Loading...
18-015.01 WM Winkler: Appleway Trail Sullivan to Corbin Spokane ,jValley CHANGE ORDER NO: 1 ENGINEERING CONSTRUCTION CONTRACT NO: 18-015.01 PROJECT: Appleway Trail CONTRACT DATE: 1/22/2018 PRIME CONTRACTOR: Wm. Winkler Company CIP NO: 237 DESCRIPTION OF CHANGES This change order pays to replace a luminaire pole and tree that was damaged by a third party. Item No. Description Unit Quantity Unit Price Total 189 Third Party Damage-Luminaire Replacement L.S. 1 $7,446.00 $7,446.00 190 Third Party Damage-Tree Replacement L.S. 1 $535.00 $535.00 Total Amount of this Change Order(incl.Tax): $7,981.00 PHYSICAL COMPLETION Original Contract Working Days: 75 _ Revision By This Change Order: _ 0 Revisions by Prior Change Orders: 0 Total Revised Contract Working Days: 75 CONTRACT AMOUNT THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT: ORIGINAL TOTAL CONTRACT AMOUNT $ 1,972,690.00 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT (through NIA) $ 0.00 TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 1,972,690.00 NET THIS CHANGE ORDER $ 7,981.00 TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 1,980,671.00 CONTRACTOR ACCEPTANCE: l DATE: 10-i 1-I The contractor hereby accepts this .•justment under th- terms of Section 1-04.4 of the original contract. RECOMMENDED BY: dirdoll b_ _ DATE: 1O/rZ 'ro<ject Managern APPROVED BY: 1v I DATE: /0//57/(1) Engin eying anager APPROVED BY: s/(/ L. DATE: 10/22/[ilf)City Manager ATTACHMENTS: Change Order Description Distribution: ORIGINAL TO: City of Spokane Valley Clerk's Office COPIES TO: Contractor,Project File, Project Inspector, Finance Department Spokane Change Order No: 1 Eley Construction Contract No: 18-015.01 THE CONTRACT IS MODIFIED AS FOLLOWS: WORK TO INCLUDE Background: A third party vehicle drove on the trail and ran into a luminaire pole at Sta 55+40 Lt. The pole was knocked over and destroyed beyond repair. The vehicle drove away through the landscaping area on the west side of Steen Road and snapped one of the trees in half. t 1 • Description of Change: Specification: There are no changes to the specification because of this change Plans: There are no changes to the plans because of this change Time: There are no changes to working days because of this change Measurement: There will be no specific measurement for lump sum items "Third Party Damage-Luminaire Replacement"and "Third Party Damage-Tree Replacement." Payment: Payment for new item#189"Third Party Damage-Luminaire Replacement" lump sum The lump sum Contract price for"Third Party Damage-Luminaire Replacement", shall be full payment for all Work to furnish, install and hookup one pedestrian luminaire pole. .., "T'okane Change Order No: 1 Valley Construction Contract No: 18-015.01 Payment for new item#190"Third Party Damage-Tree Replacement" lump sum The lump sum Contract price for"Third Party Damage-Tree Replacement", shall be full payment for all Work to remove the damaged tree and root ball, furnish, and plant one"Spire Cherry"tree. Summary of Quantities: Previous New Estim Bid Item Description UnitQty. Qty Qty Unit Price Amount Change 189 Third Party Damage-Luminaire L.S. 0 1 1 $7,446.00 $7,446.00 (NEW) Replacement 190 Third Party Damage-Tree L.S. 0 1 1 $535.00 $535.00 (NEW) Replacement TOTAL +$7,981.00