17-002.03 MDM Excavation: Euclid Ave Reconstruction • •
Spokane
.0 .1;Va11ey
CHANGE ORDER NO: 3
DEPARTMENT OF PUBLIC WORKS CONSTRUCTION CONTRACT NO: 1-7-02TOS
PROJECT: Euclid Avenue Reconstruction Project CONTRACT DATE: 5/4/2017
PRIME CONTRACTOR: MDM Construction,Inc dba MDM Excavation CIP NO: 251
DESCRIPTION OF CHANGES
This Change Order pertains to Bid Schedule A, Road work, paid for by City of Spokane Valley.
The change order pays per WSDOT Force Account procedures,for removal, disposal and backfilling of miscellaneous items
found in the subgrade discovered duting road ekcavation activities. This change results in no Increase to the Contract time.
item No. Description Unit Quantity Unit Price Total
CO 3 Removal of misc. subgrade items EST 1 $ 10,000.00 $ 10,000.00
Total Amount of this Change Order(incl.Tax): $ 10,000.00
PHYSICAL COMPLETION
Original Contract Working Days: 80 Revision By This Change Order: 0
Revisions by Prior Change Orders:•_ 0 Total Revised Contract Working Days:. 80
CONTRACT AMOUNT
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT:
ORIGINAL TOTAL CONTRACT AMOUNT $ 2,293,403.15
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT.4through°CO#_2), $ 700.00
TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 2,294,103.15
NET THIS CHANGE ORDER $ 10,000.00
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER , $ 2,304,103.15
CONTRACTOR ACCEPTANCE: (1�l�Yv\ DATE: 06/e)9/x`7
The contractor hereby accepts this adjustment under t e terms of Section 1-04.4 of the original contract.
RECOMMENDED BY: DATE: .5•/ 7
COS • •ect Manager
APPROVED BY: j j 4!' 40- DATE: 6/ /I
Pok•no County Construction Manager
1
APPROVED BY: - DATE: 6/Cfp 01)
CIP Man r
APPROVED BY: ��!--. DATE: 6 f Y--/7
Deputy City Manager
ATTACHMENTS:
DIstdbutlon:
ORIGINAL TO: City of Spokane Valley Clerk's Office
COPIES TO: Contractor,PW Project Flle,Project Inspector,Finance Department
COSV Form 9t5r2014