17-040.01 WM Winkler: Bowdish & 12th Sidewalks Spokane
Val ley CHANGE ORDER NO: 1
ENGINEERING CONSTRUCTION CONTRACT NO: 17-040 01
PROJECT: Bowdish Rd. and 12th Ave. Sidewalk Project CONTRACT DATE: 4/4/2017
PRIME CONTRACTOR: Wm. Winkler Co. CIP NO: 239
DESCRIPTION OF CHANGES
-Additional paving on Bowdish Road between 8th Ave and 12th Ave (within project limits)
Item No. Description Unit Quantity Unit Price Total
501 Bowdish Rd-Grind and HMA Inlay, 2 In. Depth LS 1 $23,669.20 $23,669.20
Total Amount of this Change Order(incl. Tax): $23,669.20
PHYSICAL COMPLETION
Original Contract Working Days: 35 Revision By This Change Order: 3
Revisions by Prior Change Orders: 0 Total Revised Contract Working Days: 38
CONTRACT AMOUNT
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT:
ORIGINAL TOTAL CONTRACT AMOUNT $ 417,112.50
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT $ 0.00
TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 417,112.50
NET THIS CHANGE ORDER $ 23,669.20
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 440,781.70
CONTRACTOR ACCEPTANCE: - DATE: b I ��
The contractor hereby accepts this adjustment under a terms of of the original contract.
RECOMMENDED BY: eigel, DATE: gAtii
APPROVED BY:
Project Manager
DATE: g'
//7
CIP Ma ger
APPROVED BY:
4,4/ DATE: g
City Manager
ATTACHMENTS:
Change Order Description
Distribution:
ORIGINAL TO: City of Spokane Valley Clerk's Office
COPIES TO: Contractor, Project File, Project Inspector, Finance Department
S(1okane
ValleChange Order 1
tj Construction Contract No: 17-040
THE CONTRACT IS MODIFIED AS FOLLOWS:
WORK TO INCLUDE
Background:
City would like to extend the asphalt paving to the full width of northbound Bowdish from 12th Avenue to 8th
Avenue within the project limits(Sta 12+06 to 26+06).
The original Contract plans call for removing and replacing the eastern half of the roadway(6' Rt to 12' Rt)in order
to install new curbing and patch the asphalt back to the curb meeting the Pavement Cut Policy. This would create
two different pavement sections in one lane with a joint down the middle of the lane.
City proposes to grind the western half of the lane(0' Rt to 6' Rt)a depth of 2 inches. Then the final 2"lift of
asphalt can be placed the entire width of the lane,providing a smoother lane,removing existing wheel rutting and
pavement distresses in the western half lane and moves the pavement joint to the center of the road,further away
from typical tire paths.
City submitted Request for Pricing#1 on 7/27/17 for the proposed work
Wm. Winkler submitted price quote on 8/1/17 and a revised price on 8/2/17.
Description of Change:
This change order pays for all the work necessary to grind and pave back a depth of 2 inches of asphalt from Sta
12+06 to 26+06 between 0' Rt. to 6' Rt.
Specification:
No changes have been made to Contract Specifications because of this change.
Plans:
No changes have been made to Contract Plans because of this change.
Time:
Three additional days is added to the Contract due to this change.
Measurement:
There is no specific measurement for the new lump sum item"Bowdish Rd-Grind and HMA Inlay,2 In.Depth."
Payment:
Payment for new item#501-"Bowdish Rd-Grind and HMA Inlay,2 In. Depth"lump sum
The lump sum price for`Bowdish Rd-Grind and HMA Inlay,2 In. Depth", shall be full pay for all costs necessary
to furnish all labor,tools,equipment,and materials to grind a 6ft width of pavement(2"depth),haul and dispose of
pokane
Change Order No: 1
Valley Construction Contract No: 17-040
grindings,clean and prepare surface for paving,HMA paving(2"depth),and adjust three manhole lids within the
grinding area.
Summary of Quantities:
A new Schedule E is added to the Contract for this roadway work that will include the following item.
Previous New Estim
Bid hem Description Unit Qty Unit Price kmount
Qty. Qty Change
501 Bowdish Rd-Grind and HMA L.S. - 1 +1 $23,669.20 $23,669.20
Inlay,2 In.Depth
TOTAL $23,669.20
ii"kerne
Bowdish Rd & 12th Ave. Sidewalk - #0239
41000 Val ley Aug 1 2017
Expenditure Accounts Budget
PE Description Current Change New
303.000.239.595.10.10.00 Salaries &Wages 18,200 2,850 21,050
303.000.239.595.10.10.99 Overtime - -
303.000.239.595.10.20.00 Employee Benefits 6,350 1,700 8,050
303.000.239.595.10.20.99 Employee Benefits - -
303.000.239.595.10.41.02 Engineering &Architectural 20,000 (7,375) 12,625
303.000.239.595.10.41.06 Prof. Svcs -Survey 9,000 2,500 11,500
303.000.239.595.10.41.07 Prof. Svcs. -Geotech - -
303.000.239.595.10.41.17 Advertising 2,000 (775) 1,225
303.000.239.595.10.49.03 Printing & Binding 1,000 (350) 650
303.000.239.595.10.49.06 Miscellaneous Services - -
303.000.239.595.10.99.99 PE Contingency 1,874 (1,874) -
I Sub Total: 58,424 (3,324) 55,100
RW Description Current Change New
303.000.239.595.20.41.02 Engineering &Architectural - 3,775 3,775
303.000.239.595.20.41.05 Professional Services 20,000 (6,450) 13,550
303.000.239.595.20.61.01 ROW Acquisition 10,000 . (525) 9,475
I Sub Total: 30,000 (3,200) 26,800
CN Description Current Change New
303.000.239.595.61.10.00 Salaries &Wages 36,000 (11,000) 25,000
303.000.239.595.61.10.99 Overtime - -
303.000.239.595.61.20.00 Employee Benefits 12,600 (3,600) 9,000
303.000.239.595.61.20.99 Employee Benefits - -
303.000.239.595.61.41.08 Prof. Svcs. Mat.Testing 9,824 (2,824) 7,000
303.000.239.595.61.41.10 Prof. Svcs. -Consulting - -
303.000.239.595.61.41.17 Advertising - -
303.000.239.595.61.49.03 Printing & Binding - -
303.000.239.595.61.63.00 Construction: Sidewalks 325,458 25,242 350,700
303.000.239.595.61.99.99 CN Contingency: Sidewalks 4,036 (1,294) 2,742
402.000.239.595.40.63.00 Construction - Drainage 60,000 10,000 70,000
.
Construction: Road - 25,000 25,000
Sub Total: 447,918 41,524 489,442
Project Total: I 536,342 35,000 571,342
Funding Accounts Budget
PE Description Current Change New
0334.0380 TIB 253,430 253,430
0374.0380 TIB 30,000 30,000
0397.3010 301 222,912 222,912
0397.4020 402 30,000 10,000 40,000
311 - 25,000 25,000
I Project Total: 536,342 35,000 571,342
APPROVALS
Project Manager Date CIP Manager Date
Deputy City Manager Date Finance Director Date
3 Accounting will look up BARS code according to Description
Notes
-Moves unused PE & ROW funds to Construction
-Budget increase of$10k from Fund 402 to cover the contract amount for storm improvements
-Budget increase of$25k from Fund 311 to provide pavement preservation on Bowdish Rd.