16-091.19 Meridian Construction: City Hall let
SPOKANE
SPOKANE VALLEY CITY HALL
fir ArchitectsWest CHANGE ORDER-019
Issue Date: 11/16/2017
Eypt'ct rr o E.t>ari l;re...t art] stx.ti,r
PROJECT OWNER CONTRACTOR DISTRIBUTION X
Spokane Valley City Hall City of Spokane Valley Meridian Construction Doug Powell X
10210 E.Sprague 11707 E.Sprague Ave. 12310 E Mirabeau Parkway Mark D'Agostino X
Spokane Valley,WA 99206 Suite 106 Suite 100 Steve Roth X
Spokane Valley,WA 99206 Spokane Valley,WA 99216 Jim Paras X
CONTRACT FOR: GENERAL CONSTRUCTION Todd Ottmar X
CONTRACT DATE: 5-20-2016
You are hereby directed to make the following changes in the contract:
REFERENCE DESCRIPTION AMOUNT
COP-096R3 Exterior Can Light insulation Enclosure $1,182.07
COP-140 West Entry aro Floor Roof Edge Detail Change $4,604.50
COP-148 Security Camera Adjustment $511.83
TOTAL $6,298.40
The Original Contract Sum was: $9,742,700.00
Net Change by Previously Authorized Change Orders: $314,286.11
The Contract Sum prior to this Change Order was: $10,056,986.11
The Contract Sum will be increased by this Change Order in the amount of: $6,298.40
The new Contract Sum including this Change Order will be: $10,063,284.51
The Contract time will be unchanged/Changed by: 0 days
The Date of Substantial Completion as of the date of this Change Order therefore is: 9/5/2017
ARCHITECT CONTRACTOR OWNER REPRESENTATIVE
Architects West,Inc. Meridian Construction City of Spokane Valley
210 E.Lakeside Ave. 12310 E.Mirabeau Parkway,Ste 100 11707 E.Sprague Ave.,Suite 106
Coeur d'Alene,ID 83814 Spokane Valley,WA 99216 Spokane Valley,WA 99206
SIGNATURE: SIGNATURE: SIGNATURE:
.-.�
DATE: 11/16/2017 DATE: I ( DATE: t`
17-