18-050.04 MDM Construction: Mission Ave Improvements Sp®kane
, . Valley' CHANGE ORDER NO: 4
ENGINEERING DIVISION CONSTRUCTION CONTRACT NO: 18-050,014
PROJECT: Mission Avenue Improvement Project CONTRACT DATE: 5/31/2018
PRIME CONTRACTOR: MDM Construction,Inc. CIP NO: 123
DESCRIPTION OF CHANGES -
This change order revises the barb wire fence replacement at 17803 E Mission Avenue from a WSDOT Wire Fence,Type 2
with 4 strands of barb wire to a modified WSDOT Wire Fence Type 1. The bottom of the Type 1 fence has 36 inches of
wire mesh. The Type 1 fence is modified so that the top will have two strands of plain wire instead of barb wire.
Item No. Description Unit Quantity Unit Price Total
Sch A 76 Wire Fence Type 2 LF -103 $ 25.00 $ (2,575.00)
CO-4.1 Wire Fence Type 1, Modified LF 444 $ 25.00 $ 11,100.00
Total Amount of this Change Order(incl.Tax): $ 8,525.00
VERBAL APPROVAL AND JUSTIFICATION
Independent Justification on File Yes
Verbal Approval Date Verbal Approval by__ Bill Helbi9
PHYSICAL COMPLETION .
Original Contract Working Days: 90 Revision By This Change Order: 0
Revisions by Prior Change Orders&
Minor Change Orders: 9 Total Revised Contract Working Days: 99
CONTRACT AMOUNT
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT:
ORIGINAL TOTAL CONTRACT AMOUNT $ 2,966,440.40
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT(through co#3) $ 44,624.75
TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 3,011,065.15
NET THIS CHANGE ORDER $ 8,525.00
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 3,019,590.15
CONTRACTOR ACCEPTANCE: DATE: /0 - .-/7,
The contractor hereby accepts this a•just /it unser t e ter !. o Section 1,04.4 of the original contract.
RECOMMENDED BY: / _ DATE: /0 •/ ' ./e6
.ject Manager
APPROVED BY: .///' DATE: /e'45
•��
/ity Engineer
APPROVED BY: �if/ A / ; DATE: 107:2Z/18
City Manager
ATTACHMENTS: 17803 Revised Fencing Exhibit
Distribution: ORIGINAL TO: City of Spokane Valley Clerk's Office
COPIES TO: Contractor,PW Project File,Project Inspector,Finance Department