Loading...
14-039.16 Max J Kuney: Sullivan West Bridge Replacement Ph 2 S1$okan ems'`' .0,0 Valley CHANGE ORDER NO: 16 DEPARTMENT OF PUBLIC WORKS CONSTRUCTION CONTRACT NO: 14-039 PROJECT: Phase 2-Sullivan Road West Bridge Replacement Project CONTRACT DATE: 8/8/2014 PRIME CONTRACTOR: Max J.Kuney Company CIP NO: 0155 DESCRIPTION)OF CHANGES This Change Order pertains to: Schedule C-Work on State-Owned Lands Signal Pole Extra Foundation Depth The signal pole foundation depth shown in the Signal Standard Detail Chart on drawing Sheet TF-02 for a 3-foot round foundation is increased from 9 feet deep to 13 feet deep.Payment for the additional 4 feet of foundation depth shall be made on a force account basis in accordance with Section 1-09.6 of the Standard Specifications. Two working days are added to the Contract time to compensate for the impact of this issue to the project critical path. Sullivan Park Lower Parking Lot-Remove and Replace Unsuitable Material The Contractor shall remove approximately one foot of unsuitable soil materials encountered beneath the Sullivan Park lower(south) parking lot pavement restoration area and replace with granular rock material. Place geotextiie fabric over the unstable area and place and compact the Imported granular material. Payment for removal and replacement of the unsuitable material shall be made on a force account basis in accordance with Section 1-09.6 of the Standard Specifications. Two working days are added to the Contract time to compensate for the Impact of this Issue to the project critical path. Centennial Trail Realignment Phase 2•Contract Time Extension Change Order No.11 for Phase 2 of the Centennial Trail realignment work was executed with the understanding that additional working days related to that work would be addressed in a later change order. Thirty-one working days are added to the Contract time to provide compensation for impacts to the project critical path schedule related to the Centennial Trail realignment Phase 2 This change order will be effective only when fully executed by the Contractor and the City. It is understood and agreed that this change order provides full and complete compensation to the Contractor both as to money and time for all costs,damages and expenses arising out of,or Incidental to,the changes to the Contract described herein,including and and all delay and impact. jtem No. Description Una Quantity Unit Price Baal CO-16.1(C) Signal Pole Extra Foundation Depth FA 1 $ 7,084.52 $ 7,084.52 CO-16.2(C) Sullivan Park-Remove and Replace Unsuitable Material FA 1 $ 18,228.32 $ 18,228.32 CO-16.3(C) Centennial Trail Realignment Phase 2-Time Extension FA 1 $ - $ 0.00 Subtotal $ 25,312.84 8.8%Sales Tax(applicable only to Bid Schedules C,D,and E) $ 2,227.53 Total Amount of this Chan e Order incl.Tax): $ 27,540.37 PHYSICAL COMPLETION Original Contract Working Days: 484 Revision By This Change Order. 35 Revisions by Prior Change Orders:,_- 51 Total Revised Contract Working Days: 570 CONTRACT AMOUNT THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT: ORIGINAL TOTAL CONTRACT AMOUNT $ 12,307,560.31 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT(through Co#15) $ 479,914.95 TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 12,787,475.26 .......... NET THIS CHANGE ORDER $ 27,540.37 TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 12,815,015.63 CONTRACTOR ACCEPTANCE: 2..4 _- DATE: The contractor hereby accepts this ad. m t u •_ .1"1:er s of Sectiir=4.4 of the original contract. I RECOMMENDED BY: , `.�� DATE: `1/b ��� Project M-' ge APPROVED BY: /%j(//E" �-�" DATE: Lv — -/7 Publics Director p, APPROVED BY: VJ1 --���1l�WlAN^— DATE: 1(3/41h 7 City Manager ATTACHMENTS: None COPIES TO: Contractor,PW Project File,Project Inspector,Finance Department,WSDOT ER Local Programs Page 1 of 1 COSV Form 9152014