 90 100 110
Reach (ft)
Hydraflow Storm Sewers 2003
~~orm Se~rer ~rof~ I~ Proj, fiile: Pass Tt~rough B2~sins stm +
~
E1ev. (ft)
216.00 213.00
, - ~
24 (ir,).,.~..,~.r
210.00
, - - ~ ..,e,o,,..,,.,,,,..,m,,,. .
„ . . . . . . . . . . . . . .
207.00 i _
. . , - ~
. . . . .
204,00
~ i
241.OD
o 10 20 30 40 50 60 70 80 90 100 110 120 1 30
- Reach {ft}
Hydraflaw Skorm 5ewers 2003
Storm Sewer Prvfiie Proj. file; Pass Through Basins.stm
~
1-
+
Elev. (ft)
238,00 _
,,,,,,,W,,,, - - - - -
,,,,,,,,,,,,,,,,,,y... . „ , , ,
. „ , . . , .
233.00 - -
~ Ln: 10
~ . „ 24_ { in}
228.0{} 3
, 24,,(in) , , , , 24 (in) , , ,
223.00
- , r- ~
.~..~W.;::;;;:,Y.X,,,.i,,, .
0
218.0
.,,,,,,,,.m....~_..,,...
.
,
213.00
0 25 50 75 100 125 150 175 200 225 250 275 300 325
Reach (ft)
Hydraflaw 5torm 5ewers 2003
Storm Sewer Profile Proj. file: Pass Through Basins.stm ~
P
l~
~
~
Elev. (ft)
236.00
. . . . . . . . . . _ . . . . . . . . „ . , , . . . , . . „ ,
229.00
~ _ a.. . . , .._..1..,.,...,,,,. _Ln:,4
24 (in)
. ~ _
222.00
~ Ln: 6
Ln:-5
24 (in) 24 (i_.~~~.____,~...... ,
~ . ~ . _ _ . . . _ . _ , ~ . . m....__,....., - - - _ , . _ _
215.00
~ _ = - - - - - ~ . - ~ - _ ► - ~u_~a=-
208.00 ~ : _ _ . _
201.00
0 10 20 30 40 50 60 70 80 90 100 110 120
Reach (ft) .
Hydraflow Storm Sewers 2003
Storm Sewer Profile Proj. file: Pass Through Basins.stm
~
~
4
Elev, (ft)
117.00
-
__._W.~.~e _
113.00
. . . . . . . . . . , , .
~ Ln:11
109.00 .
. . . . . ..0 . .
. , . . 1.2...,X ...6(n)...:.:...::.::._._... . . . __.._:;W:;., .
. . . . . . . . . . . . . , . . . . . . . . . , .
. . . . _ ~ ~ ~ . _ _ . . . . . ~ . _ ~ _ _
105.00
. . . . . . . . . . . , . , . . . . . . . . . . .
7>
~
-i
, . ~ .ti_ .
_I........ . ,
_W_ -
101.00
~ _........,,_......_m_._...
. . _ .,.mm. . . _ . . . . . _
. . . . . . , . . , . , . . . . . . , , . _ .:mm .W . . ~ .T.._~.:._ .
97.00 I
0 10 20 30 40 50 60 70 80 90 100
Reach (ft)
Hydraflow Storm Sewers 2003
• ~ f