2002, 01-23 Permit: 02000395 FurnaceSPOKANE COUNTY
SPOKANE COUNTY DIVISION OF BUILDING
AND CODE ENFORCEMENT
1026 WEST BROADWAY AVENUE • SPOKANE, WA 99260-0050
Site Information
Project Information
Site Address: 11406 E 44TH AVE
SPOKANE, WA 99203
Parcel Number 44042.0203
Subdivision: MYRON ESTATES #2
Block: Lot:
Zoning: UNK
Owner: RICHARDS, GARRY W
Address: 11406 E 44TH AVE
SPOKANE, WA 99203
Building Inspector: MARC STRAUB
Water Dist:
Project Number: 02000395 Inv: 1 Issue Date: 1/23/02
Permit Use: FURNACE
Applicant: R & R HEATING & A/C
4019E CENTRAL
SPOKANE, WA 99217
Contact R & R HEATING & A/C
4019 E CENTRAL
SPOKANE, WA 99217
Phone: (509) 484-1405
Phone: (509) 4S4-1405
Setbacks - Front: Left: Right: Rear:
Group Name:
Project Name:
Permits
Mechanical Permit
Contractor: R & R HEATING & AIR COND INC License #: RRHEAA* 106BW
GAS APPLIANCE<=100,000BT'` 1 $12.00 PROCESSING FEE
Total Permit Fee:
FOR MECHANICAL INSPECTIONS CALL (509) 477-3675.
$25.00
$37.00
Payment Summary
Total Fees AmountPaid AmountOwing
$37.00 $37.00 $0.00
Processed By: DAWN DOMPIER
Printed By: WENDEL, GLORIA
Tran Date
1/23/02
Page 1 of 1
Receipt #
421
Payment Amt
$37.00
PERMIT
tn' FILE
NOTICE
It Is the responsibility of the applicant/permittee, not Spokane County, to sae to it that the use described on the front of this permit complies with
applicable codes and requirements and that required inspectians are requested. Failure to request required inspections and obtain the necessary
approvals prior to progressing beyond the point where Inspections are required may necessitate removal of certain parts of the construction at the
applicant's/permlttee's or property owner's expense. At a minimum, the following inspections ARE REQUIRED by County Code:
1. FOOTING - when forms and reinforcement are In place and prior to placement of concrete—all structures, including manufactured homes.
NOTE: This inspection includes review of the structure's setbacks from property lines. Minimum setbacks are established by County zoning
regulations. Typically, side and rear yard setbacks are measured from property lines, while setbacks for yards abutting streets are measured from
the properly line or the center line of the roadway right-of-way, whichever provides the greater setback from the center line of the roadway right -at -
way. Curb lines and fence lines are not necessarily indicative of property lines. In some residential areas, the County can own as much as 20 feet of
fight -of -way between your properly and the actual improved streetcurb. The responsibility to comply with applicable setback provisions lies solely
with the permittee—neither Spokane County nor Its authorized representatives assume any responsibility for the verification or location of your
property lines. Please verify their location prior to locating your structure. Failure to properly locate the structure may require Its relocation at the
owner's/permittee's expense.
2. FOUNDATION - when forms and reinforcement are in place and prior to placement of concrete.
3. FRAMING - after all framing, bracing and blocking Is In place, and prior to concealing.
4. INSULATION - prior to the installation of drywall.
5. PLUMBING - after rough -in, before covering, and final.
6. MECHANICAL - rough -in of piping, before covering, metal chimneys before concealment, and final.
7. FINAL - when complete and prior to occupancy and/or use. Please provide 24 hours notice. All permits require final Inspection.
NOTE: In addition to inspection of the structure, this inspection Includes review of site Improvements (typically depicted on the approved site plan)
required by ordinance or as a condition of approval of this permit. Items such as the installation of lire hydrants, fire department access, on-site
drainage ("208 swales"), road Improvements, parking, and landscaping are common requirements of a permwVsite plan which must be com-
pleted prior to final approval of a building or issuance of a Cedifcate of Occupancy.
8. MANUFACTURED HOMES - Final inspection required when complete, stairs, handrails, skirting, etc. installed, and prior to occupancy; completed
inspection record card must be available on site.
9. SEWERS - prior to cover
10. RIGHT-OF-WAY/APPROACH - prior to placement of concrete, or, if gravel approach, after completion.
In addition to the above, any plumbing or mechanical systems or material which would be concealed by framing, drywall, concrete, etc., must be inspected
prior to cover. Check with the department far "special Inspections' In conjunction with commercial projects.
FOR INSPECTIONS:
TO INSURE PROMPT SERVICE, PLEASE GIVE ONE WORKING DAY/24 HOUR NOTICE .
PARTS OF YOUR PROJECT MAY REQUIRE PERMITS AND INSPECTIONS
FROM MORE THAN ONE AGENCY.
• Building, plumbing, mechanical and fire Inspectlons, Division
of Building and Code Enforcement
477-3675
• Construction In a flood plain, Division of Engineering & Roads
477-3600
• Electrical wiring, State Department of Labor and Industries
324-2640
• On-site waste disposal system, Spokane Regional Health District
. 324-1560
• Road cuts for utilities or driveways, Division of Engineering &
Roads - 48-HOUR NOTICE REQUIRED
477-3600
or State Department of Transportation
456-3000
• Sewer connection, Division of Utilities
477-3604
or City Public Works Department
625-6300
PERMIT EXPIRATION AND REFUNDS
Unless otherwise noted, this permit will be considered null and void by limitation If the work authorized by the permit is not commenced oris stopped for
a period of 180 days, unless a written request for an extension of the permit Is received and approved by the Building Official prior to expiration. At a
minimum an inspection should be requested at least once every 180 days to assure the validity of the permit. A permit may be renewed within one year
of the date of expiration for one-half the original fee, subject to certain limitations—please call us if you have any questions.
All refund requests must be made In writing by the appllcanVpermittee (shown on the reverse) no later than 180 days after the date of fee payment.
Refunds of not more than 80% of the permit fee paid may be authorized when no work has been done under the permit. No refunds may be authorized
more than 180 days after tee payment.
MISTAKE?
If you think we've,made an error In processing thls permit or in conducting Inspections pertaining to it, or find erroneous Information In the permit, please
bring it to our attention Immedl:�..�e filing a written request for correction within 10 working days of discovery. All such requests should be directed to
the Division of Building and • • •' ! orcement at the below address.
Spokane County Division of Building & Code Enforcement
1026 West Broadway Avenue
Spokane, WA 99260
Phone: (509) 477-3675 Fax: (509) 477-4703 TDD: (509)477-7133