14-039.19 Max J Kuney: Sullivan West Bridge Replacement Ph 2 nna1■ 1■ 1ey, CHANGE ORDER NO: 19 DEPARTMENT OF PUBLIC WORKS CONSTRUCTION CONTRACT NO: 14-039 PROJECT: Phase 2-Sullivan Road West Bridge Replacement Project CONTRACT DATE: 8/8/2014 PRIME CONTRACTOR: Max J.Kuney Company CIP NO: 0155 DESCRIPTION OF CHANGES _ This Change Order pertains to: Schedule A-Sullivan Road West Bridge Replacement Schedule C-Work on State-Owned Land Plant Establish Requirement Termination The City and Contractor mutually agree to terminate the plant establishment requirements specified in Section 8-02.3(13)of the Standard Specifications. Termination of the plant establishment requirements shall become effective when all work(except plant establishment)specified in the Contract is completed and all the obligations of the Contractor have been fulfulled(the Completion Date as specified in Section 1-01.3 of the Special Provisions). In exchange for the Contractor's reduced plant establishment responsibilities,a 20 percent credit is applied to the unit price of pay items that include plant establishment as set forth below. The unit price credits shall be applied to final quantities.. This change order will be effective only when fully executed by the Contractor and the City. It is understood and agreed that this change order provides full and complete compensation to the Contractor both as to money and time for all costs,damages and expenses arising out of,or incidental to,the changes to the Contract described herein,including and and all delay and impact. Item No. Description jLt Quantity Unit Price ijagl Schedule A CO-19.1(A) Credit for Pay Item A-102-PSIPE Shrubs-2 Gal. EA 32 $ (6.00) $ (192.00) CO-19.2(A) Credit for Pay Item A-103•PSIPE Shrubs-1 Gal. EA 48 $ (2.00) $ (96.00) CO-19.3(A) Credit for Pay Item A-104-PSIPE Tree-5 Gal. EA 10 $ (20.00) $ (200.00) CO-19.4(A) Credit for Pay Item A-105-PSIPE Tree-3 Gal. EA 19 $ (19.00) $ (361.00) CO-19.5(A) Credit for Pay Item A-106-PSIPE Tree-1 Gal. EA 21 $ (5.00) $ (105.00) Schedule A Subtotal $ (954.00) Schedule C CO-19.6(C) Credit for Pay Item C-40-PSIPE Shrubs-1 Gal. EA 139 $ (2.00) $ (278.00) CO-19.7(C) Credit for Pay Item C-41-PSIPE Tree-5 Gal. EA 15 $ (14.00) $ (210.00) CO-19.8(C) Credit for Pay Item C-42-PSIPE Tree-1 Gal. EA 41 $ (8.40) $ (344.40) CO-19.9(C) Credit for Pay Item CO-8.6(C)-PSIPE Tree-1 Gal. EA 14 $ (6.40) $ (89.60) CO-19.10(C) Credit for Pay item CO-8.24(C)-PSIPE Tree-3 Gal. EA 15 $ (23.60) $ (354.00) Schedule C Subtotal $ (1,276.00) 8.8%Sales Tax(applicable only to Old Schedules C,D,and E) $ (112.29) Total Amount of this Change Order incl.Tax: $ (2,342.29) PHYSICAL COMPLETION Original Contract Working Days:_.._.484Revision • By This Change Order.____ 0 ___ Revisions by Prior Change Orders:_,__,94 ___ Total Revised Contract Working Days: _.578 _ CONTRACT AMOUNT THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT: ORIGINAL TOTAL CONTRACT AMOUNT _,__....._... ._.._..._. ..__._ ._.....,..............._....._ .w.�_ $ 12,307,560.31 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT(through co 818) $ 520,124.66 TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 12,827,684.97 NET THIS CHANGE ORDER _..._._._...._.._._.. __..._.__.._ _..__ ....__...__._ __._..... $ (2,342.29) TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 12,825,342.68 CONTRACTOR ACCEPTANCE: ........11, /— Ilk DATE: 8 /q /17 + The contractor hereby accepts this-• tme un• 'erms of Secti V •'.4 of the original contract. V2.43 RECOMMENDED BY: :i'� ) (' tiii. DATE: `lio //k/2.h Project Manan, APPROVED BY: DATE: rd - - /7 APPROVED BY: YAaAk__ d &tu- (074f 7 City Manager ATTACHMENTS: None Page 1 of 1 COSV Form 9/5/2014 COPIES TO: Contractor,PW Project File,Project Inspector,Finance Department,WSDOT ER Local Programs