15-145.03 Award Construction: Pines & Grace Intersection Safety Project 'S 11-15.(Y5 n SP" ol ne %Bev J CHANGE ORDER NO: 3 ENGINEERING DIVISION CONSTRUCTION CONTRACT NO: 15-145 PROJECT: Pines(SR 27)and Grace Intersection Safety Project CONTRACT DATE: 5/9/2018 PRIME CONTRACTOR: Award Construction,Inc. CIP NO:' 166 DESCRIPTION OF CHANGES - This change order pays for pavement marking modifications in the Pinecroft Business Park parking lot adjacent to Pines Road. When the project widened Pines Road it removed a Spokane County sewer access driveway that allowed a Vac truck to clean out the existing sewer manhole located on the eastern edge of the Pinecroft Parking Lot. The City obtained a utility access easement so the County could access the sewer manhole through the Pinecroft parking lot. To ensure access,the area adjacent to the sewer manhole cannot be used for parking and yellow cross hatching was painted in this area. Pinecroft notified the City after the pavement marking was applied that the Business Park does not use yellow for pavement marking and requested white striping be installed. Item No. Description Unit Quantity Unit Price Total CO-3.1 Black Paint Line LF 245 $ 0.60 $ 147.00 CO-3.2 White Paint Line LF 369 $ 0.60 $ 221.40 CO-3.3 Re-mob and Prime Mark up LS 1 $ 324.21 $ 324.21 Total Amount of this Change Order(incl.Tax): $ 692.61 • VERBAL APPROVAL AND JUSTIFICATION Independent Justification on File Yes Verbal Approval NA_-_ 1 Verbal Approval by NA PHYSICAL COMPLETION Original Contract Working Days: 35 Revision By This Change Order. 1 Revisions by Prior Change Orders: 8 Total Revised Contract Working Days: 44 CONTRACT AMOUNT THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT: ORIGINAL TOTAL CONTRACT AMOUNT $ 608,893.50 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT $ 19,703.32 TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 628,596.82 NET THIS CHANGE ORDER $ 692.61 TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 629,289.43 CONTRACTOR ACCEPTANCE: / \)0 I DATE: "4 1 1 U it The contractor hereby accepts this adjusxnjTent under t e terms T.ection 1-04.4 of the original contract. RECOMMENDED BY: /-T�r� ' J/�/%/ DATE: ?'7, / S I ii.fr/i /r APPROVED BY: DATE: • ?!"la•<430 City E r • APPROVED BY: Alt 41. _ DATE: VI A/15 City Manager lull ATTACHMENTS: CO 2 Exhibit Distribution: ORIGINAL TO: City of Spokane Valley Clerk's Office COPIES TO: Contractor,PW Project File,Project Inspector,Finance Department COSV Form 915/2014