19-074.01 WM Winkler: Wilbur Road Sidewalks 1/-07q. 0 )
sob
jay CHANGE ORDER NO: 1
ENGINEERING DIVISION CONSTRUCTION CONTRACT NO: 19-074
PROJECT: Wilbur Road Sidewalk CONTRACT DATE- 4/23/2019
PRIME CONTRACTOR: Wm.Winkler Company CIP NO: 278
DESCRIPTION OF CHANGES
11-day no-cost time extension for revised retaining wall design and construction.
Item No. Description Unit Quantity Unit Price Total
CO-11 $ $ 000
8.8%Sales Tax $ N/A
Total Amount of this Change Order(incl.Tax): $ 0 00
VERBAL APPROVAL AND JUSTIFICATION
Independent Justification on File No
Verbal Approval 5/30/2019 1 Verbal Approval by Glenn Ritter
Original Contract Working Days: 25 Revision By This Change Order. 11
Revisions by Prior Change Orders 0 Total Revised Contract Working Days: 36
CONTRACT AMOUNT
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT:
ORIGINAL TOTAL CONTRACT AMOUNT $ 371,52000
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT�m ",�, z�_a $ 0.00
TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 371,520 00
NET THIS CHANGE ORDER 0.00
. . .._..... ._...._....._..._...._....._._..._.....
TOTAL CONTRACT AMOUNT I[JCLUDING THIS CHANGE ORDER $ 371,520.00
CONTRACTOR ACCEPTANCE. —�� DATE:
The contractor hereby accepts this ande=Yie fdllns of Section 1-04.4 u(.Staodginal contract.
RECOMMENDED BY: - DATE 6-5-19
{� Prop APPROVED BY' /// ti er DATE:01) /
!'v
City Engine-
APPROVED BY: DATE.
City Manager
ATTACHMENTS
Distribution. ORIGINAL TO City of Spokane Valley Clerk's Office
COPIES TO Contractor, PW Project File, Project Inspector,Finance Department