2013, 05-28 Permit: SW-13000835 SewerSPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -13000835
Permit Issued Date: 05/28/2013
Expiration Date: 05/28/2014
Project Description:
Project Name:
Primary Contact:
Phone:
SEWER CONNECTION
VALLEWIEW
LARRY MILLER EXCAVATING
509-218-3335
Applicant: LARRY MILLER EXCAVATING
Address:
Phone:
Email:
7117 E RUTTER AVE
SPOKANE, WA 99212
509-218-3335
SITE INFORMATION.
Site Address:
Parcel Number.
6404 E 17TH AVE
35252.0308
Assessor's Description: VALLEY VU HILL 1ST L8B3
Inspection Area: : (509)-477-3875
Zoning:
Owner:
Address:
Phone:
Email:
Water District: Spokane County Water
DIshict#3
PIERCE, RONALD D
6404 E 17TH AVE
SPOKANE, WA 99212-0145
Fire District: Fire District 8
Land Area: 14000 Square Feet
CONTRACTOR INFORMATION
LARRYME918DR, Exp. 03/19/2015
LARRY MILLER EXCAVATING
7117 E RUTTER AVE SPOKANE, WA 99212
509-218-3335
DETAILS-
Class
ETAILS
Class
SEWER
Typo
Quantity Unit Charge Value
FEE DETAIL'
Processing - Utilities
Utilities Permit
SEWER CONNECTION
Total Fee:
$26.32
$125.00
$151.32
1 $125.00 $125.00
$125.00
CONDITIONS'
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
SEWER PERMITS ARE VALID FOR ONE (1) YEAR FROM THE DATE OF ISSUANCE. FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER. ONE WORKING DAY NOTICE REQUIRED. PERMIT
ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
Date Printed 05/28/2013 10:08:10 Project Coordinator: Kathy Cummings
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -13000835 Permit Issued Date: 05/28/2013
Expiration Date: 05/28/2014
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 05/28/2013 10:08:10 Project Coordinator. Kathy Cummings