2012, 09-07 Permit: SW-12002144 Sewer SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number:SW-12002144 09/07/2012
Expiration Date:
Project Description: SEWER CONNECTION Primary Contact: NORM'S EXCAVATING INC
Project Name: SUTTERS PH 3 Applicant: NORM'S EXCAVATING INC
Permit Type: SEWER Address: PO BOX 574
VERADALE,WA 99037
Phone: 509-928-0580
Email:
SITE INFORMATION:
Site Address: 14015 E 15TH AVE Owner: MATHEWS,GILBERT
Parcel Number: 45233.2702 Address: 14015 E 15TH AVE
VERADALE,WA 99037-9619
Subdivision: LEHI SUBDIVISION Phone:
Assessor's Description: LEHI SUB L2 B2 Email:
Inspection Area:
Water District:Vera Fire District:Spokane Valley Fire
Irrigation District#15
Zoning: Land Area: 10843 Square Feet
CONTRACTOR INFORMATION:
General Contractor
NORMSEI972BM
NORM'S EXCAVATING INC
PO BOX 574
VERADALE,WA 99037
509-928-0580
DETAILS:
Class Type Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
$125.00
FEE DETAIL:
Processing-Utilities $25.94
Utilities Permit $125.00
Total Fee: $150.94
CONDITIONS:
Inside Public Transit Benefit Area
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
CALL 1-800-424-5555 BEFORE YOU DIG—AT LEAST 2 WORKING DAYS IN ADVANCE.SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR&INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
Date Printed:09/07/2012 08:13:55 Printed by:IIS APPPOOLWSP.NET v4.0
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW-12002144 09/07/2012
Expiration Date:
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT(509)477-3604 FROM 8:30-5:00 MONDAY-FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED.PERMIT ALLOWS FOR A 30-MINUTE INSPECTION.ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION.INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF •
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED.SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME.BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed:09/07/2012 08:13:55 Printed by:IIS APPPOOL\ASP.NET v4.0