20-007.01 Wm Winkler: CenterPlace West Lawn Phase 2 2o.()a7 °I
Spokane
III Valley CHANGE ORDER NO: 1
ENGINEERING DIVISION CONSTRUCTION CONTRACT NO: 20-007
PROJECT: CenterPlace West Lawn-Phase It CONTRACT DATE: 1/15/2020
PRIME CONTRACTOR: Wm.Winkler CIP NO: 304
DESCRIPTION OF CHANGES
Install 3—Rain Water Leaders(RWL's)for new downspouts to be installed with upcoming CenterPlace roof replacement
project. Remove&replace existing damaged concrete curb and gutter, ADA ramps,sidewalk and driveway approach.
Item No. Description Unit Quantity Unit Price Total
ONSITE-SCHEDULE A
CO-1.1 Add Rain Water Leaders#1, 2 & 3 $ 9,456.60
8.9% Sales Tax $ 841.64
Subtotal Schedule A $ 10,298.24
STREET WORK-SCHEDULE B
CO-1.2 Remove/Replace Curb, Walk and Ramps (includes tax) $ 10,414.46
CO-1.4 Remove/Replace driveway approach (includes tax) $ 6,684.28
CO-1.6 Remove/Replace two sidewalk panels(includes tax) $ 505.58
Subtotal Schedule B $ 17,604.32
Total Amount of this Change Order(incl.Tax): $ 27,902.56
VERBAL.APPROVAL AND JUSTIFICATION
Independent Justification on File Yes
Verbal Approval 4/22/2020 Verbal Approval by Glenn Ritter
" PHYSICAL COMPLETION
Original Contract Working Days: 50 Revision By This Change Order: 4
Revisions by Prior Change Orders: 0 Total Revised Contract Working Days: 54
CONTRACT AMOUNT
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT:
ORIGINAL TOTAL CONTRACT AMOUNT $ 1,326,030.55
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT(through CCU $ 0.00
TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 1,326,030.55
NET THIS CHANGE ORDER $ 27,902.56
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 1,353,933.11
CONTRACTOR ACCEPTANCE: 2 .� /., . DATE: / ( 2 0
The contractor hereby accepts this adjustmen tin' er the terms of Section 1-04.4 of the original contract.
RECOMMENDED BY: r DATE: 5/7/20
Project M n or
APPROVED BY: `�L/ DATE: OS.'—‘ /Z ' Zr)
City Engineer
APPROVED BY: v���� DATE: 3.---/ - Z3ze,
City Manager
ATTACHMENTS: Change Proposals#1R1 and#2R1
Distribution: ORIGINAL TO: City of Spokane Valley Clerk's Office
COPIES TO: Contractor,PW Project File, Project Inspector, Finance Department
-.in;OP6/2014
Community& Public Works Department
SCITY pokane"\IMINIehEngineering Division
Valley 10210 E Sprague Ave ♦ Spokane Valley WA 99206
509.720.5075 0 Fax: 509.720.5075 ♦ cityhall®spokanevalley.org
Change Order Memorandum
Date: 5/7/20
To: Bill Helbig, City Engineer
•
From: Glenn Ritter, Senior Engineer,tie Through: Gloria Mantz, Engineering Manager
Re: Change Order#1 for CenterPlace West Lawn, CIP#0304
•
Budget Account No. 309.000.304.594.75.63.00 Wm.Winkler Co. Contract No. 20-007
This change order pays for the installation of Rain Water Leaders to downspouts planned with
the CenterPlace Roof Replaement Project#0305. It also pays for the removal and replacement
of the existing broken and damaged concrete curb and gutter, sidewalk, accessible ramps and
driveway approach. The total cost(including sales tax) for this Change Order work is
$27,902.56 paid for by City of Spokane Valley. There are sufficient funds in the project budget
to cover these costs. Due to the increased scope of work, we are also allowing an additional
four (4) working days to complete the contract.
Original Contract Amount: $1,326,030.55 •
Previous Change Order Cost: $0.00
Change Order#1 Cost: 27,902.56
Project Cost including Change Order#1: $1,353,933.11
City Engineer's Contract authority: $5,000.00
($5,000)
Change Order Cost to date: $0.00
Remaining City Engineer's Contract Authority after CO #1 $5,000.00
City Manager's Contract authority: $198,904.58
($200,000.00 or 15% of contract amount)
Change Order Cost to date: $27,902.56
Remaining City Manager's Contract Authority after CO #1 $171,002.02