16-091.15 Meridian Construction: City Hall Il9 -O91 . Is
Architects est Inc. SPOKANE VALLEY CITY HALL
f '� ;j '- Architecture • LandeooWrch«acture CHANGE ORDER-015
` 4.4Issue Date: 7/7/2017
.. - .. i xprJlr winrr f III rtE� � i st�rie Ltur,'t�
PROJECT OWNER CONTRACTOR DISTRIBUTION X
Spokane Valley City Hall City of Spokane Valley Meridian Construction Doug Powell X
10210 E.Sprague 11707 E.Sprague Ave. 12310 E Mirabeau Parkway Mark D'Agostino X
Spokane Valley,WA 99206 Suite 106 Suite 100 Steve Roth X
Spokane Valley,WA 99206 Spokane Valley,WA 99216 Jim Paras X
CONTRACT FOR: GENERAL CONSTRUCTION Todd Ottmar X
CONTRACT DATE: 5-20-2016
You are hereby directed to make the following changes in the contract:
REFERENCE DESCRIPTION AMOUNT
COP-089 Sprinkler Heads at Entry Vestibule $329.75
COP-100 Added soffit N301 $688.78
CCD-037
COP-105 Whiteboard Relocation $1,807.62
CCD-031
COP-108 Knife Plate/Bucket Corrections $1,979.13
COP-113 Council Chamber Ceiling Height Change $285.93
CCD-043
COP-120 Added N201/203 Conduit $620.40
CCD-046
•
TOTAL $5,711.61
The Original Contract Sum was: $9,742,700.00
Net Change by Previously Authorized Change Orders: $186,085.46
The Contract Sum prior to this Change Order was: $9,928,788.46
The Contract Sum will be increased by this Change Order in the amount of: $5,711.61
The new Contract Sum including this Change Order will be: $9,934,500.07
The Contract time will be unchanged/Changed by: 0 days
The Date of Substantial Completion as of the date of this Change Order therefore is: 8/31/2017
ARCHITECT CONTRACTOR OWNER REPRESENTATIVE
Architects West,Inc. Meridian Construction City of Spokane Valley
210 E.Lakeside Ave. 12310 E.Mirabeau,Parkway,Ste 100 11707 E.Sprague Ave.,Suite 106
Coeur d'Alene,ID 83814 Spokane Valley,WA 99216 Spokane Valley,WA 99206
SIGNATURE: SIGNATURE: SIGNATURE:
c(\tiort
DATE: 7/7/2017 DATE: DATE:
1509—SPOKANE VALLEY CITY HALL CHANGE ORDER-015 —7/7/2017
Page 1 of 1
210 East Lakeside Avenue I Coeur d'Alene,Idaho 83814 I ph 208-667-9402 I fx 208-667-6103 I www.archltectswest.com