19-128.01 LaRiviere: 2019 Stormwater Small Works stiokank
ValleY CHANGE ORDER NO: 1
ENGINEERING DIVISION CONSTRUCTION CONTRACT NO: 19-128.01
PROJECT:2019 STORM WATER SMALL WORKS CONTRACT DATE: 10/3/2019
PRIME CONTRACTOR:LA RIVIERE,INC. CIP NO: N/A
DESCRIPTION OF CHANGES
This change order creates a quantity reconciliation for the bid items listed below to reflect the actual quantities placed during construction.
Item No. Description Unit Quantity Unit Price Total
5(Sch A) QUANTITY RECONCILIATION-PORUS GRAVEL SHOULDER S.F. -368 $6.00 -$2,208.00
6(Sch A) QUANTITY RECONCILIATION-MISC GRADING INCL.HAUL C Y_ -33 $100.00 -$3,270.00
7(Sch A) QUANTITY RECONCILIATION-CRUSHED SURFACING BASE COURSE,2 IN.DEPTH S.F. 1,809 $3.00 $5,427.00
5(Sch B) QUANTITY RECONCILIATION-PORUS GRAVEL SHOULDER S.F. -356 $6.00 -$2,136.00
6(Sch B) QUANTITY RECONCILIATION-MISC GRADING INCL HAUL C.Y. 8 $125.00 $987.50
7(Sch B) QUANTITY RECONCILIATION-CRUSHED SURFACING BASE COURSE,2 IN.DEPTH S E 1,154 $3.00 $3,462 00
8.9%Sales Tax N/A
Total Amount of this Change Order(incl.Tax): $2,262.50
VERBAL APPROVAL AND JUSTIFICATION
Independent Justification on File Yes
Verbal Approval N/A Verbal Approval by N/A
PHYSICAL COMPLETION
Original Contract Working Days: 60 Revision By This Change Order: 0
Revisions by Prior Change Orders: 0 Total Revised Contract Working Days: 60
CONTRACT AMOUNT
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT:
ORIGINAL TOTAL CONTRACT AMOUNT $ 144,276.00
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT(None) $ 0 00
TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 144,276.00
NET THIS CHANGE ORDER $ 2,262.50
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 146,538 50
CONTRACTOR ACCEPTANCE: ` DATE: )I IO t//I9
The contractor hereby accepts this adjustment under the terms ctio 4.4 original contract.
RECOMMENDED BY: . `= DATE: /1 /C 7 / 19
z—
Project Manager
APPROVED BY: i DATE: 'A7 'l7
City Engineer
APPROVED BY. DATE:
City Manager
ATTACHMENTS:
Distribution ORIGINAL TO: City of Spokane Valley Clerk's Office
COPIES TO: Contractor,PW Project File,Project Inspector,Finance Department