17-002.05 MDM Excavation: Euclid Ave Reconstruction Spokane
Valley CHANGE ORDER NO: 5
DEPARTMENT OF PUBLIC WORKS CONSTRUCTION CONTRACT NO: -1-7427-11-002
PROJECT: Euclid Avenue Reconstruction Project CONTRACT DATE: 5/4/2017
PRIME CONTRACTOR: MDM Construction,Inc dba MDM Excavation CIP NO: 251
DESCRIPTION OF CHANGES
This Change Order pertains to Bid Schedule B, Sewer work, paid for by Spokane County.
The change order pays for side sewer sleeves.
Item No. Description Unit Quantity Unit Price Total
501 Side Sewer Sleeve LF 300 $ 18.00 $ 5,400.00
8.8%Tax 475.20
Total Amount of this Change Order(incl.Tax): $ 5,875.20
PHYSICAL COMPLETION
Original Contract Working Days: 80 Revision By This Change Order. 0
Revisions by Prior Change Orders: 1 Total Revised Contract Working Days: 81
CONTRACT AMOUNT
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT:
ORIGINAL TOTAL CONTRACT AMOUNT $ 2,293,403.15
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT(through co* 4) $ 19,800.80
TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 2,313,203.95
NET THIS CHANGE ORDER $ 5,875.20
TOTAL CONTRACT AMOUNT INCLU G THIS CHANGE ORDER $ 2,319,079.15
CONTRACTOR ACCEPTANCE: LtDATE: 407—
The contractor hereby accepts this adjustment under the terms of ection 1-04.4 of the original contract.
RECOMMENDED BY: .; - DATE: 7, /ie, /7
Manager
APPROVED BY: - 'I DATE: - 03 -i 4-
S"•kane County Construction Manager
APPROVED BY: 9x01 i., DATE: 7 -1
CIP Mane r
APPROVED BY: DATE: -7 —'9 — i 7
Deputy City Manager
ATTACHMENTS:
Distribution: ORIGINAL TO: City of Spokane Valley Clerk's Office
COPIES TO: Contractor,PW Project File,Project Inspector, Finance Department
COSV Form 9/512014