CHANGE ORDER NO: 1
ENGINEERING CONSTRUCTION CONTRACT NO: 18-015.01
PROJECT: Appleway Trail CONTRACT DATE: 1/22/2018
PRIME CONTRACTOR: Wm. Winkler Company CIP NO: 237
DESCRIPTION OF CHANGES
This change order pays to replace a luminaire pole and tree that was damaged by a third party.
Item No. Description Unit Quantity Unit Price Total
189 Third Party Damage-Luminaire Replacement L.S. 1 $7,446.00 $7,446.00
190 Third Party Damage-Tree Replacement L.S. 1 $535.00 $535.00
Total Amount of this Change Order(incl.Tax): $7,981.00
PHYSICAL COMPLETION
Original Contract Working Days: 75 _ Revision By This Change Order: _ 0
Revisions by Prior Change Orders: 0 Total Revised Contract Working Days: 75
CONTRACT AMOUNT
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT:
ORIGINAL TOTAL CONTRACT AMOUNT $ 1,972,690.00
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT (through NIA) $ 0.00
TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 1,972,690.00
NET THIS CHANGE ORDER $ 7,981.00
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 1,980,671.00
CONTRACTOR ACCEPTANCE: l DATE: 10-i 1-I
The contractor hereby accepts this .•justment under th- terms of Section 1-04.4 of the original contract.
RECOMMENDED BY: dirdoll b_ _ DATE: 1O/rZ
'ro<ject Managern
APPROVED BY: 1v I DATE: /0//57/(1)
Engin eying anager
APPROVED BY: s/(/ L. DATE: 10/22/[ilf)City Manager
ATTACHMENTS:
Change Order Description
Distribution:
ORIGINAL TO: City of Spokane Valley Clerk's Office
COPIES TO: Contractor,Project File, Project Inspector, Finance Department
Spokane
Change Order No: 1
Eley Construction Contract No: 18-015.01
THE CONTRACT IS MODIFIED AS FOLLOWS:
WORK TO INCLUDE
Background:
A third party vehicle drove on the trail and ran into a luminaire pole at Sta 55+40 Lt. The pole was knocked over
and destroyed beyond repair. The vehicle drove away through the landscaping area on the west side of Steen Road
and snapped one of the trees in half.
t 1
•
Description of Change:
Specification:
There are no changes to the specification because of this change
Plans:
There are no changes to the plans because of this change
Time:
There are no changes to working days because of this change
Measurement:
There will be no specific measurement for lump sum items "Third Party Damage-Luminaire Replacement"and
"Third Party Damage-Tree Replacement."
Payment:
Payment for new item#189"Third Party Damage-Luminaire Replacement" lump sum
The lump sum Contract price for"Third Party Damage-Luminaire Replacement", shall be full payment for all Work
to furnish, install and hookup one pedestrian luminaire pole.
..,
"T'okane
Change Order No: 1
Valley Construction Contract No: 18-015.01
Payment for new item#190"Third Party Damage-Tree Replacement" lump sum
The lump sum Contract price for"Third Party Damage-Tree Replacement", shall be full payment for all Work to
remove the damaged tree and root ball, furnish, and plant one"Spire Cherry"tree.
Summary of Quantities:
Previous New Estim
Bid Item Description UnitQty. Qty Qty Unit Price Amount
Change
189 Third Party Damage-Luminaire L.S. 0 1 1 $7,446.00 $7,446.00
(NEW) Replacement
190 Third Party Damage-Tree L.S. 0 1 1 $535.00 $535.00
(NEW) Replacement
TOTAL +$7,981.00