2012, 09-07 Permit SW-12002151 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW-12002151
Permit Issued Date:
09/07/2012
Expiration Date:
Project Description: SEWER CONNECTION
Project Name: WHITE BIRCH
Permit Type: SEWER
Primary Contact: STOLZ INCORPORATED '
Applicant: STOLZ INCORPORATED
Address: 3808 S CHAPMAN RD
GREENACRES, WA 99016
Phone: 509-928-8621
Email:
SITE INFORMATION:
Site Address: 16915 E BROADWAY AVE Owner: KEOGH, JANYCE M
Parcel Number: 45131.0208 Address: 16915 E BROADWAY AVE
VERADALE, WA 99037
Subdivision: Phone:
Assessor's Description: VERA PT OF BLK 132 W1/2 EXC RD RNV Email:
Inspection Area:
Water District: Vera Fire District: Spokane Valley Fire
Irrigation District #15
Zoning: Land Area: 110567 Square Feet
CONTRACTOR INFORMATION:
General Contractor
STOLZI*053N8
STOLZ INCORPORATED
3808 S CHAPMAN RD
GREENACRES, WA 99016
509-928-8621
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
FEE DETAIL:
Processing - Utilities
Utilities Permit
Total Fee:
$125.00
$25.94
$125.00
$150.94
CONDITION$:
inside Public Transit Benefit Area
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
CALL 1-800-424-5555 BEFORE YOU DIG —AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
Date Printed: 09/07/2012 08:35:55
Printed by: IIS APPPOOLV+SP.NET v4.0
SPOKANE COUNTY BUILDING AND PLANNING
PERivil
Permit Issued Date:
Application Number: SW-12002151 09/07/2012
Expiration Date:
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY-FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30-MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 09/07/2012 08:35:55
Printed by: IIS APPPOOL ASP.NET v4.0