18-050.02 MDM Construction: Mission Ave Improvements • Spokane • vv CHANGE ORDER NO: 2 ENGINEERING DIVISION CONSTRUCTION CONTRACT NO: 18-050 PROJECT: Mission Avenue Improvement Project CONTRACT DATE: 5/31/2018 PRIME CONTRACTOR: MDM Construction,Inc. CIP NO: 123 DESCRIPTION OF CHANGES The project design calls for a 12'diameter PVC storm drain line(P-31)'on the north side of Mission Avenue to cross under a 6 inch diameter Consolidated Irrigation District 19(CID 19)6 inch diameter Asbestos Concrete waterline running on the west side of Greenacres Road on the west side of the Mission Avenue/Greenacres intersection. The storm water design assumed the waterline was installed with 4 foot of cover and the 6 foot deep storm waterline would pass underneath. The waterline,constructed in 1967 had 6 feet of cover, resulting in a conflict. CID 19 has prior rights and did not wish to reconfigure the waterline. This change order revises the stormwater piping and grades to pass over the CiD 19 waterline. It also pays, per force account for the work involved to remove the installed pipe P-30, reset SDMH-1 and core in a new western inlet at the revised invert elevation. This Change Order revises the following storm drain piping changes shown on Plan Sheets 28 and 30,revised•8/17/18: Pipe Diameter Material Length P29 12 PVC Revised length from 58 LF to 6OLF P30 Revised from 10"to 6" Revised from PVC to Ductile Iron 35' P30 is installed and will be paid for as installed. Removal of Pipe P30 will be paid Under force account. P31 12" Revised from PVC to Ductile iron Revised length from 211 LF to 209 LF SDMH-1 has been set. Payment for setting 2 feet low on 8/16/18; resetting per this change; and coreholing a new western pipe invert will be made by force.acount., Item No. Description Unit Quantity Unit Price Total CO-2.1 Drainage Crew Standby Time 7-5-18 FA EST $ 1;900.00 $ 1,900.00 CO-2.203 Solid Wall PVC Storm Sewer Pipe 12 In. Diam. LF -209 $ 34.00 $ (7,106.00) CO-2.204 Ductile iron Storm Sewer Pipe 6 In. Diam. LF 35 $ 58.50 $ 2,047,50 CO-2.205 Ductile Iron Storm Sewer Pipe 12 In. Diam. LF 209 $ 86.00 $ 17,974.00 Total Amount of this Change Order(incl.Tax): $ 14,815.50 VERBAL APPROVAL AND JUSTIFICATION Independent Justification on File Yes • Verbal Approval , Date 7/6/2018 1 Verbal Approval by. Gloria Mentz PHYSICAL COMPLETION Original Contract Working Days: 90 Revision By This Change Order: 1 Revisions by Prior Change Orders; 1.5 Total Revised Contract Working Days: 92.5 COSV Form 9/5/2014 Mission Ave Improvement Project-Contract 18-050 CO 2-Pg 2 CONTRACT AMOUNT THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT: ORIGINAL TOTAL CONTRACT AMOUNT $ 2 966,440.40 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT(ttirough•co#1) $ 16,965.35 571 TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 2,983,405.75 NET THIS CHANGE ORDER $ 14,815.50 •N16 TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 2,998,221.25 l.0-jo CONTRACTOR ACCEPTANCE: DATE: Qj Z -/ The contractor hereby accepts this adjustmen der the term• •f Section1-04.4'of the original contract. RECOMMENDED BY; DATE: D '//'• !:3 Project a g APPROVED BY: ` r��i�— DATE: DS• Z.'/,f City Eng eer APPROVED BY: // iiJ'v DATE: 8(2/I� City Manager ll ATTACHMENTS: Plan Sheets 28&30, revised 8/17/18 Distribution: ORIGINAL TO: City of Spokane Valley Clerk's Office COPIES TO: Contractor,PW Project File,Project Inspector,Finance Department • COSV Form 9/5/2014