2013, 04-29 Permit: SW-13000548 Sewer SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW-13000548 Permit Issued Date: 04/29/2013
Expiration Date: 04/29/2014
Project Description: SEWER CONNECTION
Project Name: VALLEYVIEW
Primary Contact: M&L CONSTRUCTION INC Applicant: M &L CONSTRUCTION INC
Phone: 509-466-6332 Address: 12918 N FREYA ST
MEAD,WA 99021
Phone: 509-466-6332
Email:
SITE INFORMATION:
Site Address: 5722 E 16TH AVE Owner: RUHL, ROGER
Parcel Number: 35261.0202 Address: 5722 E 16TH AVE
SPOKANE,WA 99212-3206
Phone:
Assessor's Description: HEATHER PARK ADD L2 B2 Email:
Inspection Area: : (509)-477-3675
Water District: Spokane County Water Fire District: Fire District 8
District#3
Zoning: Land Area: 11250 Square Feet
CONTRACTOR INFORMATION:
MLCONI*063N9, Exp.09/03/2014
M &L CONSTRUCTION INC
12918 N FREYA ST MEAD,WA 99021
509-466-6332
DETAILS:
Class Type Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
$125.00
FEE DETAIL:
Processing-Utilities $26.32
Utilities Permit $125.00
Total Fee: $151.32
CONDITIONS:
Inside Public Transit Benefit Area
Parcel within 100 feet of pipeline(s)owned by the following: (Yellowstone)
CALL 1-800-424-5555 BEFORE YOU DIG--AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR&INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
SEWER PERMITS ARE VALID FOR ONE (1)YEAR FROM THE DATE OF ISSUANCE. FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT(509)477-3604 FROM 8:30-5:00 MONDAY-FRIDAY PRIOR TO COVER. ONE WORKING DAY NOTICE REQUIRED. PERMIT
ALLOWS FOR A 30-MINUTE INSPECTION.ADDITIONAL INSPECTION FEES APPLY AFTER 30 MINUTES.
Date Printed:04/29/2013 09:12:22 Project Coordinator:Julie Shatto
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW-13000548 Permit Issued Date: 04/29/2013
Expiration Date: 04/29/2014
THE SUBJECT PROPERTY HAS BEEN IDENTIFIED WITHIN PROXIMITY OF 100 FEET OR LESS FROM A KNOWN REGIONAL
UNDERGROUND PIPELINE. IN ACCORDANCE WITH STATE AND FEDERAL NOTIFICATION LAWS,AND AS A CONDITION OF
ISSUANCE OF THIS PERMIT,THE APPLICANT IS ADVISED OF THE REQUIREMENT TO CONTACT THE PIPELINE OPERATOR TO
DISCUSS THE CONDITIONS AND LOCATION OF ANY PROPOSED EXCAVATION ASSOCIATED WITH THIS PROJECT PRIOR TO
SUCH EXCAVATION OCCURRING. CONTACT INFORMATION FOR AREA PIPELINE OPERATORS IS AVAILABLE THROUGH OUR
PROJECT COORDINATORS, OR AT THE FRONT COUNTER. RCW 19.122.033
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed:04/29/2013 09:12:22 Project Coordinator:Julie Shatto