2012, 03-29 Permit: SW-12001015 Sewer SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW-12-001015 03/29/2012
Expiration Date: 03/30/2012
Project Description: NEW SEWER CONNECTION Primary Contact: CRAPO, DENNIS A&MELISSA A
Applicant: CRAPO, DENNIS A&MELISSA A
Permit Type: SEWER Address: 2602 N SULLIVAN RD
SPOKANE VALLEY,WA 99216
Phone:
Email:
SITE INFORMATION:
Site Address: 10722 E 39TH LN Owner: CRAPO, DENNIS A&MELISSA A
Parcel Number: 45332.3810 Address: 2602 N SULLIVAN RD
SPOKANE VALLEY,WA 99216
Subdivision: Ponderosa East Phone:
Assessor's Description: PONDEROSA EAST: LOT 10 (AFN 5956625) Email:
Inspection Area:
Water District:Spokane Fire District: Fire District 1
County Water District#3
Zoning: Land Area: 0.1873 acres/8160 sqft
CONTRACTOR INFORMATION:
General Contractor
DIAMOND ROCK CONSTRUCTION
2602 N SULLIVAN RD
SPOKANE,WA 99216
509-924-8964
DETAILS:
Class Type Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
$125.00
FEE DETAIL:
Processing-Utilities $25.94
Utilities Permit $125.00
Total Fee: $150.94
CONDITIONS:
CALL 1-800-424-5555 BEFORE YOU DIG--AT LEAST 2 WORKING DAYS IN ADVANCE.SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR& INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT(509)477-3604 FROM 8:30-5:00 MONDAY-FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30-MINUTE INSPECTION.ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
Date Printed:03/29/2012 13:03:38 Printed by:IIS APPPOOL\ASP.NET v4.0
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW-12-001015 03/29/2012
Expiration Date: 03/30/2012
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION. _
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED.SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE. _
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed:03/29/2012 13:03:38 Printed by:IIS APPPOOL\ASP.NET v4.0