16-091.10 Meridian Construction: City Hall Iln - 0`'1. 1 . ID
SPOKANE VALLY CITY HALL
Architects West Inc.
Architecture • Landscape Architecture CHANGE ORDER-010
AL Issue Date: 3/22/2017
Exiiect more than great architecture
PROJECT OWNER CONTRACTOR DISTRIBUTION X
Spokane Valley City Hall City of Spokane Valley Meridian Construction Doug Powell X
10210 E.Sprague 11707 E.Sprague Ave. 12310 E Mirabeau Parkway Mark D'Agostino X
Spokane Valley,WA 99206 Suite 106 Suite 100 Steve Roth X
Spokane Valley,WA 99206 Spokane Valley,WA 99216 Jim Paras X
CONTRACT FOR: GENERAL CONSTRUCTION Todd Ottmar X
CONTRACT DATE: 5-20-2016
You are hereby directed to make the following changes in the contract: ,
REFERENCE DESCRIPTION AMOUNT
COP-055 Added Soffit in Room N204&Cable Tray Re-Route $3,090.46
' PR-015
RFI-100
COP-061 North Stair Veneer Support $2,789.02
CCD-014
' SK-27
COP-064 Finishes at Stair#2 Columns $787.68
SK-28
PR-018
COP-072 Door Hardware Changes $3,173.72
Sub#051
RFI-043
TOTAL $9,840.88
The Original Contract Sum was: $9,742,700.00
Net Change by PrevioUsly'Authorized Change Orders: $117,919.87
The Contract Sum prior to this Change Order was: $9,860,619.87
The Contract Sum will be increased by this Change Order in the amount of: $9,840.88
The new Contract Sum including this Change Order will be: $9,870,460.75
The Contract time will be unchanged/Changed by: 0 days
The Date of Substantial Completion as of the date of this Change Order therefore is: 7/25/2017
ARCHITECT CONTRACTOR OWNER REPRESENTATIVE
Architects West,Inc. Meridian Construction City of Spokane Valley
210 E.Lakeside Ave. 12310 E.Mirabeau Parkway,Ste 100 11707 E.Sprague Ave.,Suite 106
' Coeur d'Alene,ID 83814 Spokane Valley,WA 99216 Spokane VWIley,WA 99206
SIGNATURE: SIGNATOR : SIGNA
f JJ�I((''II\\
-DATE: 3/22/2017 DATE:_ —I(. DATE: , / /
q/cbi2pc7
1509–SPOKANE VALLEY CITY HALL CHANGE ORDER-010 –3/22/2017
Page 1of1