2012, 11-13 Permit SW-12002539 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW-12002539
Permit Issued Date:
11/13/2012
Expiration Date:
Project Description: SEWER CONNECTION Primary Contact: LUND ENTERPRISES, LLC
Project Name: GRANDVIEW ACRES Applicant: LUND ENTERPRISES, LLC
Permit Type: SEWER Address: 3619 N CEMENT RD
SPOKANE, WA 99206
Phone:
Email:
SITE INFORMATION:
Site Address:
Parcel Number:
3619 N CEMENT RD
45044.0501
Subdivision: GRANDVIEW ACRES
FIRST ADDITION
Assessor's Description: GRANDVIEW AC 1ST PT OF L1 B8 NLY 75FT OF
ELY 133FT
Inspection Area:
Owner:
Address:
Phone:
Email:
LUND ENTERPRISES, LLC
3619 N CEMENT RD
SPOKANE, WA 99206
Water District: Irvin Fire District: Spokane Valley Fire
Water District #6
Zoning: Land Area: 9999 Square Feet
CONTRACTOR INFORMATION:
Owner Acting As Builder
OWNER
OWNER PERFORMING THE WORK
SAME AS SITE ADDRESS
SAME, WA 00000
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
FEE DETAIL:
Processing - Utilities
Utilities Permit
Total Fee:
$125.00
$25.94
$125.00
$150.94
CONDITIONS:
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
Date Printed: 11/13/2012 11:31:15
Printed by: IIS APPPOOL\SmartGovProdApp
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW-12002539 11/13/2012
Expiration Date:
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY-FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30-MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Printed by: IIS APPPOOL\SmartGovProdAPP
Date Printed: 11/13/2012 11:31:15