2014, 05-06 Permit SW-14000583 SewerSPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW-14000583
Permit Issued Date: 05/06/2014
Expiration Date: 05/06/2015
Project Description:
Project Name:
Primary Contact:
Phone:
SEWER CONNECTION
GREEN HAVEN
TERRA UNDERGROUND LLC
208-659-5894
Applicant:
Address:
Phone:
Email:
TERRA UNDERGROUND LLC
PO BOX 2316
HAYDEN, ID 83835
208-659-5894
SITE INFORMATION:
Site Address:
Parcel Number:
18413 E COWLEY AVE
55184.0908
Owner:
Address:
Phone:
Assessor's Description: CORBIN ADD GRNACRS PT OF B9-11 BEG 247FT Email:
S OF NL OF L2 B9&524FT E OF WL B11 TH
W87.1FT TH S PAR TO WL B11 TO INT SLY LN
B11 TH ELY ALG SL TO PT S OF POB TH N TO
POB EXC SLY 5FT
Inspection Area: : (509)-477-3675
Water District: Consolidated Irrigation
District #19
Zoning:
BOELKE, GARY L
18413 E COWLEY AVE
SPOKANE VALLEY, WA 99016
509-863-8030
Fire District: Spokane Valley Fire
Land Area: 17906 Square Feet
CONTRACTOR INFORMATION.
TERRAUL894DJ, Exp. 03/10/2015
TERRA UNDERGROUND LLC
PO BOX 2316 HAYDEN, ID 83835
208-659-5894
DETAILS:
Class
SEWER
Type
Quantity Unit Charge Value
FEE DETAIL:
Processing - Utilities
Utilities Permit
SEWER CONNECTION
Total Fee:
$26.64
$125.00
$151.64
1 $125.00 $125.00
$125.00
CONDITIONS:
Inside Public Transit Benefit Area
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
CALL 1-800-424-5555 BEFORE YOU DIG —AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
SEWER PERMITS ARE VALID FOR ONE (1) YEAR FROM THE DATE OF ISSUANCE. FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY-FRIDAY PRIOR TO COVER. ONE WORKING DAY NOTICE REQUIRED. PERMIT
ALLOWS FOR A 30-MINUTE INSPECTION. ADDITIONAL INSPECTION FEES APPLY AFTER 30 MINUTES.
Date Printed: 05/06/2014 15:36:17 Project Coordinator: Julie Shatto
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW-14000583 Permit Issued Date: 05/06/2014
Expiration Date: 05/06/2015
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 05/06/2014 15:36:17 Project Coordinator: Julie Shatto