17-002.01 MDM Excavation: Euclid Ave ReconstructionSpokane DEPARTMENT OF PUBLIC WORKS fl-Oop.L.01 CHANGE ORDER NO: 1 CONSTRUCTION CONTRACT NO: 17-027 PROJECT: Euclid Avenue Reconstruction Project PRIME CONTRACTOR: MDM Construction, Inc dba MDM Excavation CONTRACT DATE: 5/4/2017 CIP NO: 251 DESCRIPTION OF CHANGES This Change Order pertains to Bid Schedule B - Euclid Avenue Trunk Sewer work, paid for by Spokane County. The change order replaces Euclid Avenue Trunk Sewer Project Plan sheets 4 and 5 with the attached plan sheets 4 and 5, dated 5-18-17, that lower Manhole Rim finish grade elevations 0.03' or less for Manholes Al - A5 and B1 - B5 so they will be recessed below pavement and not be hit by snowplows. Manhole B-5 has also been relocated several feet west to the Flora Rd centerline. This change results in no increase to the Contract amount as noted herein. Total Amount of this Change Order (incl. Tax): $ 0.00 PHYSICAL COMPLETION Original Contract Working Days: 80 Revisions by Prior Change Orders: 0 Revision By This Change Order. 0 Total Revised Contract Working Days: 80 CONTRACT AMOUNT THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT: ORIGINAL TOTAL CONTRACT AMOUNT $ 2,293,403.15 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT (through CD#J $ 0.00 TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 2,293,403.15 NET THIS CHANGE ORDER $ 0.00 $ 2,293,403.15 TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER CONTRACTOR ACCEPTANCE: The contractor hereby accepts this adjustme RECOMMENDED BY: APPROVED BY: APPROVED BY: DATE: 5 -36 - 17 der the terms Section 1-04.4 of the original contract. Project Manager Manager Deputy City Manager DATE: .,5' ' /y / % DATE:} -31- DATE: .S'- ! -/ ATTACHMENTS: Euclid Avenue Trunk Sewer Pian Sheets 4 and 5, dated 5-18-17 Distribution: ORIGINAL TO: City of Spokane Valley Clerk's Office COPIES TO: Contractor, PW Project File, Project Inspector, Finance Department COSV Form 9/5/2014