18-050.07 MDM Construction: Mission Ave Improvements (e-dsv.07 CHANGE ORDER NO: 7 ENGINEERING DIVISION CONSTRUCTION CONTRACT NO: 18-050 PROJECT: Mission Avenue Improvement Project CONTRACT DATE: 5/31/2018 PRIME CONTRACTOR: MDM Construction,Inc. CIP NO: 123 DESCRIPTION OF CHANGES This change order suspends work on the project due to winter weather beginning November 19,2018, provided: 1.All streets,sidewalks and driveways within the project area are completed;and 2.All residential patchbacks have been completed per Engineer's direction;and 3.All stormwater swales are functioning. The Contractor agrees to resume work on April 1,2019 with 5 working days remaining in the Contract. Total Amount of this Change Order(incl.Tax): $ 0.00 VERBAL APPROVAL AND JUSTIFICATION Independent Justification on File Yes Verbal Approval Date Verbal Approval by PHYSICAL COMPLETION Original Contract Working Days: 90 Revision By This Change Order. 0« Revisions by Prior Change Orders &Minor Change Orders: 16 Total Revised Contract Working Days: 106 CONTRACT AMOUNT THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT: ORIGINAL TOTAL CONTRACT AMOUNT ««. . $ 2,966,440.40 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT(through co es) $ 74,300.75 TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 3,040,741.15 NET THIS CHANGE ORDER «««««.«....d.......«.._..............«.« ..« ........................... $ 0.00 TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 3,040,741.15 CONTRACTOR ACCEPTANCE DATE: ,,& `S The contractor hereby accepts this adjus t under = to ',p_ of Section 1=04.4 of the original contract. RECOMMENDED BY: % Lc DATE: /7,/5--,l f3 Proj ct Ma ger / APPROVED BY: d%T/ DATE: 1!�/7I'/.6 City gineer APPROVED BY: 11$' I� A h , DATE: I k (�/ 1j City Manager 1 `6 ATTACHMENTS: Roto-Rooter Pumping Invoice Distribution: ORIGINAL TO: City of Spokane Valley Clerk's Office COPIES TO: Contractor,PW Project File,Project Inspector,Finance Department COSV Form 9/5/2014