2000, 12-13 Permit: 00011173 Mechanical FixturesSPOKANE COUNTY DIVISION OF BUILDING AND CODE ENFORCEMENT
1026 WEST BROADWAY AVENUE • SPOKANE, WA 99260-0050
(509) 477-3675
(
SITE INFORMATION PROJECT INFORMATION
Site Address: 6316 E 17TH AVE
SPOKANE, WA 99212
Parcel Number 35252.0318
Subdivision: VALLEY VIEW HILLS 1ST ADD
Block: Lot:
Zoning: UR -3 Urban Residential 3.5
Owner: HEIDENREICH, CHUCK
Address: 6316 E 17TH AVE
SPOKANE, WA 99212
Inspector: MARC STRAUB
Water Dist:
Project Number: 00011173 Inv: 1 Issue Date:
ermit Use: 2 FURNACES, AIR HANDLER & 2 PIPING
12/13/00
Applicant: R & R HEATING & A/C
4019E CENTRAL
SPOKANE, WA 99217 Phone: (509) 484-1405
Contact: R & R HEATING & A/C
4019E CENTRAL
SPOKANE, WA 99217 Phone: (509) 484-1405
etbacks - Front: Left: Right: Rear:
Group Name:
Project Name:
PERMIT(S)
Mechanical Permit
Contractor: R & R HEATING & AIR COND INC
License #: RRHEAA• 106BW
AIR HANDLER <=10,000 CFM I $12.00 PROCESSING FEE
GAS APPLIANCE<=100,000BT 2 $24.00 GAS PIPING
$25.00
2 $2.00
Total Permit Fee: $63.00
PAYMENT SUMMARY
Page I of 1 NOTES
PERMIT
Processed By: BURRIS, ROBIN
Printed By: SCHNEIDER, PENNY
Tran Date Receipt # Payment Amt
12/13/00 10491 $63.00
Total Fees AmountPaid AmountOwing
$63.00 $63.00 $0.00
FILE
NotICE
It is the responsibility of the applicant/perminee, not Spokane,County, to see to it that the use described on the front of this permit complies with
applicable codes and requirements and tha( required Inspections are requested. Failure to request required inspections and obtain the necessary
approvals prior to progressing beyond the point where Inspections are required may necessitate removal of certain parts of the construction at the
applicanfs/permittee's or property owner's expense. At a minimum, the following Inspections ARE REQUIRED by County Code:
1. FOOTING - when forms and reinforcement are In place and prior to placement of concrete—all structures, including manufactured homes.
NOTE: This inspection Includes review of the structure's setbacks from property lines. Minimum setbacks are established by County zoning
regulations. Typically, side and rear yard setbacks are measured from property lines, while setbacks for yards abutting streets are measured from
the property,line or the center line of the roadway right-of-way, whichever provides the greater setback from the center line of the roadway right-of-
way. Curb lines and fence lines are not necessarily indicative of property lines. In some residential areas, the County can own as much as 20 feet of
right-of-way between your property and the actual improved street/curb. The responsibility to comply with applicable setback provisions Iles solely
with the permittee—neither Spokane County nor Its authorized representatives assume any responsibility for the verification or location of your
property lines. Please verity their Iccafion prior to locating your structure. Failure to properly locate the structure may require Its relocation at the
owner's/permilee's expense.
2. FOUNDATION - when forms and reinforcement are in place and prior to placement of concrete.
3. FRAMING'- after all framing, bracing and blocking is in place, and prior to concealing.
4. INSULATION - prior to the Installation of drywall.
5. PLUMBING - atter rough -in, before covering, and final.
6. MECHANICAL - rough -in of piping, before covering, metal chimneys before concealment, and final.
7. FINAL - when complete and prior to occupancy and/or use. Please provide 24 hours notice. AB permits require final Inspection.
NOTE: In addition to Inspection of the structure, this inspection includes review of site Improvements (typically depicted on the approved site plan)
required by ordinance or as a condition of approval of this permit. Items such as the installation of fire hydrants, fire department access, onsite
drainage ("208 swales"), road improvements, parking, and landscaping are common requirements of a permiUsite plan which must be com-
pleted prior to final approval of a building or Issuance of a Certificate of Occupancy.
8. MANUFACTURED HOMES - Final inspection required when complete, stairs, handrails, skirting, etc. Installed, and prior to occupancy; completed
inspection record card must be available on site.
In addition to the above, any plumbing or mpchanical systems or material which would be concealed by framing, drywall, concrete, etc., must be
inspected prior to cover. Check with the department for "special inspections' In conjunction with commercial projects.
CALL 477-3675 FOR INSPECTIONS.
TO INSURE PROMPT SERVICE, PLEASE GIVE 24 HOUR NOTICE.
YOUR INSPECTOR IS
UNDER CERTAIN CIRCUMSTANCES, PARTS OF YOUR PROJECT MAY REQUIRE INSPECTIONS FROM OTHER AGENCIES:
• Road cuts for utilities or driveways, Division of Engineering 8 Roads • Sewer connection, Division of Utilities
477-3600 477-3604
or State Department of Transportafion or City Public Works Department
456-3000 625-6300
• On-site waste disposal system, Spokane Regional Health District • Electrical wiring, State Department of Labor and Industries
324.1560 324-2640
• Construction in a flood plain, Division of Engineering & Roads
477-3600
PERMIT EXPIRATION AND REFUNDS
Unless otherwise noted, this permit will be considered null and void by limitation if the work authorized by the permit is not commenced or Is stopped
for a period of 180 days, unless a written request for an extension of the permit is received and approved by the Building Official prior to expiration. At
a minimum an inspection should be requested at least once every 160 days to assure the validity of the permit. A permit may be renewed within one
year of the date of expiration for one-half the original fee, subject to certain limitations—please call us If you have any questions.
AMI refund requests must be made in writing by the applicant/permittee (shown on the reverse) no later than 180 days after the date of fee payment.
Refunds of not more than S0% of the permit fee paid may be authorized when no work has been done under the permit. No refunds may be authorized
more than 180 days after fee payment.
MISTAKE?
If you think we've made an error in processing this permit or in conducting inspections pertaining to It, or find erroneous information In the permit,
please bring it to our attention Immediately by filing a written request for correction within 10 working days of discovery. All such requests should be
directed to the Division of Building and Code Enforcement at the address found on the face of this permit.
1 certify that I am the owner or am authorized by the owner to make this application and that I have examined this permit/application, stale that the
Information contained In It and submitted by me or my agent to compile said permlt/application Is true and correct, and authorize Spokane County
to proceed with processing. In addition, I have read and understand the INSPECJION REQUIREMENTS/NOTICE provisions Included herein and
agree to comply with same. All provisions of laws and ordinances governing thls type of work will be complied with whether specified hereln or not.
1 understand that the Issuance of this permltlapplicatlon and any subsequent inspection approvals or Certificates of Occupancy shall not be
construed to give authority to violate or cancel the provisions of any state or local law regulating construction or agreement concerning thls
property, or as a warranty of conformance with the provisions of any state or local laws regulating construction.
SIGNATURE OF
APPLICANT/PERMITTEE APPLICATION
OR AUTHORIZED AGENT DATE